Connect10/Go10/TxDot projects, detours, closures for Week of April 21

Much of the work on the Go10 project this week is focused on opening the eastbound and westbound CD lanes. The CD lanes could be open by mid-May.

GO10

I-10 East at Sunland

Monday, April 22
9 p.m. to 6 a.m.

  • The main lanes of I-10 eastbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists on I-10 eastbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 East at the next ramp.
  • Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.
  • Crews will continue to install a pedestrian fence along the Sunland Park overpass.

 

Sunland Park

Tuesday, April 23
9 a.m. to 4 p.m.

  • The Sunland Park flyover entrance ramp to I-10 East and to US 85 East will close.
  • Crews will be installing a permanent barrier rail in the area.

 

I-10 East at Mesa

Tuesday, April 23
9 p.m. to 6 a.m.

  • I-10 eastbound will be reduced to one lane for approximately 2,000 feet starting prior to reaching the North Mesa exit ramp (Exit 11). The North Mesa eastbound exit will remain open.
  • Crews will be installing permanent signage in the shoulder of I-10 East.

 

Resler and Sunland Ramps

Tuesday, April 23, and Wednesday, April 24
9 p.m. each night to 6 a.m. each morning

  • The Resler entrance ramp to the eastbound CD lanes will close.
  • The eastbound Sunland Park exit ramp from I-10 will close. Motorists on I-10 East who wish to access Sunland Park Drive should use the North Mesa exit ramp (Exit 11).
  • Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.
  • Crews will be re-striping the eastbound CD lanes, installing permanent signage, and installing a pedestrian fence along the Sunland Park overpass.

 

I-10 Connect

Wednesday, April 24, from 9 p.m. to 5 a.m.
and Thursday, April 25, from 9 p.m. to 5 a.m.

  • US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South.
  • Detour: Westbound traffic will turn right on Gateway North, left on SH 20 (Alameda Avenue), left on Loop 478 (Copia Street), and then rejoin Paisano. Eastbound traffic will turn right on San Marcial Street, left on Delta Drive, left on Boone Street, and then rejoin Paisano.
  • Crews will begin placing support columns.

Sunday, April 28, at 3 a.m. to Monday, April 29, at 6 a.m.

  • Eastbound Interstate 10 will be closed to all traffic at US 54.
  • The on-ramp that connects Gateway Boulevard East to eastbound I-10 east of Loop 478 (Copia Street) will be closed to all traffic.
  • Detour: Eastbound traffic on I-10 will take Exit 22A (Loop 478/Copia Street), continue east on Gateway Boulevard East, and re-enter I-10 east at Raynolds Street.
  • Crews will be removing old pavement, placing new pavement, re-striping travel lanes and placing safety barriers.
  • Traffic on westbound I-10 will not be impacted by this work. However, a similar 27-hour closure of westbound I-10 at US 54 will be required in the coming weeks.

 

Maintenance  

Monday, April 22 through Friday, April 26
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on US 54 south at Altura to Yandell
  • Montana exit will be closed
  • Left lane closure on Gateway east and west at Piedras to McRae
  • I-10 west exit at Geronimo will be closed
  • I-10 west entrance at Paisano will be closed
  • I-10 west entrance at Trowbridge will be closed
  • I-10 east entrance and exit at Trowbridge will be closed
  • I-10 east exit and west entrance at Airway will be closed
  • Right lane closure at I-10 west exit to US 54 north exit for 2 days

Mall Braided Ramps Project

Sunday April 21, through Saturday 27 (complete closures)
9 p.m. to 6 a.m. (overnight)

  • Gateway Boulevard (frontage road) eastbound complete closure, form Airway to Hawkins
  • Hawkins Boulevard eastbound exit ramp closed
  • Crews will be working on HMAC

Sunday, April 21, through Friday, April 26 (complete closures)
9 p.m. to 6 a.m. (overnight)

