Connect 10, TxDoT Closures, detours beginning November 9

Work continues throughout the Borderland this week, with a significant closure scheduled to start Saturday, November 9.

The demolition of parts of ramps leading from I-10 to Juárez will require the complete closure of SH 20 (Alameda Avenue) under US 54 this weekend.

When the I-10 Connect Project is complete, those ramps from I-10 to Juárez will be reconfigured to give motorists bound for Juárez separate ramps from motorists bound for Loop 375.

Other daytime and nighttime closures will be in place in the week to come.

Links to full lists of closures:  West Area Projects  |  I-10 Connect  |  East Area Projects

Saturday, November 9, at 7am through Monday, November 11, at 5am |  46-Hour Closure

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds Street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54. Motorists, pedestrians and cyclists will not be allowed to cross under US 54 at any point during this closure.

Crews will be demolishing parts of Ramps F and G.

Monday, November 11, through Friday, November 15

Daily from 9am to 4pm

  • Lane closures will be in place on Ramp H which connects eastbound I-10 to northbound US 54.
  • Gateway Boulevard East will be closed to all traffic adjacent to Lincoln Park as needed.
  • The onramp which connects Gateway Boulevard East to eastbound I-10 at Loop 478 (Copia Street) will be closed to all traffic as needed.

Crews will be working on columns for the widening of Ramp H.

 

Monday, November 11, through Sunday, November 17

Non-stop closure

  • Ramp E which connects Gateway Boulevard South to southbound US 54 at Yandell Drive will be closed to all traffic.
  • DETOUR: Enter southbound US 54 at Pershing Drive.

Crews will be working on an overhead bridge deck.

Monday, November 11, through Friday, November 15

Alternating Daytime Closures

9am to 4pm

  • Gateway Boulevard East will be closed to all traffic adjacent to Lincoln Park as needed.
  • The onramp which connects Gateway Boulevard East to eastbound I-10 at Loop 478 (Copia Street) will be closed to all traffic as needed.

Crews will be working on columns for the widening of Ramp H.

Tuesday, November 12, through Thursday, November 14

Nightly from 9pm to 5am

  • Ramp D which connects southbound US 54 to eastbound I-10 will be closed to all traffic
  • DETOUR: Continue south on US 54, Take Exit 20A (US 62/Paisano Drive), u-turn to Gateway Boulevard North and follow signs to I-10.

Crews will be working on an overhead bridge deck.

Wednesday, November 13, and Friday, November 15

Daily from 9am to 4pm

  • The onramp from Gateway Boulevard South to southbound US 54 north of Pershing Drive will be closed to all traffic
  • DETOUR: Traffic will continue on Gateway South through Pershing Drive and enter southbound US 54 south of Pershing.

Crews will be drilling shafts for an overhead sign structure.

Thursday, November 14, from 9am to 4pm

  • Two left lanes will be closed on Gateway Boulevard South between Tompkins Road and Porter Avenue.
  • NOTE: Traffic using the Pershing Drive/Altura Avenue exit from southbound US 54 will have a limited merging area onto Gateway South during this work.

Crews will be drilling shafts for an overhead sign structure.

Long-Term Closures Which Will Remain in Place Next Week

  • Ramps F and G, which connect I-10 to Juárez at the Spaghetti Bowl, remain detoured through northbound US 54 to Pershing Drive until further notice.
  • Ramp T, which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive), remains closed until further notice.
  • Alternating complete closures of Durazno Avenue, Rosa Avenue and Uva Street.
  • Both turnarounds under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Intermittent lane closures will be in place on US 54 between Loop 375 and Spur 601.
  • Intermittent lane closures will be in place on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Intermittent lane closures will be in place on Gateway Boulevard West between Boone Street and Palm Street.
  • Lane closures are in place on eastbound and westbound SH 20 (Alameda Avenue) at US 54 until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) between I-110 and US 54 until further notice.
  • Lane closures are in place on Ramp D, which connects southbound US 54 to eastbound I-10, until further notice.
  • Lane closures are in place on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive) until further notice.

Monday, November 11, through Friday, November 15

Daily from 9am to 4pm

  • Lane closures will be in place on Ramp H which connects eastbound I-10 to northbound US 54.
  • Gateway Boulevard East will be closed to all traffic adjacent to Lincoln Park as needed.
  • The onramp which connects Gateway Boulevard East to eastbound I-10 at Loop 478 (Copia Street) will be closed to all traffic as needed.
  • Crews will be working on columns for the widening of Ramp H.

Monday, November 11, through Sunday, November 17

Non-stop closure

  • Ramp E which connects Gateway Boulevard South to southbound US 54 at Yandell Drive will be closed to all traffic.
  • DETOUR: Enter southbound US 54 at Pershing Drive.
  • Crews will be working on an overhead bridge deck.

Tuesday, November 12 through Thursday, November 14

Nightly from 9pm to 5am

  • Ramp D which connects southbound US 54 to eastbound I-10 will be closed to all traffic
  • DETOUR: Continue south on US 54, Take Exit 20A (US 62/Paisano Drive), u-turn to Gateway Boulevard North and follow signs to I-10.
  • Crews will be working on an overhead bridge deck.

Wednesday, November 13 and Friday, November 15

Daily from 9am to 4pm

  • The onramp from Gateway Boulevard South to southbound US 54 north of Pershing Drive will be closed to all traffic
  • DETOUR: Traffic will continue on Gateway South through Pershing Drive and enter southbound US 54 south of Pershing.
  • Crews will be drilling shafts for an overhead sign structure.

Thursday, November 14, from 9am to 4pm

  • Two left lanes will be closed on Gateway Boulevard South between Tompkins Road and Porter Avenue.
  • NOTE: Traffic using the Pershing Drive/Altura Avenue exit from southbound US 54 will have a limited merging area onto Gateway South during this work.
  • Crews will be drilling shafts for an overhead sign structure.

US 54 Widening and Illumination Project

Thursday, Nov. 7 through Tuesday, Nov. 12
9 p.m. to 7 a.m. (nightly)

  • Sun Valley off ramp northbound complete closure.
  • Crews will be working on barrier pour, striping, and rub.

Wednesday, Nov. 13
9 a.m. to 5 p.m.

  • Transmountain signal transfer to the new pole.
  • Stop and go traffic.

I-10 Ramp Improvements – Phase 2

Tuesday, Nov. 12 through Thursday, Nov. 14
9 p.m. to 6 a.m. (nightly)

  • Gateway Blvd East will be closed at Eastside Rd and Hawkins intersection.
  • Detour right on Eastside Rd, left on Industrial, past Hawkins, left at Tony Lama, and back on to Gateway Blvd East.
  • Crews will be working on placing concrete paving.

Monday, Oct. 28 through Monday, Nov. 18

  • Hawkins at Gateway Blvd East intersection will be closed.
  • No through traffic Northbound or Southbound at the intersection.
  • Gateway Blvd East traffic will continue east on the gateway or turn south on to Hawkins.
  • Northbound traffic on Hawkins will turn right onto Gateway Blvd East.
  • Southbound traffic on Hawkins will turn left onto Gateway Blvd East.

Rock Wall Repair

Tuesday, Nov. 12 through Friday, Nov. 15
9 a.m. to 4 p.m. (daily)

  • Gateway Blvd West left lane closure between Hawkins and Airway.
  • I-10 Westbound right shoulder closure between Hawkins and Airway.
  • Crews will be repairing rock wall in the area.

Spall Repair Project

Tuesday, Nov. 12 through Thursday, Nov. 14

9 p.m. to 5 a.m. (nightly)

  • Intersection of Montana and Airway will be closed.
  • Alternating two lane closures daily.
  • Crews will be repairing spalled concrete in the area.

District Wide Striping Project

Tuesday, Nov. 12 through Friday, Nov. 15
9 p.m. to 6 a.m.

  • I-10 alternating eastbound and westbound lanes between Eastlake Boulevard and Horizon Boulevard
  • Closure is necessary for mobile striping operation

Tuesday, Nov. 12 through Friday, Nov. 15
9 p.m. to 6 a.m.

  • I-10 alternating eastbound and westbound lanes between Zaragoza Road and Viscount Boulevard
  • Closure is necessary for mobile striping operation

Tuesday, Nov. 12 through Friday, Nov. 15
9 p.m. to 6 a.m.

  • I-10 alternating eastbound and westbound lanes between Airway Boulevard and West Schuster Avenue
  • Closure is necessary for mobile striping operation

TxDot, Connect10 work, detours, closures for Week of October 13

Here’s a look at the area’s project closures for the week ahead. High impact closures and complete closure lists via hyperlinks are below.

The largest on-going project is will allow crews to build new ramps to Juárez as part of the I-10 Connect Project, parts of existing ramps to Juárez must be removed. As a result of overhead demolition of parts of Ramp F which connects I-10 to Juárez, SH 20 (Alameda Avenue) will be closed to all pedestrians, cyclists and motorists at US 54 for approximately 46 hours next weekend.

Nightly closures on Alameda will continue in advance of the full weekend closure as crews finalize preparations for the demolition work. Other closures are scheduled for next week as well.

Links to full lists of closures: West Area Projects  |   I-10 Connect   |   East Area Projects

Spall Repair Project

Monday, October 14 through Thursday, October 17

9pm to 5am (Nightly)

  • Three left lanes IH-10 Eastbound from Geronimo to Airways
  • Three left lanes IH-10 Eastbound from Hawkins to McRae
  • Crews will be repairing spalled concrete in the area

Rockwall Repair

Monday, October 14 through Friday, October 18

9am to 4pm

  • Gateway West left lane closure between Hawkins and Airway
  • I-10 Westbound right shoulder closure between Hawkins and Airway
  • Crews will be repairing rock wall in the area.

Maintenance  

Monday, October 14 through Friday, October 18

9am to 4pm

  • Center lane closed at Gateway West and Piedras
  • Right lane closed at Piedras Northbound between Gateway East and Gateway West
  • Right shoulder closed at US-54 South by Cassidy Gate
  • Right lane closure at SH178 Artcraft East and Westbound between Upper Valley to State Line
  • IH-10 East at Reynolds entrance ramp will be closed.
  • IH-10 Westbound alternate lane closures between Copia and Piedras. (NIGHT – 9pm to 6am)
  • Copia entrance to IH-10 West will be closed. (NIGHT – 9pm to 6am)

IH-10 Ramp Improvements – Phase 2

Tuesday, Oct 15 through Thursday, Oct 17

9pm – 6am (Night)

  • Hawkins exit ramp closed, and Gateway East Closed at Eastside Road.
  • Detour  through Eastside Road to Industrial to Hawkins, and back on to Gateway East (Barrier Move)

Monday, October 14 through Friday, October 18

9am to 4pm

  •  Gateway East to Gateway West Turn Around, and Gateways West to Gateway East Turn Around Closed. (Painting)

Monday, October 14

9am to 4pm

  •  Right turn lane from Gateway East to Hawkins Southbound closed with TMA, also closing (2) driveways from Circle K to Gateway East. Center median shoulder work both side of median on Hawkins south of Gateway East with TMA

Tuesday, October 15

9am to 4pm

  • Right turn lane from Gateway East to Hawkins Southbound closed with TMA, also closing (2) driveways from Circle K to Gateway East. Center median shoulder work both side of median on Hawkins south of Gateway East with TMA

Wednesday, October 16

9am-4pm

  • Right turn lane from Gateway East to Hawkins Southbound closed with TMA, also closing (2) driveways from Circle K to Gateway East. Center median shoulder work both side of median on Hawkins south of Gateway East with TMA

Thursday, October 17

9am-4pm

  •  Right turn lane at the Verizon Store into the Fountains along Gateway West closed; leaving Driveway Open, Right turn from Gateway West to Northbound Hawkins closed leaving driveways open. Right lane closure Gateway West from the Airway Westbound off ramp to the first driveway to Shell on Airway leaving driveways and side streets open.

