• January 27, 2022
 I-10 Connect Closures for January 2-8 2022

Photo courtesy TxDOT

I-10 Connect Closures for January 2-8 2022

I-10 Closures – Next week, I-10 East will be closed overnight Tuesday through Thursday nights so crews can restripe the area beneath the spaghetti bowl.

Starts at 9PM, weather permitting. The detour will loop you up 54 to Pershing turnaround, and back down to I-10 East.

Also: daytime Monday through Thursday, crews will be working on bridge joint repair on ramps connecting to Loop 375 westbound and from US 54 south and from Paisano to Loop 375 eastbound. That’s 9AM – 4PM, so it should not affect rush hour traffic.

Expect daytime closures around Gateway East and Copia as needed, as well as over on Paisano as crews finish up in those areas, anytime between 7AM and 5PM, Monday through Saturday. The other closure of note will be the truck lanes on I-110 southbound Monday through Saturday while crews work on the ornamental fence. That just means trucks will be mixed in with traffic during the day, when it’s usually not so busy.

Have a great and safe New Year’s Eve, please.

I-10 Connect Closures

Tuesday 1/4/22 through Thursday 1/6/22 9pm-5am

  • Full closure of I-10 East at ramp H to Raynolds exit

Detour traffic over ramp H to Pershing U-turn, to US 54 South to ramp D back to I-10 East (map not included)

Monday, January 3, through Thursday, January 6, 9am to 4pm

  • A full closure of Ramp P, which connects US 54 southbound to Loop 375 westbound, will be in place.
  • A full closure of Ramp Y, which connects US 62 to Loop 375 eastbound, will be in place.

Monday, January 3, through Saturday, January 8, 7am to 5pm

  • A full closure of Gateway East, from entrance ramp to Marr Street, will be in place (as needed). DETOUR: Traffic should use Raynolds Street to access Gateway East.
  • A full closure of the I-10 eastbound entrance ramp at Copia Street will be in place (as needed). DETOUR: Traffic should proceed onto Durazno Avenue and use Raynolds Street to access Gateway East.
  • A closure of the right lane of Paisano Drive eastbound from San Marcial Street to Gateway South (as needed).
  • A closure of the right lane of Paisano Drive westbound from Gateway South to San Marcial Street (as needed).

Monday, January 3, through Saturday, January 8, 8am to 5pm

  • A full closure of truck lanes on I-110 southbound (as needed).

Crews will be working on ornamental fencing

Tuesday, January 4, and Wednesday, January 5, 9am to 4pm

  • A closure of the right shoulder of I-10 eastbound at Raynolds Street and Ramp D, which connects US 54 southbound to I-10 eastbound.

Wednesday, January 5, through Saturday, January 22, 24/7

  • A full closure of the US 54 southbound entrance ramp CD lanes from Cassidy Drive. DETOUR: Traffic should proceed over Pershing Drive, then enter US 54 southbound CD lanes.

Ongoing

  • Intermittent lane closures on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive), as needed.
  • Intermittent lane closures on Gateway Boulevard West between US 54 and Palm Street, as needed.
  • Shoulder work on US 54 from I-10 to Cassidy, as needed.
  • Intermittent closures on Durazno Avenue, Rosa Avenue and Uva Street. DETOUR: Traffic should use Durazno Avenue, Bowie Street and Rosa Avenue.

WEST AREA OFFICE PROJECTS

Transmountain Project

Daily until further notice.

  • Transmountain (Loop 375) east and westbound between US-54 and Tom Mays State Park alternate lane closures including shoulders.  Bike lane closed.

Crews will be working on cable barrier and mow strip.

  • Transmountain east and westbound between Resler and Summit inside shoulders closed.

Crews will be working on median drainage riprap.

  • Transmountain (Loop 375) east and westbound between mile markers 14 and 18 inside shoulders closed.

Crews will be working on median drainage, removing temporary pavement markings, and placing permanent pavement markings.  This work will be conducted under moving operations.

 

Mesa Rehabilitation Project

Monday, Jan. 3 through Friday, Jan. 7

9 a.m. to 4 p.m.

