Here’s a look at the project closures for the week ahead. The complete closure lists via hyperlinks are at the bottom of this article.
Last week, GO 10 announced crews were targeting January 28th to close the Resler westbound exit ramp (Exit 12). A firm date of Tuesday, Jan. 29th is now set to close the Resler exit.
By the morning of Wednesday, January 30th, motorists can expect to have no access to the Resler westbound exit ramp (Exit 12) for approximately three months.
The ramp closure is necessary while crews finish building the westbound collector-distributor (CD) lanes, shaded red in the artistic rendering. When the new Resler exit (Exit 12) is open, it will be accessible from the new CD lanes, as shown, not from the main lanes of I-10.
While the Resler westbound exit ramp is closed, drivers are encouraged to use the Sunland Park westbound exit ramp (Exit 13). The North Mesa westbound exit ramp (Exit 11) will also be an option for exiting drivers; however, pavement work is taking place near the North Mesa exit ramp and may result in delays for westbound exiting vehicles.
At I-10 Eastbound and Sunland Park, crews are targeting the night of Sunday, Feb. 3rd to close the existing eastbound Sunland Park exit ramp (Exit 13). Motorists can expect the new and permanent eastbound Sunland Park exit ramp (Exit 13) to be open by the morning of Monday, Feb. 4th.
Similar to Resler’s westbound exit ramp, the new Sunland Park eastbound exit ramp will be accessible to motorists from the CD lanes, as shown below in the artistic rendering. Motorists should follow the overhead exit signs to access the new Sunland Park exit ramp (Exit 13).
Traffic Changes:
GO10
- A firm date of Jan. 29 is now set to close the Resler westbound exit ramp (Exit 12). By the morning of Wednesday, Jan. 30, motorists can expect to have no access to the Resler westbound exit ramp for approximately three months.
- At I-10 eastbound and Sunland Park, crews are targeting the night of Feb. 3 to close the existing eastbound Sunland Park exit ramp (Exit 13). Motorists can expect the permanent eastbound Sunland Park exit ramp (Exit 13) to be open by the morning of Feb. 4.
Alameda Reconstruction Project
- Tuesday, Jan. 29 (closure until further notice) – Alameda Avenue (SH 20) traffic will be channelized to a single lane in each direction, utilizing the newly constructed SH 20 westbound lanes west of Presa Place and Walmart Supercenter intersection. Closures are necessary for construction of proposed concrete paving of eastbound travel lanes, outside curb intersections, sidewalk along the Franklin canal and final striping.
Maintenance
Monday, Jan. 28 through Friday, Feb. 1
9 a.m. to 3 p.m. (throughout the day)
- Right lane closure on I-10 West between Airway and Geronimo
- I-10 westbound Airway entrance ramp will be closed
- I-10 westbound Geronimo exit ramp will be closed
- Complete closure on Bomarc between Woodrow Bean east and west
US 54 Widening and Illumination Project
Saturday, Jan. 26
6 a.m. to 5 p.m. (11 hours)
- Complete closure on US 54 northbound between Diana and Sun Valley and southbound between Sun Valley and Diana
- Crews will be installing overhead sign bridge
- Detour: Northbound traffic will need to exit at the Transmountain exit ramp and re-enter at the Transmountain entrance ramp
- Detour: Southbound traffic will need to exit at the Transmountain exit ramp and re-enter at the Transmountain entrance ramp
Monday, Jan. 28 through Thursday, Jan. 31
9 p.m. to 5 a.m. (nightly)
- Complete closure on US 54 northbound between Hondo Pass to Sean Haggerty
- Crews will be restriping and moving barrier walls
Saturday, Feb. 2 through Sunday, Feb. 3
5 a.m. to 3 a.m. (22 hours)
- Complete closure on US 54 north and southbound between Hondo Pass to Sun Valley
- Crews will be installing overhead sign bridge
- Detour: Northbound traffic will need to exit at the Transmountain exit ramp and stay on the frontage road
- Detour: Southbound traffic will need to stay on the frontage road and will need to enter US 54 at the Transmountain entrance ramp
El Paso Water Utilities Project
Sunday, Jan. 27 into Monday, Jan. 28
3 a.m. to 6 a.m. (27-hour closure)
- Complete closure on I-10 westbound at Mesa
- Complete closure I-10 eastbound at Downtown
- Crews will be installing a water line and chain link fence in the area.
