Crews with the Go10 Project continue working night and day to get the roadways built, and this shortened week is no different. Below are the closures and maps for work this week.
I-10 & Sunland
Daytime
Tuesday, May 30 through Friday, June 2 – 9 a.m. to 4 p.m. each day
The left lane on I-10 in both directions will close between Buena Vista and Sunland Park.
Crews are constructing new bridge columns in the area. [Map 1]
Overnight
Tuesday, May 30 and Wednesday, May 31 – 9 p.m. each night to 6 a.m. each morning
I-10 in both directions will close completely at the Sunland Park Exit (Exit 13).
Detour: Traffic will be detoured onto the ramps alongside I-10. Follow detour signs in place.
Crews will be setting beams for the new turnaround lanes at the Sunland Park Overpass. [Map 2]
Overnight
Thursday, June 1 – 9 p.m. to 6 a.m. the next morning
I-10 Westbound will close completely at the Sunland Park Exit (Exit 13).
The Sunland Park Entrance Ramp to I-10 Westbound will close.
Detour: I-10 Westbound traffic will exit at Sunland Park (Exit 13), take North Mesa Street (SH 20) to the North Mesa/I-10 interchange where traffic may enter I-10 Westbound.
Crews will be setting beams for the new turnaround lanes at the Sunland Park Overpass. [Map 3]