  • Mesa north and southbound between Sunland Park and Baltimore mobile operation alternate lane closures.

Crews will be striping.

 

US-54 Ramp Modification Project

Continuous until further notice.

  • Gateway North between Kenworthy and Golden Sands reduced to two lanes.

Crews will be working on US-54 northbound exit ramp reconfiguration.

Tuesday, Jan. 4

9 a.m. to 4 p.m.

  • Gateway North between Golden Sands and Sean Haggerty left lane closed.

Crews will be working on concrete demolition.

Wednesday, Jan. 5 and Thursday, Jan. 6

9 a.m. to 4 p.m.

  • US-54 northbound at Kenworthy exit ramp full freeway closure.
  • Transmountain northbound entrance ramp to US-54 closed.

Crews will be working on painting barrier wall.

 

 

Pedestrian Hybrid Beacons and Improvements Project

Monday, Jan. 3 through Friday, Jan. 7

9 a.m. to 4 p.m.

  • Mesa north and southbound between Schuster and River reduced to one lane.

Crews will be working on demolition and concrete work.

 

Hazard Elimination and Safety Illumination Project

Monday, Jan. 3 through Friday, Jan. 7

9 a.m. to 4 p.m.

  • Vista Del Sol east and westbound between Zaragoza and Joe Battle left lane closed.
  • Martin Luther King north and southbound between Loma Clara and US-54 right lane closed.

Crews will be working on new illumination system.

Raised Median Project on Montana Avenue (US-62)

Monday, Jan. 3 through Friday, Jan. 7

9 a.m. to 4 p.m.

  • Montana east and westbound between Airway and Sam Moore left lane closed.

Crews will be working on raised median.

FM-1905 Rehabilitation Roadway Project

Continuous until further notice.

  • FM-1905 (Anthony) eastbound between SH-20 (Doniphan) and Wildcat lane closed.

Crews will be working on demolition and reconstruction improvements.

Concrete Rail Project

Continuous until further notice.

  • I-10 westbound between Schuster and Asarco bridge right lane closed.

Crews will be working on installing metal beam guard fence and concrete barrier.

  • I-10 eastbound between Asarco bridge and Schuster shoulder closed.

Crews will be working on concrete barrier.

Installation of Sidewalks, Raised Medians and Pedestrian Rail Project

(US-85, US-62, SL-478, BU-54A, Lee Trevino, & FM-2529)

Continuous until further notice.

  • FM-2529 McCombs north and southbound between Dyer and Sean Haggerty right lane closed.

Crews will be working on replacing concrete sidewalks and driveways.

  • Lee Trevino north and southbound between Vista Del Sol and Vista Lago left lane closed.

Crews will be working on installing a raised median.

Loop 375 (Border Highway) Wrong Way Driver Construction Project

Continuous until further notice.

  • Oregon southbound between Olivas V Aoy and 9th closed.
  • Detour to Mesa.
  • 9th east and westbound between Mesa and Oregon closed.
  • Loop 375 westbound between Madrid and Santa Fe right turn lane and shoulder closed.

Crews will be working on installing concrete median.

 

Guardrail Repair Project

Monday, Jan. 3

9 a.m. to 4 p.m.

  • I-10 westbound between Dallas and Downtown exit ramp right and left lanes closed.

Crews will be working on guardrails.

Tuesday, Jan. 4

9 a.m. to 4 p.m.

  • Loop 375 (Transmountain) westbound between Kenworthy and US-54 right lane closed.

Crews will be working on guardrails.

 

Wednesday, Jan. 5

9 a.m. to 4 p.m.

  • I-10 eastbound between Piedras and Copia center lane closed.
  • I-10 westbound between Artcraft and Transmountain median work.

Crews will be working on guardrails.

Thursday, Jan. 6

9 a.m. to 4 p.m.

  • I-10 westbound between Prospect and Porfirio Diaz right lane and exit ramp closed.

Crews will be working on guardrails.

Friday, Jan. 7

9 a.m. to 4 p.m.