Monday, October 28 through Monday, November 18

  • Hawkins at Gateway east intersection will close.
  • No through traffic north or south bound at the intersection.
  • Gateway east traffic will continue east on the gateway or turn south on to Hawkins.
  • Northbound traffic on Hawkins will turn right onto Gateway east.
  • Southbound traffic on Hawkins will turn left onto Gateway east.

Guardrail Repair Project

Monday, October 14

9am to 4pm

  • Right lane closure IH-10 Eastbound from Anthony to Westway Dr. including Anthony on-ramp to IH-10 Eastbound.

Tuesday, October 15

9am to 4pm

  • Right lane closure IH-10 Westbound between Transmountain and Vinton.

I-10 Connect

Monday, October 14, through Thursday, October 17

Nightly from 9pm to 5am

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds Street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54.
  • Crews will be preparing parts of an existing ramp for demolition.

Tuesday, October 15, from 9pm to 5am

  • Ramp B which connects northbound US 54 to Gateway Boulevard North will be closed to all traffic.
  • Ramp C which connects northbound US 54 to westbound I-10 will be closed to all traffic.
  • DETOUR TO WESTBOUND I-10: Take Exit 23 (Cassidy Road/Fort Bliss), take Exit 22B (Pershing Drive), and use the newly widened turnaround to access southbound US 54. Take Exit 21B (I-10 West/Las Cruces).
  • Crews will be placing bridge girders.

Tuesday, October 15, and Wednesday, October 16

Nightly 8pm to 5am

  • Gateway Boulevard North will be closed to all traffic between US 62 (Paisano Drive) and SH 20 (Alameda Avenue).
  • DETOUR: Northbound traffic will access US 54 via I-110.
  • Crews will be working on an overhead ramp.

46-HOUR WEEKEND CLOSURE

7am on Saturday, October 19, through

5am on Monday, October 21

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds Street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54. Motorists, pedestrians and cyclists will not be allowed to cross under US 54 at any point during this closure.
  • Crews will be demolishing parts of an existing ramp.

District Wide Striping Project

Monday, Oct. 14 through Friday, Oct. 18

9 a.m. to 4 p.m.

  • I-10 alternating eastbound and westbound lanes between Tornillo and Fort Hancock
  • Closure is necessary for mobile striping operation

Mall Braided Ramps Project

Sunday, Oct. 13 through Tuesday, Oct. 15 (complete closure)

9 p.m. to 5 a.m.

  • I-10 westbound complete closure between Hunter Drive and Hawkins Boulevard
  • Traffic will exit at McRae Boulevard and re-enter at Airway Boulevard
  • Crews will be removing portable concrete traffic barrier and final striping

Wednesday, Oct. 16 through Thursday, Oct. 17 (complete closure)

9 p.m. to 5 a.m. (overnight)

  • Gateway Boulevard eastbound to westbound turnaround at Hawkins Boulevard closed
  • Gateway Boulevard westbound to eastbound turnaround at Hawkins Boulevard closed
  • Complete closure of northbound and southbound lanes at Hawkins Boulevard underpass
  • Crews will be power-washing and painting underneath the bridge

 

Monday, October 14, through Thursday, October 17 – Nightly from 9pm to 5am

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds Street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54.

Crews will be preparing parts of an existing ramp for demolition.

Tuesday, October 15, from 9pm to 5am

  • Ramp B which connects northbound US 54 to Gateway Boulevard North will be closed to all traffic.
  • Ramp C which connects northbound US 54 to westbound I-10 will be closed to all traffic.
  • DETOUR TO WESTBOUND I-10: Take Exit 23 (Cassidy Road/Fort Bliss), take Exit 22B (Pershing Drive), and use the newly widened turnaround to access southbound US 54. Take Exit 21B (I-10 West/Las Cruces).

Crews will be placing bridge girders.

Tuesday, October 15, through Thursday, October 17 – Nightly 8pm to 5am

  • Gateway Boulevard North will be closed to all traffic between US 62 (Paisano Drive) and SH 20 (Alameda Avenue).
  • DETOUR: Northbound traffic will access US 54 via I-110.

Crews will be working on an overhead ramp.

46-HOUR WEEKEND CLOSURE – 7am on Saturday, October 19, through  5am on Monday, October 21

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and right on Raynolds Street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54. Motorists, pedestrians and cyclists will not be allowed to cross under US 54 at any point during this closure.

Crews will be demolishing parts of an existing ramp.

Long-Term Closures Which Will Remain in Place Next Week

  • Ramps F and G which connect I-10 to Juárez at the Spaghetti Bowl remain detoured through northbound US 54 to Pershing Drive until further notice.
  • Ramp T which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive) remains closed until further notice.
  • Alternating complete closures of Durazno Avenue, Rosa Avenue and Uva Street.
  • Both turnarounds under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Intermittent lane closures will be in place on US 54 between Loop 375 and Spur 601.
  • Intermittent lane closures will be in place on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Intermittent lane closures will be in place on Gateway Boulevard West between Boone Street and Palm Street.
  • Lane closures are in place on eastbound and westbound SH 20 (Alameda Avenue) at US 54 until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) between I-110 and US 54 until further notice.
  • Lane closures are in place on Ramp D which connects southbound US 54 to eastbound I-10 until further notice.
  • Lane closures are in place on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive) until further notice.

Upcoming Long-Term Closures

While the exact date and duration of the following closures have not been established, motorists are encouraged to be aware of the following proposed long-term closures:

  • Ramp V which connects southbound US 54 to US 62 (Paisano Drive) will close to all traffic so crews can temporarily open Gateway Boulevard South to two-way traffic. This temporary change is necessary to allow access to the Findley/Latta neighborhood during upcoming concrete paving work on Paisano.

  • All traffic leaving the Bridge of the Americas on northbound Interstate 110 will be required to turn right on US 62 (Paisano Drive). This temporary traffic change is necessary to allow crews to route southbound traffic on I-110 into the northbound lanes giving crews additional room to work on retaining walls.

Connect10, TxDoT work, closures, detours for week of September 15

Here’s a look at local project closures for the week ahead, complete closure lists can be accessed via hyperlinks are at the bottom of this story.

Also, as bridges around the I-10 Connect Project begin taking shape, motorists will encounter a handful of overnight closures on Interstate 10, US 62 (Paisano Drive), US 54 and SH 20 (Alameda Avenue) in the coming week.

Ramp F which connects westbound I-10 to Juárez is now closed to all traffic. This closure will be in place 24 hours a day, seven days a week until further notice. In the coming weeks, Ramp G which connects eastbound I-10 to Juárez will close, too.

Traffic seeking to access Juárez from westbound I-10 at the Spaghetti Bowl will use the following detour: Take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss); instead of going south to Juárez, follow northbound US 54. Take Exit 23 (Cassidy Road), then take Exit 22B (Pershing Drive). Use the newly widened turnaround at Pershing to enter southbound US 54. Continue on southbound US 54 and follow the signs to Juárez.

 

Commercial trucks should be mindful that they are prohibited from using many city streets adjacent to the detour route. The official detour has been designed to minimize traffic signals and includes newly widened portions to better accommodate truck traffic. However, motorists should consider using other international bridges to cross into Ciudad Juárez.

The City of El Paso International Bridges Department recommends motorists sign up for an E-Fast Pass which will help speed their crossing and qualify them for reduced toll rates for southbound crossings at the Stanton Street and Zaragoza Bridges.

For more information on the City of El Paso’s E-Fast Pass program, call (915) 212-7540. Click here to apply.

Other Long-Term Closures Which Will Remain in Place Next Week

  • Ramp E which connects Gateway Boulevard South to southbound US 54 at Yandell Drive remains closed until further notice.
  • Ramp T which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive) remains closed until further notice.
  • Alternating complete closures of Durazno Avenue, Rosa Avenue and Uva Street.
  • Both turnarounds under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Intermittent lane closures will be in place on US 54 between Loop 375 and Spur 601.
  • Intermittent lane closures will be in place on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Intermittent lane closures will be in place on Gateway Boulevard West between Boone Street and Palm Street.
  • Lane closures are in place on eastbound and westbound SH 20 (Alameda Avenue) at US 54 until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) between I-110 and US 54 until further notice.
  • Lane closures are in place on Ramp D which connects southbound US 54 to eastbound I-10 until further notice.

Lane closures are in place on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive) until further notice.

Sunday, September 15, from 9pm to 5am

  • Eastbound I-10 will be closed to all traffic at US 54.
  • DETOUR: Take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss) to northbound US 54, take Exit 23 (Cassidy Road/Fort Bliss), take Exit 22B (Pershing Drive), use the turnaround to enter southbound US 54 and follow signs to westbound I-10.

Crews will be working on an overhead bridge deck.

Sunday, September 15, through Thursday, September 19

Nightly from 9pm to 5am

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and left on Raynolds street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54.

Crews will be working on an overhead bridge deck.

Tuesday, September 17, and Thursday, September 19, from 9pm to 5pm

  • US 62 (Paisano Drive) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn right on San Marcial Street, left on Delta Drive, and left on Boone Street before returning to Paisano. Westbound traffic will turn right on Gateway Boulevard North, left on SH 20 (Alameda Avenue), and left on Loop 478 (Copia Street) before returning to Paisano.
  • NOTE: Traffic leaving westbound Loop 375 via Exit 20 (US 62/Paisano Drive) will not be able to turn left on Paisano or continue onto Gateway Boulevard North.

Crews will be working on an overhead bridge deck.

Wednesday, September 18, and Thursday, September 19, from 9pm to 5pm

  • Southbound US 54 will be closed to all traffic at I-10
  • DETOUR: From US 54, take Exit 21B (I-10 East/Van Horn); From I-10, take Exit 23B (US 62/180/Paisano Drive/Chelsea Street); turn right on Paisano to re-join US 54 near the El Paso Zoo.

Sunday, September 15, through Saturday, September 21

Daily from 9am to 4pm

  • Gateway Boulevard East will be intermittently closed to all traffic adjacent to Lincoln Park.
  • The on-ramp from Gateway Boulevard East to eastbound I-10 near Loop 478 (Copia Street) will be intermittently closed to all traffic.

Crews will be working on drilled shafts.

***

IH-10 Ramp Improvements – Phase 2

Monday, September 16

9 p.m. to 6 a.m. (throughout the night)

  • Hawkins Exit closed, and gateway east closed at Eastside Road. Detour through eastside road to Industrial to Hawkins South to Phoenix to Hunter. Gateway East closed at Tony Lama Street Detour through Tony Lama to Hawkins to Phoenix to Hunter/Viscount and back on to Gateway East.

Monday, September 16 through Friday, September 20, 2019

9 a.m. to 6 p.m. (nightly)

  • Gateway East to Gateway West Turn-Around closed at Hunter/Viscount
  • Gateway West to Gateway East Turn-Around Closed at Hunter/Viscount

Tuesday, September 17

9 a.m. to 4 p.m. (throughout the day)

  • Mandatory left turn lane approaching Gateway West from Southbound Hawkins closed with TMA. Right turn to Northbound Hawkins from Gateway West closed with TMA, with the shoulder work around island of right turn lane. Left shoulder work along center median of Northbound Hawkins north of Gateway West.

Tuesday, September 17 through Thursday, September 19

9 p.m. to 6 a.m. (nightly)

  • Hunter/Viscount intersection closed for bridge painting. No through traffic. Detour through gateway west to Hawkins and turn back on gateway east. Detour through gateway east, turn around at McCrae, and head back through gateway west.

Wednesday, September 18

9 a.m. to 4 p.m. (throughout the day)

  • Mandatory left turn lane approaching Gateway West from Southbound Hawkins closed with TMA. Right turn to Northbound Hawkins from Gateway West closed with TMA, with the shoulder work around island of right turn lane. Left shoulder work along center median of Northbound Hawkins north of Gateway West.

Thursday, September 19

9 a.m. to 4 p.m. (throughout the day)

  • Right turn lane from Southbound Hawkins to Gateway West closed with TMA, shoulder work around island of right turn lane. Right shoulder work along southbound Hawkins south of Gateway West.