  • Hawkins Boulevard westbound exit ramp closed
  • Crews will be painting bridge

 

Guardrail Repair Project

Tuesday, April 23
9 a.m. to 4 p.m. (throughout the day)

  • Right lane closure on US 54 south between Stan Roberts and Mesquite Hills

Wednesday, April 24
9 a.m. to 4 p.m. (throughout the day)

  • Left lane closure on Gateway south between Vinton intersection to Vinton entrance ramp to I-10
  • Vinton entrance ramp to I-10 east will be closed

Thursday, April 25
9 a.m. to 4 p.m. (throughout the day)

  • Ramp C – US 54 north to I-10 west will be closed
  • Copia westbound exit ramp will be closed

Mesa Park Project 

Monday, April 22, to Thursday, May 2
9 p.m. to 5 a.m. (nightly closure)

  • Left lane closure I-10 east and west
  • Crews will be reconstructing median and left lane

 

Border West Expressway Project

US 85

Wednesday, April 24, to Thursday, May 16
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Friday, April 26, to Monday, May 27
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

 

Loop 375

Friday, April 26, to Monday, April 29
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

 

 

Links to full lists of closures:

 West Area Projects   |   GO10   |   Border West Expressway   |   I-10 Connect   |   East Area Projects

LOCATION DURATION DESCRIPTION
I-10 East at Sunland

 

One Night

Mon, April 22

9 pm to 6 am

 

·      The main lanes of I-10 eastbound will close completely between the Sunland Park exit ramp and the Sunland Park entrance ramp. Detour: Motorists on I-10 eastbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 East at the next ramp.

·      Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.

Sunland Park

 

One Day

Tues, April 23

9 am to 4 pm

 

·      The Sunland Park flyover entrance ramp to I-10 East and to US 85 East will close.

 

I-10 East at Mesa

 

One Night

Tues, April 23

9 pm to 6 am

 

·      I-10 eastbound will be reduced to one lane for approximately 2,000 feet starting prior to reaching the North Mesa exit ramp (Exit 11). The North Mesa eastbound exit will remain open.

 

Resler and Sunland ramps

 

Two Nights

Tues, April 23-Wed, April 24

 

9 pm each night to 6 am each morning

 

·      The Resler entrance ramp to the eastbound CD lanes will close.

·      The eastbound Sunland Park exit ramp from I-10 will close. Motorists on I-10 East who wish to access Sunland Park Drive should use the North Mesa exit ramp (Exit 11).

·      Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.

 

North Mesa exit

 

Four Days

Tues, April 23-Fri, April 26

 

9 am to 4 pm each day

 

·      The westbound North Mesa exit ramp (Exit 11) from I-10 will be reduced by one lane. The dedicated right turn lane will remain open.

 

I-10 West at Sunland

 

One Night

Thur, April 25

9 pm to 6 am

 

·      I-10 westbound will close completely between the Sunland Park exit ramp (Exit 13) and the Sunland Park entrance ramp. Detour: Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 West at the next ramp.

·      Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.

Sunland and Resler ramps

 

Four Nights

Sun, April 28-Wed, May 1

 

9 pm each night to 6 am each morning

·      The Sunland Park entrance ramp to I-10 West will close. Motorists should use an alternate entrance ramp to I-10 West.

·      The westbound CD lanes will close completely starting at Sunland Park Drive.

·      The westbound Resler exit ramp will close. Motorists should use an alternate exit ramp.

 

TxDoT/Go10/10Connect closures, detours for Week of April 13

Long before motorists can drive on them, work is underway on the unseen, underground supports for some of the new direct connector ramps being built as part of the Texas Department of Transportation’s I-10 Connect Project in Central El Paso.

Crews have begun work at several locations on drilled shafts which will support the columns for several new bridges. The shafts are four to five feet in diameter and some extend almost 90 feet below the surface. After the shafts are drilled, workers build a basketlike structure of steel rebar and insert it into the hole. The hole is then filled with concrete on top of which bridge support columns will eventually be built.