  • Transmountain between North and South Desert turnaround closed.

Crews will be working on guardrails.

Maintenance

Monday, Jan. 3 through Friday, Jan. 7

9 a.m. to 3 p.m.

  • I-10 westbound at Executive exit ramp closed.

Crews will be installing signs.

  • US-54 southbound Pershing exit ramp closed.

Crews will be working on shoulder.

EAST AREA OFFICE PROJECTS

Loop 375 Frontage Road Project

Monday, Jan. 3 through Friday, Dec. 7 (be prepared to stop)

Daily, from 9 a.m. until 4 p.m. and continuous until further notice

  • South Americas Avenue (frontage road) southbound to northbound turnaround will be occasionally blocked between North Loop Drive and Union Pacific Railroad (UPRR) tracks
  • South Americas Avenue southbound to northbound traffic will remain open and be flagged through work zone

Crews will be installing electrical conduit and hauling material

 

Loop 375 Widening Project

Monday, Jan. 3 (complete closure)

9 p.m. until 5 a.m. (overnight)

  • Loop 375 southbound complete lane closure between Pellicano Drive and Bob Hope Drive

Traffic will exit at Pellicano Drive and reenter at Bob Hope Drive

Crews will be placing concrete pavement

Continuous closure until further notice

  • S Americas Avenue northbound to southbound turnaround at Pan American Drive will be closed
  • S Americas Avenue southbound to northbound turnaround at Pan American Drive will be closed

Crews will be widening LP 375 main lane bridge structures

Continuous closure until further notice

  • S Americas Avenue northbound to southbound turnaround at Socorro Road will be closed
  • S Americas Avenue southbound to northbound turnaround at Socorro Road will be closed

Crews will be widening LP 375 main lane bridge structures

Continuous closure until further notice

  • S Americas Avenue northbound to southbound turnaround at North Loop Drive will be closed
  • S Americas Avenue southbound to northbound turnaround at North Loop Drive will be closed

Crews will be widening LP 375 main lane bridge structures

Continuous closure until further notice

  • S Americas Avenue southbound to northbound truck turnaround will be closed

Crews will be widening LP 375 main lane bridge structures

Continuous closure until further notice

  • S Americas Avenue northbound to southbound turnaround at Alameda Avenue will be closed

Crews will be widening LP 375 main lane bridge structures

Montana Frontage Road Project

Tuesday, Jan. 4 through Friday, Jan. 7

Daily, from 9 a.m. until 4 p.m.

  • Montana Avenue (US 62/180) westbound (frontage road) right lane closure between Loop 375 and Saul Kleinfeld Drive

Traffic traveling westbound on frontage road will merge to center or left lanes

Crews will be working on landscaping

Thursday, Jan. 6 through Friday, Jan. 7

Daily, from 6 a.m. until 2 p.m.

  • Montana Avenue (US 62/180) westbound (frontage road) left lane closure between Loop 375 and Lee Boulevard

Traffic traveling eastbound will merge to center or right lane

Crews will be hauling material

 

Thursday, Jan. 6 through Friday, Jan. 7

Daily, from 6 a.m. until 2 p.m.

  • Montana Avenue (US 62/180) eastbound left lane closure between Lee Boulevard and Loop 375

Traffic traveling eastbound will merge to center or right lane

Crews will be working on landscaping

 

Zaragoza Mill and Inlay Project

Monday, Jan. 3 through Friday, Jan. 7

Daily, from 9 a.m. until 4 p.m.

  • N Zaragoza Road (FM 659) northbound and southbound right shoulder closures between Pebble Hills Boulevard and Montana Avenue (US 62/180)

Crews will be ROW clearing and grading sidewalk

Monday, Jan. 3 through Thursday, Jan. 6

Nightly, from 9 p.m. until 5 a.m. (overnight)

  • N Zaragoza Road (FM 659) northbound and southbound left lane closures between North Loop Drive (FM 76) and Escobar Drive

Northbound and Southbound traffic will be reduced to one lane in work areas

Crews will be constructing center medians

Tuesday, Jan. 4 through Thursday, Jan. 6

Nightly, from 9 p.m. until 5 a.m. (overnight)

  • N Zaragoza Road (FM 659) southbound right lane closure between Sun Fire Boulevard and Charles R. Schulte Drive

Southbound traffic will be reduced to one lane on median

Crews will be resetting concrete barrier

Thursday, Jan. 6 through Friday, Jan. 7

Daily, from 9 a.m. until 4 p.m.