Friday, September 20

9 a.m. to 4 p.m. (throughout the day)

  • Right turn lane from Southbound Hawkins to Gateway West closed with TMA, shoulder work around island of right turn lane. Right shoulder work along southbound Hawkins south of Gateway West.

Spall Repair Project

Monday, September 16 through Thursday, September 19

9 p.m. to 5 a.m. (Nightly)

  • Three left lanes IH-10 Eastbound at Geronimo to Hawkins Blvd.
  • Airway before and after overpass
  • Crews will be repairing spalled concrete in the area

I-10 Ramp Improvements – Phase 2

Monday, September 16

9 p.m. to 6 a.m. (throughout the night)

  • Hawkins Exit closed, and gateway east closed at Eastside Road. Detour through eastside road to Industrial to Hawkins South to Phoenix to Hunter. Gateway East closed at Tony Lama Street Detour through Tony Lama to Hawkins to Phoenix to Hunter/Viscount and back on to gateway east.

Tuesday, September 17 through Thursday, September 19

9 a.m. to 4 p.m. (throughout the night)

  • Hunter/Viscount intersection closed for bridge painting. No through traffic. Detour through gateway west to Hawkins and turn back on gateway east. Detour through gateway east, turn around at McRae, and head back through gateway west.

Starting October 1-15, 2019

  • Hawkins at Gateway east intersection will be close.
  • No through traffic north or south bound at the intersection.
  • Gateway east traffic will continue east on the gateway or turn south on to Hawkins.
  • Northbound traffic on Hawkins will turn right onto Gateway east.
  • Southbound traffic on Hawkins will turn left onto Gateway east.

Mall Braided Ramps Project

Sunday, Sept. 15 through Thursday, Sept. 19

9 p.m. to 5 a.m.

  • I-10 westbound complete lane closure between Hawkins Boulevard to Airway Boulevard
  • Crews will be removing permanent concrete barrier from median

Until further notice

  • Gateway East Boulevard alternating lane closures between Airway Boulevard and Hawkins Boulevard
  • Gateway West Boulevard west alternating lane closures between Viscount Boulevard and Hawkins Boulevard

Mesa Park Interchange Project

Wednesday, September 18 through Friday, October 2

  • Complete closure Executive Westbound Off Ramp Closure is needed for crews to finish rebuilding off ramp

US 54 Widening and Illumination Project

Monday, September 16 through Thursday, September 19

9 p.m. to 6 a.m. (nightly)

  • US54 Northbound completely closed from Hondo Pass Overpass to Transmountain Overpass
  • All traffic will exit Hondo Pass off ramp northbound and re-enter at Transmountain on ramp
  • Striping, installing and removing signs
  • US54 Southbound off ramp at Loop 375 and re-enter at Loop 375

Maintenance

Monday, September 16 through Friday, September 20

9 a.m. to 4 p.m. (throughout the day)

  • Center lane closed at Gateway West and Piedras
  • Right lane closed at Piedras Northbound between Gateway East and Gateway West
  • Right shoulder closed at US-54 South by Cassidy Gate
  • IH-10 West at Copia exit will be closed
  • Left lane Gateway East between Luna and Estrella
  • Right lane closure at SH178 Artcraft East and Westbound between Upper Valley to State Line

I-10 Connect

Sunday, September 15, from 9pm to 5am

  • Eastbound I-10 will be closed to all traffic at US 54.
  • DETOUR: Take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss) to northbound US 54, take Exit 23 (Cassidy Road/Fort Bliss), take Exit 22B (Pershing Drive), use the turnaround to enter southbound US 54 and follow signs to westbound I-10.
  • Crews will be working on an overhead bridge deck.

Sunday, September 15, through Thursday, September 19

Nightly from 9pm to 5am

  • SH 20 (Alameda Avenue) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn left on Loop 478 (Copia Street), right on Gateway Boulevard East, and left on Raynolds street. Westbound traffic will use westbound US 62 (Paisano Drive) and turn right on Loop 478 (Copia Street).
  • NOTE: Alameda will remain open to local traffic only except for the area immediately under US 54.
  • Crews will be working on an overhead bridge deck.

Tuesday, September 17, and Thursday, September 19, from 9pm to 5pm

  • US 62 (Paisano Drive) will be closed to all traffic at US 54.
  • DETOURS: Eastbound traffic will turn right on San Marcial Street, left on Delta Drive, and left on Boone Street before returning to Paisano. Westbound traffic will turn right on Gateway Boulevard North, left on SH 20 (Alameda Avenue), and left on Loop 478 (Copia Street) before returning to Paisano.
  • NOTE: Traffic leaving westbound Loop 375 via Exit 20 (US 62/Paisano Drive) will not be able to turn left on Paisano or continue onto Gateway Boulevard North.
  • Crews will be working on an overhead bridge deck.

Wednesday, September 18, and Thursday, September 19, from 9pm to 5pm

  • Southbound US 54 will be closed to all traffic at I-10
  • DETOUR: From US 54, take Exit 21B (I-10 East/Van Horn); From I-10, take Exit 23B (US 62/180/Paisano Drive/Chelsea Street); turn right on Paisano to re-join US 54 near the El Paso Zoo.

Links to full lists of closures:  West Area Projects  |   I-10 Connect  |  East Area Projects

Go10, Connect10, TxDoT Closures, detours for week of June 16

Massive closure of I-10 in both directions is set for this Sunday, June 16 (Father’s Day).

“We weighed the pros and cons…working on Father’s Day means we can achieve the ultimate goal of being finished with roadway work by June 30,” Go10 officials shared via a news release. ” Not working on Father’s Day could set us back two weeks or longer.  We’re almost done (and out of your way).”

Don’t forget to follow TxDoT on Twitter at @TxDOTELP where right now you can find a video on the progress of their Montana Expressway Project. PLUS sign up for traffic alerts on www.drivetexas.org.

GO10

I-10 Both Directions

Sunday, June 16 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 East will close completely between North Mesa Street (SH 20) and Sunland Park Drive. Detour: Motorists traveling on I-10 East will exit at North Mesa (exit 11), then follow North Mesa Street (SH 20) to Executive Center Blvd. Motorist may re-enter I-10 East using the Executive Center entrance ramp.
  • I-10 West will close completely between Executive Center Blvd and Redd Road. Detour: Motorists traveling on I-10 West will exit at Executive Center (exit 16), follow Executive Center Blvd to North Mesa Street (SH 20), then follow the detour signs along North Mesa Street (SH 20). Motorists may re-enter I-10 West using the Redd Road entrance ramp.
  • The westbound and eastbound CD lanes will close at the Sunland Park exit ramps.
  • The Resler flyover entrance ramp to I-10 East will close.
  • All Sunland Park entrance ramps to I-10 West and to I-10 East will close.
  • Paisano Drive (US 85) – in front of the auto dealerships – will close at Sunland Park Drive.
  • Crockett Street access to Paisano Drive (US 85) will close.
  • Both westbound US 85 overpasses, which lead to the Sunland Park area, will close at McNutt Road.
  • The eastbound-to-westbound turnaround bridge at the Sunland Park Drive overpass will close.
  • The Schuster/UTEP entrance ramp to I-10 West will close.
  • The North Mesa entrance ramp to I-10 East will close.
  • Crews will be re-striping the main lanes of I-10, removing temporary barrier, and constructing permanent barrier among other activities.

I-10 East at Sunland

Monday, June 17, and Tuesday, June 18
9 p.m. each night to 6 a.m. each following morning

  • I-10 East will close completely at the Sunland Park exit ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 East.
  • Crews will be constructing permanent concrete barrier.

I-10 West at Sunland & eastbound CDs at Sunland

Wednesday, June 19 and Thursday, June 20
9 p.m. each night to 6 a.m. each following morning

  • I-10 West will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 West at the next ramp.
  • The eastbound CD lanes will close at the Sunland Park exit ramp. Detour: Motorists traveling on the eastbound CD lanes will exit at Sunland Park, the follow Sunland Park Drive to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to Executive Center Boulevard. Motorists may re-enter I-10 East using the Executive Center Boulevard entrance ramp.
  • The Resler flyover entrance ramp to I-10 East will close.
  • Paisano Drive (US 85) – in front of the auto dealerships – will close at Sunland Park Drive.
  • The Sunland Park flyover entrance ramp to I-10 East will close.
  • Crockett Street access to Paisano Drive (US 85) will close.
  • The westbound to eastbound turnaround bridge will close.
  • Crews will be constructing permanent concrete barrier and striping I-10 West.

North Mesa

Tuesday, June 18 and Wednesday, June 19
9 p.m. each night to 6 a.m. each morning

  • North Mesa Street (SH 20) – in the westbound direction – will close completely between Remcon Circle and South Desert Boulevard.
  • North Mesa Street (SH 20) – in the eastbound direction – will close completely between Osborne Drive and North Desert Boulevard.
  • Restriction:  Eastbound and westbound motorists who exit at North Mesa (exit 11) will be forced to turn right onto North Mesa Street (SH 20).
  • Crews will be adjusting the striping on several portions North Mesa Street.

Sunland

Tuesday, June 18 and Wednesday, June 19
9 a.m. to 4 p.m. each day

  • Sunland Park Drive – traveling in the direction toward Doniphan Drive – will have a right lane closed the mall traffic signal lights and Machuca Road.
  • The dedicated right turn lane from Sunland Park Drive to enter I-10 West will close.

Thursday, June 20 and Friday, June 21
9 a.m. to 4 p.m. each day

  • Sunland Park Drive – traveling in the direction toward the mountain – will have a right lane closed between Machuca Road and the mall traffic signal lights.
  • The dedicated right turn lane from Sunland Park Drive to Paisano Drive (US 85) will close.

I-10 West at Sunland

Sunday, June 23 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 West will close completely between Sunland Park (exit 13) and North Mesa. Detour: Motorists on I-10 West will exit at Sunland Park (exit 13), then follow the CD lanes westbound. Motorists may re-enter I-10 West using the Redd Road entrance ramp.
  • The North Mesa entrance to I-10 West will close.
  • The Sunland Park entrance ramp to I-10 West will close.
  • Crews will be removing barrier, striping pavement, installing guardrail, and other punch list items.

Sunday, June 30 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 West will close completely between Sunland Park (exit 13) and North Mesa.
  • All closures are subject to change or cancellation.
  • All closure times are approximate.
  • Exit and entrance ramps may close up to one hour prior to the start time of an I-10 closure.

Mesa Park Interchange Project 

Wednesday, June 19 and Thursday, June 20
9 p.m. to 6 a.m. (nightly)

  • Complete freeway closure westbound from Schuster exit to Sunland Park
  • Traffic detour exit at Schuster

Spall Repair Project

Sunday, June 16, through Thursday, June 20
9 p.m. to 5 a.m. (nightly)

  • Two right lanes I-10 westbound at Viscount overpass closed
  • McRae on-ramp westbound closed
  • McRae off-ramp westbound closed

Bridge Repair Project

Sunday, June 16, through Thursday, June 20
9 p.m. to 5 a.m. (nightly)

  • I-10 eastbound right lane at Geronimo overpass closed
  • I-10 westbound right lane at Geronimo overpass closed
  • Turnaround from Gateway West to Gateway East at Geronimo closed
  • Left lane on Gateway East after Geronimo closed
  • Left lane on Gateway West before Geronimo closed

Hawkins/Viscount Operation Improvements Project

Monday June 17
9 a.m. to 4 p.m.

  • Airway East to West and West to East turnarounds closed.

Tuesday, June 18
9 a.m. to 4 p.m.

  • Viscount East to West and West to East turnarounds closed
  • Right shoulder work Gateway east from Winslow to 100 ft east of Hunter

Monday, June 28 to Saturday, July 15
9 a.m. to 4 p.m.