Links to full lists of closures:
West Area Projects | GO10 | Border West Expressway | East Area Projects
LOCATION | DURATION | DESCRIPTION | |||
North Mesa
|
Overnight
Jan. 28 9 pm to 6 am the next morning
|
· The North Mesa exit ramp (Exit 11) from I-10 Eastbound will be open; however, motorists will only be able to turn right at the North Mesa Street (SH 20) signalized intersection.
· North Mesa Street (SH 20) in the eastbound direction will close between Osborne Drive and Remcon Circle. · North Mesa Street (SH 20) in the westbound direction will close between Bartlett Drive and South Desert Boulevard. · The North Mesa exit ramp (Exit 11) from I-10 Westbound will close.
|
|||
I-10 and Sunland | Overnight
Jan. 29-31 9 pm each night to 6 am each morning
|
Resler exit to close: Crews plan to close the Resler exit ramp (Exit 12) on the night of Jan 29. It will stay closed for approximately three months.
· I-10 Westbound will close completely between Sunland Park (Exit 13) and the North Mesa overpass. · The Sunland Park entrance ramp to I-10 Westbound will close. · The Sunland Park exit ramp (Exit 13) from I-10 Eastbound will close. · Sunland Park Drive in the westbound direction will close between the mall signalized intersection and Machuca Road. · The Resler flyover entrance ramp to I-10 Eastbound will close.
Detour: Motorists on I-10 Westbound will exit at Sunland Park Drive (Exit 13), follow Sunland Park Drive to North Mesa Street (SH 20), then re-enter I-10 Westbound using the North Mesa entrance ramp.
ATTENTION – Resler exit to close: By the morning of Jan. 30 and for approximately three months, motorists will have NO access to the westbound Resler exit ramp (Exit 12). Motorists are encouraged to use the westbound Sunland Park exit (Exit 13) while the Resler exit is closed. The North Mesa exit (Exit 11) will also be open; however, pavement work is taking place near the North Mesa exit ramp and may cause delays for exiting traffic.
|
|||
I-10 at North Mesa
|
Overnight
Feb. 3-7 9 pm each night to 6 am each morning
Note: If this work activity is delayed, such as due to weather, then it will occur later in the week of Feb. 3. |
MILESTONE – Sunland eastbound exit to be relocated permanently: By the morning of Feb. 4, motorists on I-10 Eastbound should expect the existing Sunland Park exit ramp (Exit 13) to be permanently closed and permanently relocated and accessible from the eastbound CD lanes.
· I-10 Eastbound will close completely between the North Mesa exit (Exit 11) and the Sunland Park overpass. · The Resler flyover entrance ramp to I-10 Eastbound will close. · The North Mesa entrance ramp to I-10 Eastbound will close. · The North Mesa exit ramp (Exit 11) from I-10 Westbound will close.
Detour: Motorists on I-10 Eastbound will exit at North Mesa (Exit 11), follow North Mesa Street (SH 20) to Doniphan Drive, then follow Doniphan Drive to Sunland Park Drive. Motorists may re-enter I-10 Eastbound using the Sunland Park entrance ramp.
|
|||
North Mesa
|
27 HOURS
Sunday, Feb. 17 at 3 am to Monday, Feb. 18 at 6 am
Note: If this work activity is canceled, such as due to weather, then it will be re-scheduled for Feb. 24-25.
|
MILESTONE – Mesa pavement work to be completed: Crews are targeting Feb. 17 to be finished with pavement work on North Mesa Street between Osborne Drive and Remcon Circle. Lanes will be in their final configuration and driveways to businesses will be restored.