Here’s a look at project closures for the weekend and the week ahead.  Significant closures are highlighted and complete closure lists via hyperlinks are available below.

As work continues on two new direct connector ramps being built as part of the I-10 Connect project, daytime and nighttime closures are scheduled at two locations next week.

Ramp N, which connects eastbound Loop 375 to northbound US 54, will be closed daily so crews can work on bridge railings and drilled shafts for a new direct connector which will connect traffic from eastbound Loop 375 to eastbound I-10.

Meantime, SH 20 (Alameda Avenue) will be subject to overnight closures next week at US 54 as crews place bridge deck panels for a new direct connector linking US 54 and I-10 to the Bridge of the Americas.

Links to complete list of closures: West Area Projects   |   I-10 Connect   |   East Area Projects

Mesa Park Interchange Project

Saturday, April 4

  1. a.m.-9 a.m.
  • Westbound off ramp closed
  • Crews will be striping

Border West Expressway

Wednesday, April 1- Wednesday, April 8 (weeknights only)

9pm – 5am (nightly)

  • Westbound and Eastbound Loop 375 main lanes from Paisano (Bowie High School) to Executive ramps.
  • Crews will be working on maintenance.

Transmountain Project

Monday, April 6 through Friday, April 10
7 a.m. to 4 p.m. (Shoulder closures)

  • Loop 375 east/westbound from Resler past Tom Mays Park Access Rd closed.
  • Crews will be working on excavating and compacting dirt median.

9 a.m. to 4 p.m. (Alternate lane and shoulder closures)

  • Loop 375 east/westbound from Resler past Tom Mays Park Access Rd closed.
  • Crews will be striping, placing concrete barriers and hot mix asphaltic concrete.

Monday, April 6 through Friday, April 10
Nightly, from 9 p.m. to 5 a.m.

  • Full closure Loop 375 westbound from Resler to US-54.
  • Detour – US-54 South and I-10 West. After placement of the concrete barriers, westbound traffic will remain in one lane.
  • Crews will be striping and placing concrete barriers.

I-10 Ramp Improvements – Phase 2

Monday, April 6 through Friday, April 10
9 a.m. to 4 p.m.

  • I-10 at Airway turnarounds closed in both directions.
  • I-10 at Airway underpass southbound right lane closed.
  • I-10 at Viscount/Hunter turnarounds closed in both directions.
  • Shoulder work along Gateway Blvd East from Hunter to Benson.
  • Crews will be working on traffic signals.
  • I-10 at Gateway Blvd East from Eastside to Hawkins right lane closed.
  • Crews will be working on an inlet.
  • Gateway Blvd West alternate lane closures from Hawkins to Airway.

Monday, April 6 through Friday, April 10
Nightly, from 9 p.m. until 6 a.m.

  • I-10 eastbound from Hawkins to Hunter/Viscount full closure.
  • Detour – exit Hawkins and re-enter at McRae.
  • Crews will be striping I-10 eastbound.
  • Airway southbound alternate lane closure to Gateway Blvd West.
  • Detour – Left at Viscount or right at International.
  • Gateway Blvd West alternate lane closure from Hawkins to Airway.
  • Detour – North on Hawkins, right at Viscount to Airway.
  • Crews will be striping.

Maintenance

Monday, April 6 through Friday, April 10
8 a.m. to 3 p.m.

  • I-10 westbound between Airways and Downtown left lane closed.
  • I-10 eastbound between Schuster and Robert E. Lee left lane closed.
  • Crews will be working on shoulder work.
  • Border Hwy Loop 375 westbound between Schuster and Executive right lane closed.
  • Crews will be cleaning drains.
  • Border Hwy Loop 375 eastbound between US-54 and Fonseca left lane closed.
  • Crews will be working on the concrete barrier wall and left shoulder going westbound.
  • Alternating lane closures on Mesa from Schuster to Montana.
  • Crews will be working on asphalt repairs.