  • Right and left shoulder work along Airway east exit ramp
  • Left shoulder work along Gateway east to Airway east to west turnaround
  • Turnaround will be closed with right shoulder work under bridge at Airway south

Maintenance  

Monday, June 17 through Friday, June 21
9 a.m. to 3 p.m. (throughout the day)

  • Left lane closure east and west at US 85/Paisano between Spur 1966 and Doniphan
  • I-10 westbound at Piedras entrance ramp will be closed
  • I-10 westbound at Cotton exit ramp will be closed
  • Left lane closure at Missouri between Magnolia and Cotton
  • Alternate closure east and west bound at Woodrow Beam between Rushing and Alcan

US 54 Widening and Illumination Project

Monday, June 17
9 p.m. to 5 a.m.

  • Northbound US 54 from Transmountain on-ramp to Sun Valley overpass right lane closed

Tuesday, June 18

  • Southbound US 54 from Sun Valley on-ramp to Transmountain off-ramp right lane closed

Border West Expressway Project

US 85

Monday, June 10, to Thursday, June 13
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Loop 375

Friday, June 14, to Monday, June 17
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

Delta

Saturday, June 22
5 a.m. to 6 p.m. (complete closure)

  • Westbound and eastbound from Coles Street to San Marcial Street
  • Closure is needed for bridge work

I-10 Connect

Monday, June 17, through Thursday, June 20
Nightly 9 pm to 5 am, continuing for several weeks

  • Ramp F, which connects westbound Interstate 10 to Juárez, will close all traffic.
  • Detour: From westbound I-10, take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss) to northbound US 54, take Exit 23 (Cassidy Road/Fort Bliss), take exit 22B (Pershing Drive), use the newly widened turnaround at Pershing Drive, re-enter southbound US 54 and follow signs to Juárez.
  • Gateway Boulevard East will be closed to all traffic near Lincoln Center.
  • Detour: Enter eastbound I-10 east of Loop 478 (Copia Street) and take Exit 23A (Raynolds Street).
  • Crews will be completing prep work on ramps.

Wednesday, June 19, and Thursday, June 20
Nightly 9 pm to 5 am

  • Eastbound I-10 will be closed to all traffic at US 54.
  • Detour: All traffic will take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss) to northbound US 54, take exit 22B (Pershing Drive), use the newly widened turnaround at Pershing Drive, re-enter southbound US 54 and follow signs to Juárez or eastbound I-10.
  • Crews will be working on a drilled shaft in the median of I-10 to support a column for one of the new direct connectors linking southbound US 54 and Juárez.
  • Crews will be placing concrete barriers.

 

Mall Braided Ramps Project

Sunday, June 16, through Friday, June 21
9 p.m. to 5 a.m.

  • I-10 westbound right lane closure between Viscount Boulevard and Hawkins Boulevard
  • Hawkins Boulevard exit ramp closed
  • Crews will be painting bridge

Loop 375 Frontage Road Project

Monday, June 17, through Wednesday, June 19
11 p.m. to 5 a.m.

  • Loop 375 northbound complete lane closure between Zaragoza Road and Socorro Road
  • All traffic must exit at Zaragoza Road (use frontage road) and re-enter after Alameda Avenue
  • Crews will be placing portable concrete traffic barriers

Links to full lists of closures:  West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect   |  East Area Projects

LOCATION DURATION DESCRIPTION
I-10 Both Directions

 

27 Hours

Sunday, June 16

3 am to 6 am the next day

 

·   I-10 East will close completely between North Mesa Street (SH 20) and Executive Center Blvd.  Detour:  Motorists traveling on I-10 East will exit at North Mesa (exit 11), then follow North Mesa Street (SH 20) to Executive Center Blvd. Motorist may re-enter I-10 East using the Executive Center entrance ramp.

·   I-10 West will close completely between Executive Center Blvd and Redd Road. Detour:  Motorists traveling on I-10 West will exit at Executive Center (exit 16), follow Executive Center Blvd to North Mesa Street (SH 20), then follow the detour signs along North Mesa Street (SH 20). Motorists may re-enter I-10 West using the Redd Road entrance ramp.

·   The CD lanes both directions will close.

·   The Resler flyover entrance ramp to I-10 East will close.

·   All Sunland Park entrance ramps to I-10 West and to I-10 East will close.

·   Paisano Drive (US 85) – in front of the auto dealerships – will close at Sunland Park Drive.

·   Crockett Street access to Paisano Drive (US 85) will close.

·   Both westbound US 85 overpasses, which lead to the Sunland Park area, will close at McNutt Road.

·   The eastbound-to-westbound turnaround bridge at the Sunland Park Drive overpass will close.

·   The Schuster/UTEP entrance ramp to I-10 West will close.

·   The North Mesa entrance ramp to I-10 East will close.

 

Crews will be re-striping the main lanes of I-10, removing temporary barrier, and constructing permanent barrier among other activities.

 

I-10 East at Sunland Nightly

June 17 and 18

9 pm each night to 6 am each following morning

 

·   I-10 East will close completely at the Sunland Park exit ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 East.
North Mesa

 

Nightly

June 18 and 19

9 pm each night to 6 am each morning

 

·   North Mesa Street (SH 20) – in the westbound direction – will close completely between Remcon Circle and South Desert Boulevard.

·   North Mesa Street (SH 20) – in the eastbound direction – will close completely between Osborne Drive and North Desert Boulevard.

·   Restriction:  Eastbound and westbound motorists who exit at North Mesa (exit 11) will be forced to turn right onto North Mesa Street (SH 20).

 

Sunland

 

Daytime

June 18 and 19

9 am to 4 pm each day

 

·   Sunland Park Drive – traveling in the direction toward Doniphan Drive – will have a right lane closed the mall traffic signal lights and Machuca Road.

·   The dedicated right turn lane from Sunland Park Drive to enter I-10 West will close.

 

I-10 West at Sunland & eastbound CDs at Sunland

 

Nightly

June 19 and 20

9 pm each night to 6 am each following morning

 

·   I-10 West will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 West at the next ramp.

·   The eastbound CD lanes will close at the Sunland Park exit ramp. Detour:  Motorists traveling on the eastbound CD lanes will exit at Sunland Park, the follow Sunland Park Drive to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to Executive Center Boulevard. Motorists may re-enter I-10 East using the Executive Center Boulevard entrance ramp.

·   The Resler flyover entrance ramp to I-10 East will close.

·   Paisano Drive (US 85) – in front of the auto dealerships – will close at Sunland Park Drive.

·   The Sunland Park flyover entrance ramp to I-10 East will close.

·    Crockett Street access to Paisano Drive (US 85) will close.

·   The westbound to eastbound turnaround bridge at Sunland will close.

Sunland

 

Daytime

June 20 and 21

9 am to 4 pm each day

 

·   Sunland Park Drive – traveling in the direction toward the mountain – will have a right lane closed between Machuca Road and the mall traffic signal lights.

·   The dedicated right turn lane from Sunland Park Drive to Paisano Drive (US 85) will close.

 

I-10 West at Sunland

 

27 Hours

Sunday, June 23

3 am to 6 am the next day

 

·   I-10 West will close completely between Sunland Park (exit 13) and North Mesa. Detour: Motorists on I-10 West will exit at Sunland Park (exit 13), then follow the CD lanes westbound. Motorists may re-enter I-10 West using the Redd Road entrance ramp.

·   The North Mesa entrance to I-10 West will close.

·   The Sunland Park entrance ramp to I-10 West will close.

 

Crews will be removing barrier, striping pavement, installing guardrail, and other punch list items.

 

 

Connect10, Go10, TxDoT closures and detours for week of June 1st

Go10 officials say that June 30th is the target date for being finished with all roadway work. After June, expect work to continue off the roadways for another two months or so.

Off-the-roadway work will be for miscellaneous items, such as, finishing a rock wall in the Sunland Park area, flood control work, clean up, and other punch list items.  GO 10 is a $158 million, four-year project that started in 2015 and is finishing on-time and on-budget.

A few miles east, work continues on the I-10 Connect Project.  When the I-10 Connect Project is complete, southbound traffic on US 54 will have access to a new direct connector ramp soaring over Interstate 10 leading directly to the Bridge of the Americas and Juárez.

But constructing that ramp requires work above one on-ramp and in the median of I-10 near the Spaghetti Bowl. To safely accommodate that work, requiring the following closures will be in place in the coming weeks.

     Changes START JUNE 3 – MONDAY– for  some downtown streets as the Border West Expressway projects nears completion.

Long Term On-Ramp Closure

Monday, June 3, and continuing until further notice:

  • Ramp E which connects Gateway Boulevard South to southbound US 54 south of Yandell Drive will be closed to all traffic.
  • DETOUR: Enter southbound US 54 from Gateway Boulevard South immediately south of Pershing Drive.

Crews will be working on columns and column caps.

27-Hour Closure of Westbound I-10

3am on Sunday, June 9, through 6am on Monday, June 10

  • Westbound Interstate 10 will be closed to all traffic at US 54.
  • Ramp L which connects Gateway Boulevard West to westbound I-10 west of Raynolds Street will be closed to all traffic.
  • Ramp C which connects northbound US 54 to westbound I-10 will be closed to all traffic
  • DETOUR: Westbound traffic on I-10 will take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss), travel northbound on US 54, take Exit 23 (Fort Bliss/Cassidy Road), and then take Exit 22 (Pershing Drive) to Gateway Boulevard North. Traffic will then use the newly-widened turnaround at Pershing Drive to access Gateway Boulevard South then enter southbound US 54 and continue straight ahead to re-enter westbound I-10.

Crews will begin work on a drilled shaft.

Overnight Closure of Eastbound I-10

Sunday, June 9, 9pm to 5am

  • Eastbound Interstate 10 will be closed to all traffic at US 54.
  • The on-ramp which connects Gateway Boulevard East to eastbound I-10 east of Loop 478 (Copia Street) will be closed to all traffic.
  • DETOUR: Eastbound traffic on I-10 will take Exit 22A (Loop 478/Copia Street), continue east on Gateway Boulevard East, and re-enter I-10 east of Raynolds Street.
  • NOTE: Traffic bound for northbound US 54 or Juárez will follow the above detour and continue on Gateway Boulevard East to US 62/180 (Paisano Drive). Traffic bound for Juárez will turn right on Paisano; Traffic bound for northbound US 54 will u-turn to Gateway Boulevard West at Paisano, enter westbound I-10 and take Exit 22B (US 54/Alamogordo/Fort Bliss/Juárez).

Crews will begin work on a drilled shaft.

The Following Long-Term Closures Will Remain In Place During the Week of June 2:

  • The on-ramp from Gateway Boulevard North to I-110 near the El Paso Zoo will be closed to all traffic each weekday.
  • Intermittent lane closures will be in place on Gateway Boulevard East from Piedras Street to US 62/180 (Paisano Drive).
  • Intermittent lane closures will be in place on Gateway Boulevard West from Boone Street to Palm Street.
  • Ramp T which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive) remains closed until further notice.
  • Both turnarounds between Gateway Boulevard North and Gateway Boulevard South under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Turnaround from Gateway Boulevard East to Gateway Boulevard West under I-10 at Trowbridge Drive remains closed until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) at US 54 until further notice.
  • Lane closures are in place on Ramp D which connects southbound US 54 to eastbound I-10 until further notice.
  • Intermittent lane closures on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive).

All closures are subject to change due to weather or field conditions. On ramps and off ramps may close up to an hour before stated times.

GO10

I-10 East at Redd

Sunday, June 2 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 East will close completely between Redd Road and Executive Center Boulevard. Detour: Motorists on I-10 East will exit at Redd Road (exit 9), follow South Desert Boulevard to North Mesa Street (SH 20), follow North Mesa Street (SH 20) to Executive Center Boulevard. Re-enter I-10 East using the Executive Center entrance ramp.
  • The North Mesa entrance ramp to I-10 East will close.
  • The eastbound collector-distributor (CD) lanes will close completely at North Mesa Street (SH 20).
  • Paisano Drive (US 85) – in front of the auto dealerships – will close completely starting at Sunland Park Drive.
  • Crockett Street access to Paisano Drive (US 85) will close.
  • Both turnaround bridges at Sunland Park Drive will close.
  • The Sunland Park flyover ramp and the Resler flyover ramp will close.
  • Milestone: When this 27-hour closure lifts, motorists on I-10 East can expect a lane pattern change near Buena Vista that will place them on the mainlanes of I-10. This change comes after two years of drivers being detoured onto the CD lanes.