Crews are currently drilling shafts for Bridge No. 4 which will connect southbound US 54 to the Bridge of the Americas by flying high over Interstate 10 as well as several new and existing ramps at the Spaghetti Bowl. They are also working on shafts for Bridge No. 8 which will provide direct access from eastbound Loop 375 to eastbound I-10 by running parallel to northbound US 54 over US 62 (Paisano Drive).

The work requires a mobile drill rig, concrete pump and other heavy equipment. To ensure the safety of motorists and workers during these operations, the following closures are scheduled for the week of April 14, 2019:

Sunday, April 14, 2019, 9pm to 5am

  • Westbound US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South.
  • DETOUR: Westbound traffic will turn right on Gateway North, left on SH 20 (Alameda Avenue), left onLoop 478 (Copia Street), and then rejoin Paisano.
  • The ramp which connects Gateway Boulevard North to eastbound Interstate 110 will be closed to all traffic.
  • DETOUR: Traffic seeking to use I-110 to access I-10 will remain on Gateway North, turn right on Alameda and then access I-10 via Raynolds Street.
  • Lane closures will be in place on eastbound Interstate 110 between US 62 (Paisano Drive) and SH 20 (Alameda Avenue).

Crews will be working on drilled shafts.

Monday, April 15, 2019, 9pm to 5am

  • Westbound US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South.
  • DETOUR: Westbound traffic will turn right on Gateway North, left on SH 20 (Alameda Avenue), left onLoop 478 (Copia Street), and then rejoin Paisano.
  •  Southbound US 54 will be closed to all traffic south of US 62 (Paisano Drive).
  • DETOUR: Traffic bound from southbound US 54 to eastbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and proceed straight ahead on Gateway Boulevard South to access eastbound Loop 375. Traffic bound from southbound US 54 to westbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and turn right on Paisano and proceed west for 1.6 mile before turning left on Coles Street to access westbound Loop 375.
  • The ramp which connects Gateway Boulevard North to eastbound Interstate 110 will be closed to all traffic.
  • DETOUR: Traffic seeking to use I-110 to access I-10 will remain on Gateway North, turn right on Alameda and then access I-10 via Raynolds Street.

Crews will be working on drilled shafts.

Tuesday, April 16, through Thursday, April 18, 2019  –  Nightly from 9pm to 5am

  • Southbound US 54 will be closed to all traffic south of US 62 (Paisano Drive).
  • DETOUR: Traffic bound from southbound US 54 to eastbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and proceed straight ahead on Gateway Boulevard South to access eastbound Loop 375. Traffic bound from southbound US 54 to westbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and turn right on Paisano and proceed west for 1.6 mile before turning left on Coles Street to access westbound Loop 375.

Crews will be working on drilled shafts.

The Following Long-Term Closures Will Remain In Place During the Week of April 14:

  • The u-turn from Gateway Boulevard North to Gateway Boulevard South at Pershing Drive remains closed until further notice.
  • Ramp T which connects Gateway Boulevard North to northbound US 54 remains closed until further notice.
  • Both u-turns between Gateway Boulevard North and Gateway Boulevard South at US 62 (Paisano Drive) remain closed until further notice.
  • Lane closures are in place on eastbound and westbound US 62 (Paisano Drive) at US 54 until further notice.
  • Intermittent lane closures on Gateway Boulevard South between Findley Avenue and Paisano Drive (US 62).

All closures are subject to change due to weather or field conditions. On ramps and off ramps may close up to an hour before stated times.

GO10

I-10 East

Saturday, April 13
4 a.m. to 2 p.m.

  • I-10 eastbound will be reduced to one lane at the Resler flyover ramp.
  • Crews will be installing an overhead sign structure.