  • N Zaragoza Road (FM 659) northbound right lane closure between North Loop Drive (FM 76) and Escobar Drive

Northbound and Southbound traffic will be reduced to one lane in work areas

Crews will be hauling construction equipment

Guardrail Repair

Gateway East Boulevard at Eastlake

Monday January 3, 2022

9 a.m. to 4 p.m.

  • Gateway East Blvd Right Lane Closure from Eastlake to N. Moon Rd.
  • Gateway East Blvd Left Lanes will remain open.

Loop 375 southbound at Pellicano off ramp

Wednesday January 5, 2022

9 a.m. to 4 p.m.

  • SL375 Southbound Right Lane Closure from Vista Del Sol Blvd to Pellicano Dr.
  • SL375 Southbound at Pellicano Off Ramp Closure.
  • SL375 Southbound Left Lanes will remain open.

Loop 375 southbound at North Loop off ramp

Thursday January 6, 2022

9 a.m. to 4 p.m.

  • SL375 Southbound Right Lane Closure from IH10 to North Loop Dr.
  • SL375 Southbound at North Loop Off Ramp Closure.
  • SL375 Southbound Left Lanes will remain open.

Passing Lanes and Safety Treat Fixed Objects Project

Continuous until further notice

  • Montana Avenue (US 62/180) alternating eastbound and westbound left lane and right lane closures between RM 94 (Dell City) and RM 114 (Salt Flats)

Closure is necessary for roadway resurfacing and construction of two passing lanes

Median Concrete Barrier Project

Continuous until further notice

  • Montana Avenue (US 62/180) eastbound and westbound complete left lane closure between RM 124 and RM 126 (Guadalupe Peak)
  • Traffic will be reduced to one lane in work areas

Closure is necessary for installation of median concrete barrier

RM 652 Full Rehabilitation Project

Continuous until further notice

  • RM 652 westbound continuous left lane closure 8.36 miles east of FM 3541 to Reeves County Line
  • Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with a 14-foot lane width restriction

Closure is necessary for the construction of new roadway consisting of full depth rehabilitation

RM 652 Full Depth Rehabilitation Project

Continuous until further notice

  • RM 652 continuous left lane closure 5.4 miles east of Montana Avenue (US 62/180) to RM 1165/652
  • Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with 18-foot lane width restriction

Closure is necessary for the electric work, rock wall installation, RCP pipe and inlet

RM 652 Widening Project

Continuous until further notice

  • RM 652 continuous alternating eastbound and westbound left lane closures between RM 1165/652 and 0.91 mile west of FM 3541
  • Continuous two-way traffic, one-lane work zone requiring traffic to be alternating onto one lane and controlled by Temporary Traffic Signals with 14-foot lane width restriction

Closure is necessary for the construction of new roadway consisting of full depth rehabilitation

Deceleration Lane and Driveway Entrance

Continuous closure until further notice

  • Gateway East Boulevard (frontage road) right lane closure at Nuevo Hueco Tanks Boulevard

Closure is necessary for construction of new deceleration lane and driveway entrance to new Quick Pic

Continuous closure until further notice

  • Gateway West Boulevard (frontage road) right lane closure between Emerald Pass Avenue and Eastlake Boulevard

Closure is necessary for construction of deceleration lane and driveway entrance to new Amazon Building

Continuous closure until further notice

  • Joe Battle Boulevard northbound right lane closure between Pellicano Drive and 1430 Joe Battle Boulevard

Closure is necessary for construction of new deceleration lane and driveway entrance

Please follow the detour signs in place on all projects.  All work is dependent upon weather conditions

For more information, Click Here   |   For our complete coverage, Click Here

Related post