 

I-10 West at Executive

Monday, June 3
9 p.m. to 6 a.m. the next morning

  • I-10 West will close completely between the Executive Center exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Executive Center (exit 16), follow Executive Center Blvd to North Mesa (SH 20), follow North Mesa (SH 20) to Sunland Park Drive, then follow Sunland Park Drive to the entrance ramp to I-10 West.
  • The Schuster/UTEP entrance ramp to I-10 West will close.
  • Crews will be constructing permanent concrete barrier.

 

I-10 West at Sunland

Tuesday, June 4
9 p.m. to 6 a.m. the next morning

  • I-10 West will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 West at the next ramp.
  • Crews will be constructing permanent concrete barrier.

 

I-10 East at Sunland

Wednesday, June 5, and Thursday, June 6
9 p.m. each night to 6 a.m. each following morning

  • I-10 East will close at the Sunland Park exit ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 East.
  • Crews will be constructing permanent concrete barrier.

 

I-10 East at Mesa

Sunday, June 9 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 East will close completely between North Mesa Street (SH 20) and Sunland Park Drive. Detour: Motorists traveling on I-10 East will be detoured onto the eastbound CD lanes, bypassing all signalized intersections.
  • The North Mesa entrance ramp to I-10 East will close.
  • Crews will be removing barrier and striping I-10 pavement to final configuration.

 

I-10 West at Sunland

Monday, June 10, and Tuesday, June 11
9 p.m. each night to 6 a.m. each following morning

  • I-10 West will close between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 West at the next ramp.
  • Crews will be constructing permanent concrete barrier.

 

I-10 East at Sunland

Wednesday, June 12, and Thursday, June 13
9 p.m. each night to 6 a.m. each following morning

  • I-10 East will close at the Sunland Park exit ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 East.
  • Crews will be constructing permanent concrete barrier.

 

I-10 Both Directions

Sunday, June 16 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 East will close completely between North Mesa Street (SH 20) and Sunland Park Drive. Detour: Motorists traveling on I-10 East will be detoured onto the eastbound CD lanes, bypassing all signalized intersections.
  • I-10 West will close completely between Executive Center Blvd and Redd Road. Detour: Motorists traveling on I-10 West will exit at Executive Center (exit 16), follow Executive Center Blvd to North Mesa Street (SH 20), then follow the detour signs along North Mesa Street (SH 20). Motorists may re-enter I-10 West using the Redd Road entrance ramp.
  • The westbound CD lanes will be closed starting at Sunland Park.
  • All Sunland Park entrance ramps to I-10 West will be closed.
  • Both westbound US 85 overpasses, which lead to the Sunland Park area, will close.
  • The eastbound-to-westbound turnaround bridge at the Sunland Park Drive overpass will close.
  • The Schuster/UTEP entrance ramp to I-10 West will close.
  • The North Mesa entrance ramp to I-10 East will close.
  • Crews will be removing barrier, striping I-10 pavement to final configuration, among other activities.

 

I-10 West at Sunland

Sunday, June 23 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 West will close completely between Sunland Park (exit 13) and North Mesa.

Sunday, June 30 (27-hour closure)
3 a.m. to 6 a.m. the next day

  • I-10 West will close completely between Sunland Park (exit 13) and North Mesa.

I-10/Americas – Phase IV Project

Tuesday, June 4 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 westbound closure at Eastlake Boulevard
  • I-10 westbound to Loop 375 northbound connector
  • I-10 westbound to Loop 375 southbound connector
  • Crews will be repairing bridge

Mall Braided Ramps Project

Sunday, June 2 (complete closure)
9 p.m. to 5 a.m.

  • I-10 eastbound closure between Airway Boulevard and Viscount Boulevard
  • Crews will be setting high mast illumination

Monday, June 3 (complete closure)
9 p.m. to 5 a.m.

  • I-10 westbound closure between Viscount Boulevard and Airway Boulevard
  • Crews will be pulling fiber cables to camera pole

Border West Expressway

US 85

Friday, May 31, to Monday, June 3
7 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Loop 375

Friday, May 31, to Monday, June 3
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

Friday, June 14, to Monday, June 17
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

 

Spur 1966

Saturday, June 1
6 a.m. to 7 p.m. (complete closure)

  • Eastbound and westbound from US 85 to Schuster Avenue
  • Closure is needed for roadway work

Miscellaneous Concrete Project

Monday, June 3, through Friday, June 7
9 a.m. to 4 p.m. (throughout the day)

  • Right lane on US 54 north at Trowbridge overpass
  • Montana entrance ramp will be closed
  • Contractor will be repairing concrete in the area.

Mesa Park Interchange Project

Sunday, June 9, to Monday, June 10
3 a.m. to 6 a.m. (27-hour closure)

  • Complete freeway closure from Schuster exit to Sunland Park
  • Traffic detour through Mesa
  • Traffic lanes will be switched affecting the Executive exit westbound

Maintenance  

Monday, June 3, through Friday, June 7
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on US 54 north from Ramp H to Altura
  • Trowbridge exit ramp closed on US 54 north
  • Montana entrance ramp closed on Gateway North
  • Entrance and exits on Border Highway westbound between Zaragoza and Fonseca
  • Alternate lane closures on Woodrow Beam East and West Bound between Kenworthy and Railroad.
  • I-10 West Artcraft ramp exit closed.
  • Left lane on Desert North between Helen of Troy and Paseo del Norte.
  • Left lane closure east and west at US 85/Paisano between Spur 1966 and Doniphan

Dyer/Zaragoza Overlay Project

Monday, June 3, through Friday, June 7
8 a.m. to 3 p.m. (throughout the day)

  • Alternate lane closure northbound
  • Southbound to one lane traffic

I-10 Connect

Monday, June 3, and continuing until further notice:

  • Ramp E, which connects Gateway Boulevard South to southbound US 54 south of Yandell Drive, will be closed to all traffic.
  • Detour: Enter southbound US 54 from Gateway Boulevard South immediately south of Pershing Drive.
  • Crews will be working on overhead columns and column caps.

3 a.m. on Sunday, June 9, through 6 a.m. on Monday, June 10

  • Westbound Interstate 10 will be closed to all traffic at US 54.
  • Ramp L, which connects Gateway Boulevard West to westbound I-10 west of Raynolds Street, will be closed to all traffic.
  • Ramp C, which connects northbound US 54 to westbound I-10, will be closed to all traffic
  • Detour: Westbound traffic on I-10 will take Exit 22B (US 54/Alamogordo/Juárez/Fort Bliss), travel northbound on US 54, take Exit 23 (Fort Bliss/Cassidy Road), and then take Exit 22 (Pershing Drive) to Gateway Boulevard North. Traffic will then use the newly-widened turnaround at Pershing Drive to access Gateway Boulevard South then enter southbound US 54 and continue straight ahead to re-enter westbound I-10.
  • Crews will begin work on a drilled shaft.

Sunday, June 9, 9 p.m. to 5 a.m. 

  • Eastbound Interstate 10 will be closed to all traffic at US 54.
  • The on-ramp which connects Gateway Boulevard East to eastbound I-10 east of Loop 478 (Copia Street) will be closed to all traffic.
  • Detour: Eastbound traffic on I-10 will take Exit 22A (Loop 478/Copia Street), continue east on Gateway Boulevard East, and re-enter I-10 east of Raynolds Street.
  • Note: Traffic bound for northbound US 54 or Juárez will follow the above detour and continue on Gateway Boulevard East to US 62/180 (Paisano Drive). Traffic bound for Juárez will turn right on Paisano; Traffic bound for northbound US 54 will U-turn to Gateway Boulevard West at Paisano, enter westbound I-10 and take Exit 22B (US 54/Alamogordo/Fort Bliss/Juárez).
  • Crews will begin work on a drilled shaft.

Links to full lists of closures:  West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect   |  East Area Projects

LOCATION DURATION DESCRIPTION
I-10 East at Redd

 

27 Hours

Sunday, June 2

3 am to 6 am the next day

 

·   I-10 East will close completely between Redd Road and Executive Center Blvd. Detour:  Motorists on I-10 East will exit at Redd Road (exit 9), follow South Desert Blvd to North Mesa Street (SH 20), follow North Mesa Street (SH 20) to Executive Center Blvd. Re-enter I-10 East using the Executive Center entrance ramp.

·   The North Mesa entrance ramp to I-10 East will close.

·   The eastbound collector-distributor (CD) lanes will close completely at North Mesa Street (SH 20).

·   Paisano Drive (US 85) – in front of the auto dealerships – will close completely starting at Sunland Park Drive.

·   Crockett Street access to Paisano Drive (US 85) will close.

·   Both turnaround bridges at Sunland Park Drive will close.

·   The westbound-to-eastbound turnaround bridge at North Mesa Street will close.

·   The Sunland Park flyover ramp and the Resler flyover ramp will close.

 

MILESTONE:  When this 27-hour closure lifts, motorists on I-10 East can expect a lane pattern change near Buena Vista that will place them on the main lanes of I-10. This change comes after two years of drivers being detoured onto the CD lanes.

 

US 85 Westbound Daytime

June 3 and June 4

9 am to 4 pm each day

 

·   The US 85 westbound overpass, which leads to the Sunland Park signalized intersection, will close.

·   The right lane on the US 85 westbound overpass, which leads to the westbound CD lanes near Sunland Park, will close.

 

North Mesa

 

Daytime

June 3-7

9 am to 4 pm each day

 

·   The right lane on eastbound North Mesa Street (SH 20) will close between Osborne Drive and South Desert Blvd.

·   The right lane on South Desert Blvd will close for about 300 feet starting at North Mesa Street (SH 20).

I-10 West at Executive

 

Overnight

June 3

9 pm to 6 am the next morning

 

·   I-10 West will close completely between the Executive Center exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Executive Center (exit 16), follow Executive Center Blvd to North Mesa (SH 20), follow North Mesa (SH 20) to Sunland Park Drive, then follow Sunland Park Drive to the entrance ramp to I-10 West.

·   The Schuster/UTEP entrance ramp to I-10 West will close.

 

I-10 West at Sunland

 

Overnight

June 4

9 pm to 6 am the next morning

 

·   I-10 West will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 West at the next ramp.

 

I-10 East at Sunland

 

Nightly

June 5 and June 6

9 pm each night to 6 am each morning

 

·   I-10 East will close completely at the Sunland Park exit ramp. Detour: Motorists will exit at Sunland Park (exit 13) and follow the CD lanes to re-enter I-10 East.
I-10 East at Mesa

 

27 Hours

Sunday, June 9

3 am to 6 am the next day

 

·   I-10 East will close completely between North Mesa Street (SH 20) and Sunland Park Drive.  Detour:  Motorists traveling on I-10 East will be detoured onto the eastbound CD lanes, bypassing all signalized intersections.

·   The North Mesa entrance ramp to I-10 East will close.

 

Go10, Connect10, TxDoT closures, detours and work for week of May 19

Here’s a look at project closures for the week ahead, including TWO (2) 27-Hour Closures of I-10. 

Also after a week of closures primarily focused on the northbound lanes of US 54, crews will turn their attention to the southbound lanes of US 54 next week as they continue placing temporary concrete barrier to outline the work zone for the I-10 Connect project.

The 30-foot, 42-inch barriers will create an added layer of separation — and safety — between motorists, construction crews and heavy machinery.

The following closures and detours will be in place to accommodate this work:

Sunday, May 19, and Monday, May 20

Nightly 9pm to 5am

  • Mainlanes of southbound US 54 will be closed to all traffic between the Pershing Drive underpass and Interstate 10.
  • Ramp D which connects southbound US 54 to eastbound I-10 will be closed to all traffic.
  • DETOURS: All southbound traffic on US 54 will take Exit 21B (I-10 West/Las Cruces). All traffic bound from US 54 to I-10 will enter westbound I-10 and continue west or take Exit 20 (Cotton Street), turn left on Cotton, and left on eastbound I-10. To continue on southbound US 54, traffic will take Exit 21C (Montana Avenue), continue on Gateway Boulevard South, and re-enter southbound US 54 south of Yandell Drive.