 

I-10 East

Week 1: Sunday, April 14, and Monday, April 15
Week 2: Sunday, April 21, through Tuesday, April 23
9 p.m. each night to 6 a.m. each morning

  • I-10 eastbound will close completely between the Sunland Park exit ramp (Exit 13) and the Sunland Park entrance ramp. Detour: Motorists on I-10 eastbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 East at the next ramp.
  • Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.
  • Crews will continue to install a pedestrian fence along the turnaround lanes at the Sunland Park overpass.

 

I-10 West

Week 1: Tuesday, April 16, through Thursday, April 18
Week 2: Wednesday, April 24, and Thursday, April 25
9 p.m. each night to 6 a.m. each morning

  • I-10 westbound will close completely between the Sunland Park exit ramp (Exit 13) and the Sunland Park entrance ramp. Detour: Motorists on I-10 westbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 West at the next ramp.
  • Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.
  • Crews will continue to install a pedestrian fence along the turnaround lanes at the Sunland Park overpass.

 

Spalling Repair Project

Saturday, April 13, through Sunday, April 14
6 a.m. to 6 a.m. (48-hour closure)

  • Left two lane closure on Gateway south between Dyer and Julian tank crossing
  • US 54 southbound Ellerthorpe exit ramp will be closed

 

Hawkins/Viscount Operation Improvements Project

Monday, April 15, through Friday, April 19
9 p.m. to 6 a.m. (nightly closure)

  • Complete closure on I-10 East between Hawkins to Viscount
  • Crews will be working on striping in the area
  • Detour: exit Hawkins and reenter at McRae entrance ramp

 

Pothole Repair Project

Monday, April 15
9 a.m. to 4 p.m. (throughout the day)

  • I-10 westbound Copia entrance ramp will be closed
  • I-10 right shoulder at the Copia entrance ramp will be closed

 

Mesa Park Interchange Project

Monday, April 15, to Thursday, May 2
9 p.m. to 5 a.m. (nightly closure)

  • Left lane closure I-10 East and West
  • Crews will be reconstructing median and left lane

 

Guardrail Repair Project

Tuesday, April 16
9 a.m. to 4 p.m. (throughout the day)

  • Railroad entrance ramp to Spur 601 east will be closed

 

Thursday, April 18
9 a.m. to 4 p.m. (throughout the day)

  • Wyoming entrance ramp to I-10 East will be closed

 

Maintenance

Sunday, April 14
7 a.m. to 12 p.m. (throughout the day)

  • Complete closure of Artcraft overpass east and west at I-10

 

Monday, April 15, through Friday, April 19
9 a.m. to 3 p.m. (throughout the day)

  • Alternate lane closure at Desert North at Artcraft (SH 178)
  • Closure at I-10 west at the Artcraft west exit
  • Right lane closure at I-10 west exit to US 54 north exit for two days
  • Right lane closure on US 54 south at Altura to Yandell
  • Montana exit will be closed
  • Left lane closure on Gateway east and west at Piedras to McRae
  • I-10 west exit at Geronimo will be closed
  • I-10 west entrance at Paisano will be closed
  • I-10 east entrance at Copia will be closed
  • I-10 east entrance and exit at Trowbridge will be closed
  • I-10 east exit and west entrance at Airway will be closed

 

Border West Expressway

US 85

Friday, April 12, to Monday, April 15
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

 

Friday, April 26, to Monday, April 29
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

 

Mall Braided Ramps Project

Sunday, April 14, through Friday, April 19 (complete closures)
9 p.m. to 6 a.m. (overnight)

  • Gateway Boulevard (frontage road) eastbound complete closure
  • Hawkins Boulevard eastbound exit ramp closed
  • Crews will be milling

 

Monday, April 15, through Thursday, April 18 (complete closures)
9 a.m. to 4 p.m.

  • Hawkins Boulevard westbound exit ramp closed
  • Crews will be painting bridge

 

I-10 Connect

Sunday, April 14, 9 p.m. to 5 a.m.

