Next week, nighttime work and closures continue at I-10/North Mesa and I-10/Sunland Park.
The next 27-hour closure is scheduled for Sunday, Dec. 9 at Sunland Park with the goal of opening more lanes on the Sunland Park Drive main overpass.
All closures are subject to change or cancelation due to weather. Updates are posted on the GO 10 website, Twitter, and Facebook.
GO10
North Mesa
Overnight
Sunday, December 2 through Thursday, December 6
8 p.m. each night to 6 a.m. each morning
- North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.
- All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close.
- South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).
- McClintock Drive access to South Desert Boulevard will close.
- Crews will be installing concrete pavement at the I-10/North Mesa intersections.
I-10 West at Sunland
Overnight
Sunday, December 2 through Thursday, December 6
9 p.m. each night to 6 a.m. each morning
- I-10 westbound will close at the Sunland Park exit ramp (Exit 13).
- Sunland Park Direct Connect closed – Utilize Paisano EBFR to access I-10
- Detour: Motorists on I-10 westbound will exit at Sunland Park and immediately re-enter I-10 at the next ramp.
- Crews will be demolishing concrete pavement in the median of I-10 and hauling the debris away.
Sunland Park
27 HOURS
Sunday, December 9 at 3 a.m. until Monday, December 10 at 6 a.m.
- Sunland Park Drive will close in both directions between Machuca Road and the mall signalized intersection.
- All Sunland Park exit ramps and entrance ramps at I-10 will close.
- Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273).
- The Racetrack Drive entrance ramp to westbound Paisano Drive (US 85) will close.
- LANE PATTERN CHANGE: The goal is to open more traffic lanes on the Sunland Park Drive middle overpass.
- WEATHER NOTE: This work activity is dependent on weather temperatures and, therefore, is subject to change.
Border West Expressway
Executive Center Blvd.
Saturday, December 8 to Sunday, December 9
6 a.m. to 10 p.m. (Continuous full closure)
- Westbound and eastbound from I-10 to US 85
- Closure is needed for roadway work
US 85
Saturday, December 1 to Sunday, December 2
4 a.m. to 6 p.m. (Continuous full closure)
- Westbound and eastbound from Spur 1966 to San Francisco St.
- Closure is needed for bridge work
Monday, December 3 to Thursday, December 6
9 p.m. to 5 a.m. (nightly full closure)
- Westbound and eastbound from Spur 1966 to San Francisco St.
- Closure is needed for bridge work
Mesa Park Interchange Project
Executive
Friday, Dec. 7 through Monday, Dec. 10
8 p.m. to 6 a.m. (continuous closure)
- I-10 eastbound Executive entrance ramp will be closed
- Monday, Dec. 10 during the morning hours traffic will enter I-10 eastbound under a temporary ramp, while the old adjacent entrance ramp undergoes construction
- Traffic Signal outage to occur on Saturday morning between 6 a.m. to 9 a.m.
- To avoid congestion in the area, traffic should seek alternate routes through Schuster or Downtown entrance ramps.
Alameda Pedestrian Improvements Project
Monday, Dec. 3 (until further notice)
7 a.m. to 4 p.m.
- Right lane closure along Alameda Avenue (SH 20) between Flicker Way and Delta Drive
- Closure is necessary for proposed construction of extending existing box culvert, RCP (reinforced concrete pipe) culvert, pedestrian and driveway improvements
- Crews will be placing portable traffic control barrier and delineators
Alameda Reconstruction Project
Monday, Dec. 3 through Friday, Dec. 21
8 p.m. to 5 a.m. and 9 a.m. to 3 p.m.
- Alameda Avenue (SH 20) eastbound and westbound alternating lane closures between Padres Drive and Loop 375
- Crews will be removing existing striping and install new striping
Monday, Dec. 3 through Friday, Dec. 21
8 a.m. to 3 p.m. and 8 p.m. to 5 a.m.