Crews will be placing concrete safety barriers

Sunday, May 19, 9pm to 5am

  • Gateway Boulevard South will be closed to all traffic between Cassidy Road and Tompkins Road.
  • DETOUR: Van Buren Avenue, left on Loop 478 (Dyer Street), left on Tompkins Road, right on Gateway South.

Crews will be placing concrete safety barriers

Tuesday, May 21, 9pm to 5am

  • Collector/distributor (C/D) lanes of southbound US 54 will be closed to all traffic between the Pershing Drive underpass and the Trowbridge Drive overpass.
  • DETOURS: Traffic on southbound US 54 will access westbound I-10 by taking Exit 22 (Pershing Drive/Fort Bliss), then taking the Pershing Drive/Altura Avenue exit, continuing on Gateway Boulevard South, and entering westbound I-10 south of Trowbridge Drive. Traffic on Spur 601 bound for westbound I-10 should continue to Gateway Boulevard South and follow the above detour.
  • NOTE: Thru traffic on southbound US 54 and traffic to eastbound I-10 will not be affected.

Crews will be placing concrete safety barriers

Wednesday, May 22, and Thursday, May 23

Nightly 9pm to 5am

  • All lanes of southbound US 54 will be closed to all traffic south of Spur 601.
  • The ramp from westbound Spur 601 to southbound US 54 will be closed to all traffic.
  • DETOURS: All traffic on southbound US 54 must take Exit 22 (Pershing Drive/Fort Bliss), then take the Pershing Drive/Altura Avenue exit, continue on Gateway Boulevard South, and re-enter US 54 north of Pershing Drive.
  • All traffic bound from westbound Spur 601 to US 54 will go northbound on US 54; traffic seeking to head south will take Exit 25 (Ellerthorpe Avenue) and u-turn.

Crews will be placing concrete safety barriers

Monday, May 20, through Friday, May 31

Daily 9am to 4pm

  • The on-ramp from Gateway Boulevard North to I-110 near the El Paso Zoo will be closed to all traffic.
  • DETOUR: Gateway Boulevard North, turn right on SH 20 (Alameda Avenue), left on Raynolds Street to I-10.

Crews will be preparing to tie in a new ramp to an existing ramp.

The Following Long-Term Closures Will Remain In Place During the Week of May 20:

  • Intermittent lane closures will be in place on Gateway Boulevard East from Piedras Street to US 62/180 (Paisano Drive).
  • Intermittent lane closures will be in place on Gateway Boulevard West from Boone Street to Palm Street.
  • Ramp T which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive) remains closed until further notice.
  • Both turnarounds between Gateway Boulevard North and Gateway Boulevard South under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Turnaround from Gateway Boulevard East to Gateway Boulevard West under I-10 at Trowbridge Drive remains closed until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) at US 54 until further notice.
  • Lane closures are in place on Ramp D which connects southbound US 54 to eastbound I-10 until further notice.
  • Intermittent lane closures on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive).

All closures are subject to change due to weather or field conditions. On ramps and off ramps may close up to an hour before stated times.

Spalling Repair Project

Saturday, May 18, through Sunday, May 19
6 a.m. to 3 p.m. (33-hour closure)

  • Left two lanes on Gateway south from Payne to Tompkins
  • Pershing exit ramp from Gateway south will be closed.

Miscellaneous Concrete Project

Monday, May 20, through Friday, May 24
9 a.m. to 4 p.m. (throughout the day)

  • Right lane on US 54 north at Trowbridge overpass
  • Montana entrance ramp will be closed
  • Contractor will be repairing concrete in the area.

Mesa Park Interchange Project

Sunday, May 19, and Monday, May 20
Midnight to 6 a.m. (each morning)

  • Full freeway closure between Sunland Park to Executive
  • Detour through North Mesa
  • Crews is needed for phasing of project and restaging equipment

Tuesday, May 28, and Wednesday, May 29
9 p.m. to 5 a.m. (nightly)

  • Right lane closure at I-10 west at Executive
  • Crews will be working on delivery of girders for the westbound bridges.

Wednesday, May 29, and Thursday, May 30
9 a.m. to 4 p.m. (daily)

  • Right lane closure at I-10 west at Executive
  • Crews will be working on delivery of girders for the westbound bridges.

Guardrail Repair Project

Friday, May 17
9 a.m. to 4 p.m. (throughout the day)

  • Right lane closure on I-10 east between Piedras to Copia entrance

Monday, May 20
9 a.m. to 4 p.m. (throughout the day)

  • Right lane closure on 375 Border Highway west between Fonseca to Paisano exit

Tuesday, May 21
9 a.m. to 4 p.m. (throughout the day)

  • Left lane closure on Franklin entrance ramp to I-10 east

Maintenance  

Monday, May 20, through Friday, May 24
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on I-10 east from Geronimo to 500 ft past Robert E. Lee
  • Right two lane closures on SH 20 south from Mesa to Crossroads
  • Left lane closure on Doniphan from McClintock to Mesa
  • Right lane closure on Doniphan from Crossroads to Mesa
  • Right lane closure on Artcraft East from Santiago to Doniphan
  • Modesta closed from Tarango to Artcraft
  • Santiago closed from Leslie to Artcraft
  • Left lane on Padres exit ramp closed on LP 375 east
  • Left lane on Padres closed from Buena Park to LP 375 entrance ramp east
  • Right lane closure on US 54 south from Altura to Ramp K
  • Montana exit ramp closed on US 54 south
  • Trowbridge entrance ramp closed on Gateway south
  • Right lane closure on US 54 north from Ramp H to Altura
  • Trowbridge exit ramp closed on US 54 north
  • Montana entrance ramp closed on Gateway North

Border West Expressway Project

US 85

Friday, May 17, to Monday, May 20
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Monday, May 20, to Thursday, May 23
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Friday, May 31, to Monday, June 3
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Monday, June 3, to Thursday, June 6
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Loop 375

Friday, May 31, to Monday, June 3
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

GO10

I-10 West at Executive

Sunday, May 19
3 a.m. to 6 a.m. the next day (27-hour closure)

  • The mainlanes of I-10 West will close completely between Executive Center Boulevard and North Mesa Street. Detour: Motorists on I-10 West will exit at Executive Center (exit 16), follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) toward the North Mesa entrance ramp to re-enter the mainlanes of I-10 West.
  • US 85 at McNutt Road will close.
  • All Sunland Park westbound ramps will close.
  • The turnaround bridge, eastbound to westbound, at Sunland Park Drive will close.
  • The Resler westbound exit ramp will close.
  • The Schuster westbound entrance ramp to I-10 West will close.
  • Crews will be re-striping a portion of I-10 West, installing signs, and moving barrier walls.

I-10 East at Sunland

Sunday, June 2
3 a.m. to 6 a.m. the next day (27-hour closure)

  • I-10 East will close completely between Sunland Park Drive and Executive Center Boulevard. Detour: Motorists on I-10 East will exit at Sunland Park (exit 13), then follow the detour signs to North Mesa Street (SH 20). Motorists may re-enter I-10 East using the Executive Center Boulevard entrance ramp.
  • Paisano Drive (US 85) – in front of the auto dealerships – will close completely starting at Sunland Park Drive.
  • The turnaround bridge, westbound to eastbound, at Sunland Park Drive will close.
  • The Sunland Park flyover ramp will close.
  • The eastbound collector-distributor (CD) lanes will close at Sunland Park. Detour: Motorists on the eastbound CD lanes will detour to the signalized intersection at Sunland Park Drive. Motorists will have to turn at the signalized intersection.
  • Crews will be striping a portion of I-10 East and removing barrier, giving relief to the pinched eastbound lanes near Buena Vista.

I-10 Connect

Sunday, May 19, and Monday, May 20
Nightly 9 p.m. to 5 a.m.

  • Mainlanes of southbound US 54 will be closed to all traffic between the Pershing Drive underpass and Interstate 10.
  • Ramp D, which connects southbound US 54 to eastbound I-10, will be closed to all traffic.
  • Detours: All southbound traffic on US 54 will take Exit 21B (I-10 West/Las Cruces). All traffic bound from US 54 to I-10 will enter westbound I-10 at which point they can continue west or take Exit 20 (Cotton Street), turn left on Cotton, and left on eastbound I-10. To continue on southbound US 54, traffic will take Exit 21C (Montana Avenue), continue on Gateway Boulevard South, and re-enter southbound US 54 south of Yandell Drive.
  • Crews will be placing concrete safety barriers

Wednesday, May 22, and Thursday, May 23
Nightly 9 p.m. to 5 a.m.

  • All lanes of southbound US 54 will be closed to all traffic south of Spur 601.
  • The ramp from westbound Spur 601 to southbound US 54 will be closed to all traffic.
  • Detours: All traffic on southbound US 54 must take Exit 22 (Pershing Drive/Fort Bliss), then take the Pershing Drive/Altura Avenue exit, continue on Gateway Boulevard South, and re-enter US 54 north of Pershing Drive.
  • All traffic bound from westbound Spur 601 to US 54 will go northbound on US 54; traffic seeking to head south will take Exit 25 (Ellerthorpe Avenue) and U-turn.
  • Crews will be placing concrete safety barriers

Monday, May 20, through Friday, May 31
Daily 9 a.m. to 4 p.m.

  • The on-ramp from Gateway Boulevard North to I-110 near the El Paso Zoo will be closed to all traffic.
  • Detour: Gateway Boulevard North, turn right on SH 20 (Alameda Avenue), left on Raynold Street to I-10.
  • Crews will be preparing to tie in a new ramp to an existing ramp.

Mall Braided Ramps Project

Monday, May 20 (complete closure)
9 p.m. to 5 a.m.

  • I-10 eastbound closure between Airway Boulevard and Viscount Boulevard
  • Crews will be removing dynamic message signs

Monday, May 20 (complete closure)
9 p.m. to 5 a.m.

  • I-10 westbound left lane closure at Airway Boulevard entrance ramp
  • I-10 westbound right shoulder closure at Airway Boulevard entrance ramp
  • Crews will be removing dynamic message signs

Sunday, May 19, through Thursday, May 23 (complete closure)
9 p.m. to 5 a.m.

  • I-10 westbound right shoulder closure at Hawkins Boulevard exit ramp
  • Crews will be painting Viscount Boulevard entrance ramp

Links to full lists of closures:  West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect (New!)

LOCATION DURATION DESCRIPTION
I-10 West at Executive

 

27 Hours

Sunday, May 19

3 am to 6 am the next day

 

·      The main lanes of I-10 West will close completely between Executive Center Boulevard and North Mesa Street.

 

Detour:  Motorists on I-10 West will exit at Executive Center (exit 16), follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) toward the North Mesa entrance ramp to re-enter the main lanes of I-10 West.

 

·      US 85 at McNutt Road will close.

·      The Racetrack Drive entrance ramp to US 85 westbound will close.

·      All Sunland Park westbound ramps will close.

·      The turnaround bridges at Sunland Park Drive will close.

·      The Resler westbound exit ramp will close.

·      The Schuster westbound entrance ramp to I-10 West will close.

 

Crews will be re-striping a portion of I-10 West, installing signs, and moving barrier walls.

 

Paisano at Sunland

 

Three Days

May 21-23

9 am to 4 pm each day

 

·      The left lane on Paisano Drive (US 85) – in front of the auto dealerships – will close starting at Sunland Park Drive.

·      The turnaround bridge, westbound to eastbound, at Sunland Park Drive will close.

 

Crews will be installing signs.

 

I-10 East at Sunland

 

27 Hours

Sunday, June 2

3 am to 6 am the next day

 

·      I-10 East will close completely between Sunland Park Drive and Executive Center Boulevard.