  • Westbound US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South.
  • Detour: Westbound traffic will detour by turning right on Gateway North, left on SH 20 (Alameda Avenue), left on Loop 478 (Copia Street), and then rejoining Paisano.
  • The ramp which connects Gateway Boulevard North to eastbound Interstate 110 will be closed to all traffic.
  • Detour: Traffic seeking to use I-110 to access I-10 will detour by remaining on Gateway North, turning right on Alameda, and then accessing I-10 via Raynolds Street.
  • Lane closures will be in place on eastbound I-110 between US 62 (Paisano Drive) and SH 20 (Alameda Avenue).
  • Crews will be working on drilled shafts.

Monday, April 15, 9 p.m. to 5 a.m.

  • Westbound US 62 (Paisano Drive) will be closed to all traffic between Gateway Boulevard North and Gateway Boulevard South.
  • Detour: Westbound traffic will detour by turning right on Gateway North, left on SH 20 (Alameda Avenue), left on Loop 478 (Copia Street), and then rejoining Paisano.
  • Southbound US 54 will be closed to all traffic south of US 62 (Paisano Drive).
  • Detour: Traffic bound from southbound US 54 to eastbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and proceed straight ahead on Gateway Boulevard South to access eastbound Loop 375. Traffic bound from southbound US 54 to westbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and turn right on Paisano and proceed west for 1.6 miles before turning left on Coles Street to access westbound Loop 375.
  • The ramp which connects Gateway Boulevard North to eastbound I-110 will be closed to all traffic.
  • Detour: Traffic seeking to use I-110 to access I-10 will detour by remaining on Gateway North, turning right on Alameda, and then accessing I-10 via Raynolds Street. 

Tuesday, April 16, through Thursday, April 18, 2019
Nightly from 9 p.m. to 5 a.m.

  • Southbound US 54 will be closed to all traffic south of US 62 (Paisano Drive).
  • Detour: Traffic bound from southbound US 54 to eastbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and proceed straight ahead on Gateway Boulevard South to access eastbound Loop 375. Traffic bound from southbound US 54 to westbound Loop 375 will take Exit 20A (US 62/Paisano Drive) and turn right on Paisano and proceed west for 1.6 miles before turning left on Coles Street to access westbound Loop 375.
  • Crews will be working on drilled shafts.

Links to full lists of closures:

 West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect (New!)

 

LOCATION DURATION DESCRIPTION
I-10 East at Mesa

 

Daytime

Saturday, April 13

4 am to 2 pm

 

·      I-10 Eastbound will be reduced to one lane between the North Mesa overpass and the Resler flyover ramp.
I-10 East at Sunland

 

Overnight

April 14 and 15

 

9 pm each night to 6 am each morning

 

·      I-10 Eastbound will close completely between the Sunland Park exit ramp (Exit 13) and the Sunland Park entrance ramp. Detour: Motorists on I-10 Eastbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 East at the next ramp.

·      Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.

 

I-10 West at Sunland Overnight

April 16-18

 

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close completely between the Sunland Park exit ramp (Exit 13) and the Sunland Park entrance ramp. Detour: Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 West at the next ramp.

·      Sunland Park Drive at the I-10 overpass will have one lane closed in each direction.

 

Video+Info: Work Begins on I-10 Connector; Other Projects Continue

Plenty of projects around town, including the new I-10 Connector project at the Spaghetti Bowl.  Below are links to information on each closure and details about each project.

  • I-10 Connect project is underway! For the next month, crews will be installing concrete barrier to ready work areas. This will result in many overnight closures. The first start on SUNDAY! A hyperlink to the FULL list is below. Maps can be found HERE. Make sure you check the NEW link below and sign up for alerts. You can also follow the project on social media platforms.
  • 27-hour closure on Mesa for our GO10 project is this weekend. Plan accordingly if you plan to be in that area between Sunday 3a.m. and Monday 6a.m., then be careful Monday morning as eastbound traffic on Mesa will experience a traffic shift between Osborne and Remcon.