I-10 Riprap Project

Monday, April 6 through Friday, April 10
9 a.m. to 4 p.m.

  • I-10 eastbound CD/ML right lane closed between Top Golf and Executive.
  • Eastbound CD entrance ramp to I-10 eastbound closed.
  • I-10 westbound CD right lane closed between Resler and Mesa.
  • Crews will be placing rock, concrete riprap, and grading slopes.

Guardrail Repair Project

Monday, April 6
9 a.m. to 4 p.m.

  • I-10 eastbound from Schuster to Porfirio Diaz right lane closed with complete off-ramp closed at Porfirio Diaz.
  • Crews will be repairing guardrail.

Tuesday, April 7
9 a.m. to 4 p.m.

  • Center lane closed at Missouri from Stevens to Cotton and right lane closed on Cotton from Wyoming to Gateway Blvd East intersection.
  • Crews will be repairing guardrail.

Wednesday, April 8
9 a.m. to 4 p.m.

  • Loop 375 eastbound from Plexxar to Tom Mays Park right lane closed.
  • Crews will be repairing guardrail.

Thursday, April 9
9 a.m. to 4 p.m.

  • I-10 eastbound from Mesa to Sunland Park right lane closed.
  • Crews will be repairing guardrail.

Friday, April 10
9 a.m. to 4 p.m.

  • I-10 eastbound from Mesa to Sunland Park left lane closed.
  • Crews will be repairing guardrail.

I-10 Landscape Improvements

Monday, April 6 through Friday, May 1
Daily, from 9 a.m. until 4 p.m. and continuous until further notice

  • I-10 alternating eastbound and westbound left and right lane closures between Eastlake Boulevard and Horizon Boulevard
  • I-10 alternating eastbound and westbound entrance and exit ramps to include turnaround
  • Closure is necessary for construction of landscape improvements to include excavation, ground cover, modular block planters, concrete and maintenance

Monday, April 6, through Friday, April 10

Daily from 9am to 4pm

  • Ramp N which connects eastbound Loop 375 to northbound US 54 will be closed to all traffic.
  • DETOUR: Take Exit 59 (US 62/Paisano Drive/Cole Street), turn right on Gateway Boulevard North.

Crews will be working on bridge railings and drilled shafts

Wednesday, April 8, and Thursday, April 9

Nightly from 9pm to 5am

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54.

 

Crews will be placing overhead bridge deck panels.

 

The following long-term closures will continue without interruption:

  • Ramps F and G, which connect I-10 to Juárez at the Spaghetti Bowl, remain detoured through northbound US 54 to Pershing Drive until further notice.
  • Interstate 110, the short freeway spur leading to and from the Bridge of the Americas, remains closed to northbound traffic until further notice.
  • The ramp from southbound US 54 to US 62 (Paisano Drive) remains closed until further notice.
  • Both turnarounds under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Intermittent closures on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Intermittent closures will be in place on Gateway Boulevard West between Boone Street and Palm Street.
  • Intermittent closures will be in place on Durazno Avenue, Rosa Avenue and Uva Street.
  • Intermittent lane closures will be in place on US 54 between Loop 375 and Spur 601.
  • Intermittent lane closures will be in place on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Lane closures will be in place on eastbound and westbound SH 20 (Alameda Avenue) at US 54 until further notice.
  • Lane closures will be in place on eastbound and westbound US 62 (Paisano Drive) between I-110 and US 54 until further notice.
  • Lane closures will be in place on Ramp D, which connects southbound US 54 to eastbound I-10 until further notice.
  • Lane closures will be in place on Ramp H, which connects eastbound I-10 to northbound US 54, until further notice.

Onramp and offramp closures may begin up to one hour earlier than stated times. All information is subject to change based upon weather and field conditions.

Staff Report

Staff Reports are just that, Staff Reporting the news. No skew, no opinion just the news. We pride ourselves on making sure that we bring you the news as soon as it is published, submitted or sent to us. No need to have a reporter rewrite or give their opinion. The facts or information, nothing more.