 

Detour:  Motorists on I-10 East will exit at Sunland Park (exit 13), then follow the detour signs to North Mesa Street (SH 20). Motorists may re-enter I-10 East using the Executive Center Boulevard entrance ramp.

 

·      Paisano Drive (US 85) – in front of the auto dealerships – will close completely starting at Sunland Park Drive.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The turnaround bridge, westbound to eastbound, at Sunland Park Drive will close.

·      The Sunland Park flyover ramp will close.

·      The eastbound collector-distributor (CD) lanes will close at Sunland Park.

 

Detour: Motorists on the eastbound CD lanes will be detoured to the signalized intersection at Sunland Park Drive. Motorists will have to turn at the signalized intersection.

 

Crews will be striping a portion of I-10 East and removing barrier, giving relief to the pinched eastbound lanes near Buena Vista.

 

Connect10, Go10, TxDoT work, closures and more for week of May 5

Here’s a look at the project closures for the week ahead, including a 26-hour closure this weekend on the GO10 Project.   Once the closure lifts, the collector-distributor lanes will open along with the turnaround lanes at the Sunland Park Interchange.

Marking the most significant milestone for the GO 10 project, the full length of the I-10 collector-distributor (CD) lanes will open Monday morning, May 6. The CD lanes – eastbound and westbound – are located along I-10 between Buena Vista (mile marker 14) and North Mesa (exit 11).

Access to the CD lanes means drivers will enjoy additional lanes and more vehicular capacity through the I-10 corridor on El Paso’s westside.

It also means a safer corridor because the CD lanes will help to separate local drivers (who live and work on the westside) from long-haul drivers (such as semi-trucks and long-distance commuters).

For the region, it means near completion of Loop 375 thanks to more access to overpasses and ramps in the I-10/Sunland area.

Pictured above is part of the GO 10 project in the Sunland Park area that represents the most complicated section of the entire six-mile GO 10 work zone. Officials say this section will probably benefit most from the CD lanes because its transformation was the most complex. It involved the demolition and rebuilding of seven bridges and the construction of seven bridges that did not exist before.

Opening the CD lanes in this area will be like fully opening a faucet that had been on trickle for the last three years.

Although the CD lanes mark a major win for West El Paso, motorists may expect GO 10 construction activities to be ongoing throughout the six-mile corridor, particularly in the median of I-10 between Sunland Park and approximately mile marker 15.

Crews still have until this summer to finish roadway work while still being on-time and on-budget.

Mesa Park Interchange Project

Monday, Wednesday and Friday May 6, 8 and 10

9 a.m.- 5 p.m. Daily

IH-10 East bound at Executive right lane closure

Crews will be working alongside freeway placing concrete.

 

Wednesday May 8 – Thursday, May 16

9 p.m. – 5 a.m. (nightly closure excluding Friday and Saturday night)

  • Left lane closure I-10 east and westbound
  • Crews will be reconstructing median and left lanes

 

GO10

Sunland Park

26 Hours

Sunday, May 5

4 a.m. to 6 a.m. the next day

  • The Sunland Park exit ramp (Exit 13) from I-10 West will close. Motorists should use an alternate exit ramp.
  • The Sunland Park entrance ramp to I-10 West will close. Motorists should use an alternate entrance ramp.
  • The westbound Resler exit ramp will close. Motorists should use an alternate exit ramp.
  • US 85 westbound overpass, which leads to Sunland Park Drive, will close at McNutt Road.
  • The Racetrack Drive entrance ramp to the US 85 westbound overpass to Sunland Park Drive will close.
  • The Resler flyover entrance ramp to I-10 East will close.
  • The Sunland Park exit ramp from I-10 East will close.
  • MILESTONE:  Crews are aiming to open entire length of collector-distributor (CD) lanes in both directions by 6 am on Monday, May 6.

 

I-10 West at Sunland

Three nights

Monday, May 6 through Wednesday, May 8

9 p.m. each night to 6 a.m. each morning

  • I-10 westbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp.
  • Detour:  Motorists on I-10 West will exit at Sunland Park (exit 13). Follow the detour signs to re-enter I-10 West at the next ramp.
  • Crews will be placing concrete barrier in the I-10/Sunland Park area. Work will be ensuing to open the median of I-10 between Sunland Park and Executive Center.

 

I-10 West at Sunland

One night

Thursday, May 9

9 p.m. to 6 a.m. the next morning

  • I-10 westbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour:  Motorists on I-10 West will exit at Sunland Park (exit 13), then follow the westbound CD lanes to North Mesa Street. Motorists may re-enter I-10 westbound using the North Mesa entrance ramp.
  • The Sunland Park entrance ramp to I-10 West will close.
  • Crews will be re-striping I-10 West.

 

Mall Braided Ramps Project

Sunday, May 5 (complete closure)

9 p.m. to 5 a.m.

  • Gateway Boulevard east closure between Airway Boulevard and Hawkins Boulevard
  • Hawkins Boulevard eastbound exit ramp closed
  • Crews will be removing portable concrete traffic barrier

Monday, May 6 through Friday, May 10

9 a.m. to 4 p.m.

  • Hawkins Boulevard westbound exit ramp closed
  • Crews will be painting bridge

Wednesday, May 8 (complete closure)

9 p.m. to 5 a.m. (overnight)

  • Gateway Boulevard east closure between Airway Boulevard and Hawkins Boulevard
  • Hawkins Boulevard eastbound exit ramp closed
  • Crews will be removing portable concrete traffic barrier, milling and striping

 

Border West Expressway

I-10

Monday, May 6, and Tuesday, May 7
9 p.m. to 5 a.m. (nightly closure)

  • Eastbound two left lanes – closures from Executive to Schuster
  • Closure is needed for roadway work

 

Maintenance  

Monday, May 6 through Friday, May 10
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on US 54 south at Altura to Yandell
  • Montana exit will be closed
  • Left lane closure on Gateway east and west at Piedras to McRae
  • I-10 west exit at Geronimo will be closed
  • I-10 west entrance at Paisano will be closed
  • I-10 west entrance at Trowbridge will be closed
  • I-10 east exit and west entrance at Airway will be closed
  • Right lane closure on I-10 east between Campbell to Cotton

I-10 Connect

Sunday, May 5, and Monday, May 6

9pm to 5am

  • Southbound US 54 south of US 62 (Paisano Drive) will be closed to all traffic.
  • DETOURS: Traffic bound from southbound US 54 to eastbound Loop 375 will take Exit 20A (US 62/Paisano Drive), continue on Gateway Boulevard South, then enter eastbound Loop 375. Traffic bound from southbound US 54 to westbound Loop 375 will take Exit 20A (US 62/Paisano Drive), turn right on Paisano, continue 1.7 miles and enter Loop 375 via Coles Street.
  • Crews will be working on bridge widening.

The Following Long-Term Closures Will Remain In Place During the Week of May 5:

  • Ramp T which connects Gateway Boulevard North to northbound US 54 north of US 62 (Paisano Drive) remains closed until further notice.
  • Both turnarounds between Gateway Boulevard North and Gateway Boulevard South under US 54 at US 62 (Paisano Drive) remain closed until further notice.
  • Turnaround from Gateway Boulevard East to Gateway Boulevard West under I-10 at Trowbridge Drive remains closed until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) at US 54 until further notice.
  • Lane closures are in place on Ramp D which connects southbound US 54 to eastbound I-10 until further notice.
  • Intermittent lane closures on Gateway Boulevard South between Findley Avenue and US 62 (Paisano Drive).

All closures are subject to change due to weather or field conditions. On ramps and off ramps may close up to an hour before stated times.

Full lists of closures: West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect (New!)  |  East Area Projects

LOCATION DURATION DESCRIPTION
Sunland Park

 

26 Hours

Sunday, May 5

4 a.m. to 6 a.m. the next day

 

·      The Sunland Park exit ramp (exit 13) from I-10 West will close. Motorists should use an alternate exit ramp.

·      The Sunland Park entrance ramp to I-10 West will close. Motorists should use an alternate entrance ramp.

·      The westbound Resler exit ramp will close. Motorists should use an alternate exit ramp.

·      US 85 westbound overpass, which leads to Sunland Park Drive, will close at McNutt Road.

·      The Racetrack Drive entrance ramp to the US 85 westbound overpass to Sunland Park Drive will close.

·      The Resler flyover entrance ramp to I-10 East will close.

·      The Sunland Park exit ramp from I-10 East will close.

 

MILESTONE:  Crews are aiming to open the entire length of collector-distributor (CD) lanes in both directions by 6 am on Monday, May 6.  That means:

  • Motorists on I-10 West who wish to take the Resler exit ramp will be able to bypass the traffic signals at Sunland Park Drive.
  • Motorists coming from Resler Drive and who wish to enter I-10 East will be able to bypass the traffic signals at Sunland Park Drive.
  • Motorists on US 85 westbound who wish to enter I-10 West will be able to do so, bypassing the traffic signals at Sunland Park Drive.

 

I-10 West at Sunland

 

Three nights

May 6-8

9 p.m. each night to 6 a.m. each morning

 

·      I-10 westbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp.

·      Detour:  Motorists on I-10 West will exit at Sunland Park (exit 13). Follow the detour signs to re-enter I-10 West at the next ramp.

 

Crews will be placing concrete barrier in the I-10/Sunland Park area. Work will be ensuing to finish the median of I-10 between Sunland Park and Executive Center.

 

I-10 West at Sunland One night

May 9

9 p.m. to 6 a.m. the next morning

 

·      The main lanes of I-10 westbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour:  Motorists on I-10 West will exit at Sunland Park (exit 13), then follow the westbound CD lanes to North Mesa Street. Motorists may re-enter I-10 West using the North Mesa entrance ramp.

·      The Sunland Park entrance ramp to the main lanes of I-10 West will close.

TxDoT, Go10, Connect 10 Detours, Closures and More Starting March 23

Here’s a look at project closures for the week ahead; The big one: there is a 27-hour closure this weekend as crews on the GO10 project work on the final configuration for the Sunland Park intersection.

REMINDER: The I-10 Connect project is underway and has resulted in more long-term closures! Crews will also start a partial bridge demolition this weekend. Make sure you sign up for alerts online. You can also follow the project on social media platforms.

Don’t forget to follow TxDoT on Twitter at @TxDOTELP. PLUS sign up for traffic alerts online. The El Paso District is the only TxDOT District that gets motorists alerts straight to thier inbox.

GO10 – Sunland Park

27-hour Closure Saturday, March 23 at 3 a.m., to Sunday, March 24 at 6 a.m.

  • I-10 westbound will close completely between Executive Center Boulevard and North Mesa Street (SH 20). Detour: Motorists on I-10 westbound will exit at Executive Center (Exit 16) and follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to North Desert Boulevard. Motorists may use the Redd Road entrance ramp to re-enter I-10 westbound.
  • All exit ramps and entrance ramps at I-10 and Sunland Park will close.
  • Sunland Park Drive will close between Constitution Drive and the mall traffic signal lights.
  • The Schuster/UTEP entrance ramp to I-10 westbound will close.
  • The US 85 direct connector westbound bridge, which leads to Sunland Park Drive, will close at McNutt Road.
  • The Racetrack entrance ramp to the US 85 westbound bridge will close.
  • Paisano Drive (US 85) – near the auto dealerships – will close at Sunland Park Drive.
  • Crockett Street access to Paisano Drive (US 85) will close.
  • The Sunland Park flyover entrance ramp to I-10 eastbound will close.
  • The Resler flyover entrance ramp to I-10 eastbound will close.
  • This closure is necessary so crews may setup permanent traffic signals, down permanent striping on Sunland Park Drive, and remove barrier from Sunland Park.
  • Note: The Texas turnaround lanes at the Sunland Park Drive overpass will not open as a result of this closure.

I-10 west at Sunland

Thursday, March 28
9 p.m. to 6 a.m. the next morning

  • The Sunland Park entrance ramp to I-10 westbound will close.
  • I-10 westbound will be reduced to one lane in the Sunland Park area.
  • Milestone: Crews will be working to open the Resler westbound exit ramp. They will also be working to open the new Sunland Park entrance ramp to the westbound main lanes of I-10.