GO10

North Mesa

27-hour Closure
Sunday, March 3 at 3 a.m., to Monday, March 4 at 6 a.m.

  • All exit ramps and entrance ramps at the I-10/North Mesa interchange will close.
  • South Desert Boulevard will close at McClintock Street.
  • North Mesa Street (SH 20) will close in both directions between Osborne Drive and Remcon Circle.
  • Milestone: Once this 27-hour closure lifts, lanes on North Mesa Street (SH 20) between Osborne and Remcon will be in their final configuration, and driveways to nearby businesses will be restored.
  • Note: If this work activity is canceled, then it will be rescheduled for March 10-11.

 

I-10 Westbound

Monday, March 4, and Tuesday, March 5
9 a.m. to 4 p.m. each day

  • The right lane on I-10 westbound will be closed for approximately 1,300 feet starting at approximately mile marker 15 (the Top Golf area).
  • Note: This lane closure will reduce I-10 westbound from three lanes to two lanes.
  • Crews will be in the area working on the traffic camera system.

 

Mesa Park Interchange project

Tuesday, March 5 through Thursday, March 7
9 a.m. to 4 p.m. (throughout the day)

  • Westbound exit ramp at Executive will be closed
  • Crews will be working to reconstruct proposed ramp

 

Wednesday, March 6 through Friday, March 8
9 a.m. to 4 p.m. (throughout the day)

  • Eastbound entrance ramp at Executive will be closed
  • Crews will be working to reconstruct proposed ramp

 

Spalling Repair project

Saturday, March 2 through Sunday, March 3
6 a.m. to 6 a.m. (48 hours)

  • Two right lanes at Gateway west at Airway will be closed
  • The right turn lane from Gateway west to Airway northbound will also be closed
  • Crews will be repairing spalled concrete pavement in the area

 

Hawkins/Viscount Operation Improvements project

Monday, March 4 through Saturday, March 9
9 a.m. to 4 p.m. (throughout the day)

  • Right lane closure on Gateway east between Robert E. Lee to Hawkins
  • Crews will be working on electrical work in the area

 

Border West Expressway

Loop 375

Monday, March 4, to Friday, March 8
9 a.m. to 4 p.m.

  • Alternative westbound and eastbound lane closures from Park Street to San Marcial Street
  • Closure is needed for roadway work

 

Friday, March 8, to Monday, March 11
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Oregon Street to US 54
  • Closure is needed for roadway work

 

I-10 Connect

Sunday, March 3, to Monday, March 4
9 p.m. to 5 a.m.

  • Ramp N, which connects eastbound Loop 375 to northbound US 54, will be closed to all traffic.
  • Lane restrictions will be in place on northbound US 54 at US 62 (Paisano Drive).
  • Crews will be installing traffic barriers.

Monday, March 4, to Tuesday, March 5
9 p.m. to 5 a.m.

  • Ramp N, which connects eastbound Loop 375 to northbound US 54, will be closed to all traffic.
  • Ramp O, which connects westbound Loop 375 to northbound US 54, will be closed to all traffic.
  • Crews will be installing traffic barriers.

Tuesday, March 5, to Wednesday, March 6
9 p.m. to 5 a.m.

  • Ramp R, which connects westbound Loop 375 to Gateway North Boulevard, will be closed to all traffic.
  • Ramp T, which connects Gateway North Boulevard to US 54, will be closed to all traffic.
  • Lane restrictions will be in place on Gateway North Boulevard.
  • Crews will be installing traffic barriers.

Wednesday, March 6, to Thursday, March 7
9 p.m. to 5 a.m.

  • The ramp that connects Gateway North Boulevard to eastbound I-110 will be closed to all traffic.
  • Crews will be installing traffic barriers.

Thursday, March 7, to Friday, March 8
9 p.m. to 5 a.m.