- Alternating westbound lane closures between Alameda Avenue (SH 20) and Presa Place
- Crews will be installing water main placement
Night Work
Thursday, Dec. 6
9 p.m. to 3 a.m. (one night only)
- Right lane closure on I-10 westbound between the Dallas exit ramp to the Mesa exit ramp
- Westbound Dallas entrance ramp will be closed
- Westbound Mesa exit ramp will be closed
Maintenance
Monday, Dec. 3 through Friday, Dec. 7
9 a.m. to 3 p.m. (throughout the day)
- Alternate lane closures on I-10 east and westbound between Stateline to Redd Road
- Right lane closure on South Desert Boulevard between Thorn Avenue to Graphite Drive
- Left lane closure on North Desert Boulevard between Artcraft to Transmountain
- Northbound Artcraft entrance ramp to I-10 will be closed
- Eastbound Global Reach exit ramp on Spur 601 will be closed
- Alternate lane closures on Bomarc north and southbound between Gateway Boulevard East and Gateway Boulevard West, crews will be working under the overpass.
Guardrail Repair Project
Thursday, Nov. 29
9 a.m. to 3 p.m. (throughout the day)
- Right lane closure on US 54 northbound between the Ellerthorpe entrance ramp to the Hondo Pass exit ramp
- Northbound Ellerthorpe entrance ramp will be closed
Friday, Nov. 30
9 a.m. to 3 p.m. (throughout the day)
- Left lane closure on Gateway Boulevard East between at the Copia intersection to Raynolds
Monday, Dec. 3
9 a.m. to 3 p.m. (throughout the day)
- Left lane closure on Transmountain (Loop 375) eastbound between the Paseo del Norte entrance ramp to the Main Gap
Tuesday, Dec. 4
9 a.m. to 3 p.m. (throughout the day)
- Alternate lane closure on Gateway Boulevard West between Airway Boulevard to Geronimo Boulevard
- Robert E. Lee will be closed in the area
Wednesday, Dec. 5
9 a.m. to 3 p.m. (throughout the day)
- Right lane closure on Ramp K (US 54 south to I-10 west) southbound between the Montana exit ramp to the Piedras exit ramp
- Westbound Piedras exit ramp will be closed
Thursday, Dec. 6
9 a.m. to 3 p.m. (throughout the day)
- Right lane closure on US 54 southbound between the Dyer exit ramp to the Spur 601 exit ramp
- Southbound Ellerthorpe exit ramp will be closed
- Southbound Spur 601 exit ramp will be closed
- Alternate lane closure on Wyoming eastbound between Mesa Street and Kansas Street
Links to full lists of closures:
West Area Projects | GO10 | Border West Expressway | East Area Projects
LOCATION | DURATION | DESCRIPTION |
North Mesa
|
Overnight
Dec. 2-6 8 pm each night to 6 am each morning
|
· North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.
· All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close. · South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20). · McClintock Drive access to South Desert Boulevard will close.
Crews will be installing concrete pavement at the I-10/North Mesa intersections.
|
I-10 West at Sunland
|
Overnight
Dec. 2-6 9 pm each night to 6 am each morning
|
· I-10 Westbound will close at the Sunland Park exit ramp (Exit 13).
· The Sunland Park flyover entrance ramp to I-10 Eastbound will close.
Detour: Motorists on I-10 Westbound will exit at Sunland Park and immediately re-enter I-10 at the next ramp.
Crews will be demolishing concrete pavement in the median of I-10 and hauling away debris.
|
Sunland Park
|
27 HOURS
Dec. 9 at 3 am until Dec. 10 at 6 am
|
· Sunland Park Drive will close in both directions between Machuca Road and the mall signalized intersection.
· All Sunland Park exit ramps and entrance ramps at I-10 will close. · Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273). · The Racetrack Drive entrance ramp to westbound Paisano Drive (US 85) will close.
LANE PATTERN CHANGE: The goal is to open more traffic lanes on the Sunland Park Drive middle overpass.
WEATHER NOTE: This work activity is dependent on weather, therefore, is subject to change.
|