I-10 west

Tuesday, March 26, and Wednesday, March 27
9 p.m. each night to 6 a.m. each morning

  • I-10 westbound will close completely between Executive Center Boulevard and Sunland Park Drive. Detour: Motorists on I-10 westbound will exit at Executive Center (Exit 16), follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to Sunland Park Drive. Motorists may re-enter I-10 westbound at the Sunland Park entrance ramp.
  • The Schuster/UTEP entrance ramp to I-10 westbound will close.
  • Crews will be pouring concrete in the median of I-10 between Sunland Park and Executive Center.

North Mesa

27-hour Closure
Sunday, March 31 at 3 a.m., to Monday, April 1 at 6 a.m.

  • All the exit ramps and entrance ramps at I-10 and North Mesa will close.
  • North Mesa Street (SH 20) will close in both directions between Osborne Drive and Remcon Circle.
  • Crews will be setting up permanent traffic signals, putting down permanent striping on North Mesa, and removing some barrier.

 

Mall Braided Ramps Project

Monday, March 25 (complete closures)
9 p.m. to 5 a.m. (overnight)

  • Gateway West Boulevard at Hawkins Boulevard intersection
  • Gateway East Boulevard to Gateway West Boulevard turnaround at Hawkins intersection
  • Crews will be hanging beams

 

I-10 Connect

Sunday, March 24, to Thursday, March 28
9 p.m. to 5 a.m.

  • US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South each night.
  • Detours: Westbound thru traffic will detour by turning right on Gateway Boulevard North, left on SH 20 (Alameda Avenue) and left on Loop 478 (Copia Street), before returning to US 62 (Paisano Drive). Eastbound thru traffic will detour by turning right on San Marcial Street, left on Delta Drive, and left on Boone Street before returning to US 62 (Paisano Drive). Traffic bound from eastbound US 62 (Paisano Drive) to Juárez via the Bridge of the Americas will not be impacted. Traffic bound from westbound US 62 (Paisano Drive) to Juárez via the Bridge of the Americas should instead access the port of entry by traveling on I-10 to Exit 22B and entering Juárez via I-110.
  • Crews will be demolishing parts of the US 54 bridge over US 62 (Paisano Drive).

Beginning Sunday, March 24 at 9 p.m., and continuing until further notice

  • Ramp T, which connects Gateway Boulevard North to northbound US 54 near the El Paso Zoo, will be closed to all traffic for several months.
  • Detours: Traffic bound for northbound US 54 or westbound I-10 will detour via US 62 (Paisano Drive) to eastbound I-110 before continuing on northbound US 54 or taking Exit 21B (I-10 West/Montana Avenue/Las Cruces). Traffic bound to eastbound I-10 will not require a detour.
  • Crews will begin drilling support shafts for bridges.

Monday, March 25
9 a.m. to 5 p.m.

  • Gateway Boulevard East will be closed to all traffic under the Spaghetti Bowl.
  • Detour: Traffic will detour by entering I-10 east of Loop 478 (Copia Street) and taking Exit 23A/Raynolds Street to return to Gateway East.
  • Durazno Avenue will be closed to thru traffic between Uva Street and Bowie Street
  • Detour: Thru traffic will detour to Rosa Avenue via Uva or Bowie. Local traffic will be allowed to access residential properties via Durazno.
  • Crews will continue placing concrete barriers.

Wednesday, March 27
9 p.m. to 5 a.m.

  • Lane closures will be in place on eastbound I-10 between Loop 478 (Copia Street) and Raynolds Street.
  • The on-ramp from Gateway Boulevard East to I-10 east of Copia will be closed to all traffic.
  • For I-10 traffic, no detour is required. Traffic bound from Gateway East to I-10 will continue on the Gateway and enter I-10 east of Raynolds.
  • Crews will continue placing concrete barriers.

 

Border West Expressway

Loop 375

Friday, March 22, to Monday, March 25
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

I-10

Thursday, March 21
9 p.m. to 5 a.m.

  • Eastbound left lane from Executive Center Boulevard to Schuster Avenue
  • Closure is needed for roadway work

US 85

Tuesday, March 26, to Thursday, March 28
9 p.m. to 5 a.m. (full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Doniphan

Saturday, March 30, to Sunday, March 31
5 a.m. to 6 p.m. (continuous full closure)

  • Eastbound and westbound from Racetrack to Executive
  • Closure is needed for structure work

 

Spalling Repair Project

Saturday, March 23 through Sunday, March 24
6 a.m. to 6 a.m. (48-hour closure)

  • Left two lane closure on Gateway south between Dyer and Julian tank crossing
  • Ellerthorpe exit ramp will be closed

Thursday, March 28
9 p.m. to 5 a.m. (8-hour closure)

  • Right two lane closure on on I-10 westbound at Executive exit ramp
  • Executive exit ramp will be closed

 

US 54 Widening and Illumination Project

Saturday, March 30
5 a.m. to 5 p.m.

  • Full freeway closure main lanes US 54 north and southbound
  • Traffic northbound will exit Hondo Pass and reenter Transmountain
  • Traffic southbound will exit Transmountain and reenter at Hondo Pass

Saturday, April 6
5 a.m. to 5 p.m.

  • Full freeway closure main lanes US 54 north and southbound
  • Traffic northbound will exit Hondo Pass and reenter Transmountain
  • Traffic southbound will exit Transmountain and reenter at Hondo Pass

Links to full lists of closures:  West Area Projects   |   GO10   |   Border West Expressway   |   I-10 Connect   |   East Area Projects

Before crews begin widening US 54 over US 62 (Paisano Drive) as part of the I-10 Connect Project, they’ll begin demolishing parts of the existing US 54 bridge there next week.

That work will require complete overnight closures of Paisano between Gateway Boulevard North and Gateway Boulevard South.

This stretch of US 54 will be widened from two southbound lanes to three as part of the three-year, $96 million project which will dramatically re-shape the Spaghetti Bowl and nearby roadways in Central El Paso.

Elsewhere, motorists should also expect the following upcoming traffic impacts as crews begin drilling support shafts for bridges and continue placing concrete safety barriers:

  • A one-night lane closure on eastbound Interstate 10
  • A long-term closure of Ramp T which connects Gateway Boulevard North to US 54
  • Surface street closures near the Spaghetti Bowl

Below is a detailed list of all closures and detours related to the I-10 Connect Project currently scheduled during the week of March 24:

Sunday, March 24, to Thursday, March 28, 2019 9pm to 5am

  • US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South each night.

DETOURS: Westbound thru traffic will detour by turning right on Gateway Boulevard North, left on SH 20 (Alameda Avenue) and left on Loop 478 (Copia Street), before returning to US 62 (Paisano Drive). Eastbound thru traffic will detour by turning right on San Marcial Street, left on Delta Drive, and left on Boone Street before returning to US 62 (Paisano Drive).

Traffic bound from eastbound US 62 (Paisano Drive) to Juárez via the Bridge of the Americas will not be impacted. Traffic bound from westbound US 62 (Paisano Drive) to Juárez via the Bridge of the Americas should instead access the port of entry by travelling on Interstate 10 to Exit 22B and entering Juárez via I-110.

Crews will be demolishing parts of the US 54 bridge over US 62 (Paisano Drive).

Beginning on Sunday, March 24, at 9pm and continuing until further notice

  • Ramp T which connects Gateway Boulevard North to northbound US 54 near the El Paso Zoo will be closed to all traffic for several months.

DETOURS: Traffic bound for northbound US 54 or westbound I-10 will detour via US 62 (Paisano Drive) to eastbound I-110 before continuing on northbound US 54 or taking Exit 21B (I-10 West/Montana Avenue/Las Cruces). Traffic bound to eastbound I-10 will not require a detour.

Crews will begin drilling support shafts for bridges.

Monday, March 25, 2019, 9am to 5pm

  • Gateway Boulevard East will be closed to all traffic under the Spaghetti Bowl.

DETOUR: Traffic will detour by entering I-10 east of Loop 478 (Copia Street) and taking Exit 23A/Raynolds Street to return to Gateway East.

  • Durazno Avenue will be closed to thru traffic between Uva Street and Bowie Street

DETOUR: Thru traffic will detour to Rosa Avenue via Uva or Bowie. Local traffic will be allowed to access residential properties via Durazno. Crews will continue placing concrete barriers.

Wednesday, March 27, 2019, 9pm to 5am

  • Lane closures will be in place on eastbound I-10 between Loop 478 (Copia Street) and Raynolds Street.
  • The on-ramp from Gateway Boulevard East to I-10 east of Copia will be closed to all traffic.

DETOURS: For I-10 traffic, no detour is required. Traffic bound from Gateway East to I-10 will continue on the Gateway and enter I-10 east of Raynolds. Crews will continue placing concrete barriers.

The following long-term closures will continue during the week of March 24:

  • Weekday lane closures on Gateway Boulevard North between US 62 (Paisano Drive) and SH 20 (Alameda Avenue). Crews will be installing fiber optic communication lines.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) between Gateway Boulevard North and I-110.
  • Both u-turns between Gateway Boulevard North and Gateway Boulevard South at US 62 (Paisano Drive) remain closed until further notice.

Drivers are encouraged to register for text alerts and electronic newsletter distribution by visiting i10connectelpaso.com. All closures are subject to change due to weather or field conditions. On ramps and off ramps may close up to an hour before stated times.

LOCATION DURATION DESCRIPTION
I-10 West and Sunland Park

 

27 HOURS

SATURDAY, March 23 at 3 am

until

Sunday, March 24 at 6 am

 

·      I-10 Westbound will close completely between Executive Center Boulevard and North Mesa Street (SH 20).

 

Detour: Motorists on I-10 Westbound will exit at Executive Center (Exit 16) and follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to North Desert Boulevard. Motorists may use the Redd Road entrance ramp to re-enter I-10 Westbound.

 

·      All exit ramps and entrance ramps at I-10 and Sunland Park will close.

·      Sunland Park Drive will close between Constitution Drive and the mall traffic signal lights.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

·      The US 85 direct connector westbound bridge, which leads to Sunland Park Drive, will close at McNutt Road.

·      The Racetrack entrance ramp to the US 85 westbound bridge will close.

·      Paisano Drive (US 85) – near the auto dealerships – will close at Sunland Park Drive.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

 

This closure is necessary so crews may setup permanent traffic signals, lay down permanent striping on Sunland Park Drive, and remove barrier from Sunland Park.

 

I-10 West

 

Overnight

March 26 and 27

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close completely between Executive Center Boulevard and Sunland Park Drive.

 

Detour: Motorists on I-10 Westbound will exit at Executive Center (Exit 16), follow Executive Center Boulevard to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to Sunland Park Drive. Motorists may re-enter I-10 Westbound at the Sunland Park entrance ramp.

 

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Crews will be pouring concrete in the median of I-10 between Sunland Park and Executive Center.

 

I-10 West at Sunland

 

Overnight

March 28

9 pm to 6 am the next morning

 

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      I-10 Westbound will be reduced to one lane in the Sunland Park area.

 

Milestone: Crews will be working to open the Resler westbound exit ramp. They will also be working to open the new Sunland Park entrance ramp to the westbound main lanes of I-10.

 

North Mesa

 

27 HOURS

Sunday, March 31 at 3 am

until

Monday, April 1 at 6 am

 

·      All the exit ramps and entrance ramps at I-10 and North Mesa will close.

·      North Mesa Street (SH 20) will close in both directions between Osborne Drive and Remcon Circle.

 

Crews will be setting up permanent traffic signals, laying down permanent striping on North Mesa, and removing some barrier.

 

STEP 728
Rugby Coming Soon 728
Utep Football Generic 728
EP MediaFest 2020 728
Mountains 728
ENTERPRISE 728
Amy’s Astronomy
Rhinos 2019/2020 728
Towntalk Teaser 728
Bordertown Undergroun Show 728