  • Ramp T, which connects Gateway North Boulevard to northbound US 54, will be closed to all traffic.
  • Lane restrictions will be in place on northbound US 54 at US 62 (Paisano Drive).
  • Crews will be installing traffic barriers.

 

Loop 375 South Frontage Road Project

Monday, March 4
9 a.m. to 4 p.m.

  • Loop 375 southbound Zaragoza Road exit ramp closed
  • Crews will be installing portable traffic control barrier and temporary striping

Links to full lists of closures:

 West Area Projects  |  GO10  |  Border West Expressway  |  I-10 Connect   | East Area Projects

LOCATION DURATION DESCRIPTION
North Mesa

 

27 HOURS

Sunday, March 3 at 3 am

until

Monday, March 4 at 6 am

 

·      All exit ramps and entrance ramps the I-10/North Mesa interchange will close.

·      South Desert Boulevard will close at McClintock Street.

·      North Mesa Street (SH 20) will close in both directions between Osborne Drive and Remcon Circle.

 

Milestone:  Once this 27-hour closure lifts, lanes should be in their final configuration and driveways to nearby businesses will be restored.

 

Note:  If this work activity is canceled, then it will be re-scheduled for March 10-11.

 

I-10 Westbound

 

Daytime

March 4 and 5

9 am to 4 pm each day

 

·      The right lane on I-10 Westbound will be closed for approximately 1,300 feet starting at approximately mile marker 15 (the Top Golf area). Note: This lane closure will reduce I-10 Westbound from three lanes to two lanes.

 

Crews will be in the area working on the traffic camera system.

 

TxDoT, Go10 Closures, Detours for Week of December 16

Here are the project closures for the week ahead. They include a 27-hour closure at Mesa that will result in a traffic switch and an overnight closure of the Anthony overpass.

More highlights and the complete closure lists via hyperlinks are below.

This 27-hour closure will result in a Phase 3 lane pattern change on North Mesa Street (SH 20). Phase 3 will allow crews begin the three-month process to upgrade the remaining section of pavement on North Mesa Street (SH 20).

Mesa Park Interchange Project 

Friday, Dec. 14 through Monday, Dec. 17
9 p.m. to 6 a.m. (57-hour continuous closure)

  • I-10 eastbound Executive entrance ramp will be closed
  • Saturday, Dec. 15, during the morning hours, traffic will enter I-10 eastbound under a temporary ramp, while the old adjacent entrance ramp undergoes construction
  • Monday morning traffic will be using a new portion of the Executive eastbound entrance ramp
  • To avoid congestion in the area, traffic should seek alternate routes through Sunland Park, Schuster or Downtown entrance/exit ramps in the area.

Sunday, Dec. 16
9 p.m. to 6 a.m. (one night only)

  • Two right lane closures on I-10 eastbound at the Executive underpass
  • Crews will be installing temporary pavement marking and placement of barrier
  • All freeway ramps at Executive will be closed

Wednesday, Dec. 19
9 p.m. to 6 a.m. (one night only)

  • Complete closure on I-10 westbound at Schuster
  • Detour: Westbound traffic will need to take N. Mesa and re-enter at the Sunland Park entrance ramp
  • Crews will be placing concrete pavement on the center median

 

Westway Project Phase III

Monday, Dec. 17 into Tuesday, Dec. 18
8 p.m. to 6 a.m. (one night only)

  • Complete closure at the Anthony overpass
  • Anthony Bridge will be closed
  • Detour: North and southbound traffic will need to use alternate routes, by accessing the frontage road

 

GO10

I-10 and North Mesa

27-hour Closure
Sunday, Dec. 16 at 3 a.m. to Monday, Dec. 17 at 6 a.m.

  • I-10 eastbound will close at Redd Road (Exit 9).
  • North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.
  • All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close.
  • South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).
  • McClintock Drive access to South Desert Boulevard will close.
  • Lane pattern change: This closure will result in re-configured traffic lane patterns on North Mesa Street (SH 20) at the I-10 overpass. Motorists should continue to approach the area cautiously. Expect delays.

I-10 West at Executive

Sunday, Dec. 16 through Thursday, Dec. 20
9 p.m. each night to 6 a.m. each morning

  • I-10 westbound will close between Executive Center Boulevard and Sunland Park Drive.
  • The Schuster/UTEP entrance ramp to I-10 westbound will close.
  • Detour: Motorists on I-10 westbound will exit at Executive Center (Exit 16), follow Executive Center Boulevard to North Mesa Street, then follow North Mesa to Sunland Park Drive. Motorists may re-enter I-10 westbound via the Sunland Park entrance ramp.

Sunland/US 85 Direct Connector

Daily Closure
Monday, Dec. 17 at 9 a.m. through Friday, Dec. 21 at 4 p.m.

  • The direct connector ramp from the Sunland Park flyover ramp to Paisano (US 85) will close.
  • Clarification: The Sunland Park flyover entrance ramp to I-10 eastbound will be open, but the option to connect to Paisano (US 85) will be closed.
  • This closure is necessary while crews access the direct connector ramp to haul debris.

North Mesa

Monday, Dec. 17 through Thursday, Dec. 20
8 p.m. each night to 6 a.m. each morning

  • The eastbound lanes on North Mesa Street (SH 20) – traveling in the direction from Osborne to Remcon – will close between Osborne Drive and Remcon Circle.
  • The North Mesa exit ramp (Exit 11) from I-10 westbound will close.
  • The North Mesa entrance ramp to I-10 eastbound will close.
  • The North Mesa exit ramp (Exit 11) from I-10 eastbound will be open; however, exiting vehicles will be forced to turn right onto North Mesa Street (SH 20) at the signalized intersection.
  • The North Mesa entrance ramp to I-10 westbound will be open.
  • By this time, traffic lane patterns will have been re-configured on North Mesa Street (SH 20), and crews will begin the three-month process of upgrading the remaining section of pavement on North Mesa Street (SH 20).

I-10

Thursday, Dec. 20
9 p.m. to 5 a.m.

  • Eastbound left lane from Executive Center Boulevard to Schuster Avenue
  • Closure is needed for traffic switch work

US 85

Monday, Dec. 17 to Thursday, Dec. 21
9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

 

Links to FULL lists of closures:

West Area Projects  |  GO10  |  Border West Expressway  |  East Area Projects

LOCATION DURATION DESCRIPTION
I-10 and North Mesa

 

27 HOURS

Sunday, Dec. 16 at 3 am

to

Monday, Dec. 17 at 6 am

 

·      I-10 Eastbound will close at Redd Road (Exit 9).

·      North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.

·      All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

·      McClintock Drive access to South Desert Boulevard will close.

 

LANE PATTERN CHANGE:  This closure will result in re-configured traffic lane patterns on North Mesa Street (SH 20) at the I-10 overpass. Motorists should continue to approach the area cautiously. Expect delays.

 

I-10 West at Executive

 

Overnight

Dec. 16-20

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close between Executive Center Boulevard and Sunland Park Drive.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Detour: Motorists on I-10 Westbound will exit at Executive Center (Exit 16), follow Executive Center Blvd to North Mesa Street, then follow North Mesa to Sunland Park Drive. Motorists may re-enter I-10 Westbound via the Sunland Park entrance ramp.

 

Sunland/US 85 Direct Connector

 

Daytime

Dec. 17-21

9 am to 4 pm each day

 

·      The connector ramp from the Sunland Park flyover ramp to Paisano (US 85) will close.

 

Clarification:  The Sunland Park flyover entrance ramp to I-10 Eastbound will be open; but, the option to use the connector ramp from the flyover ramp to Paisano (US 85) will be closed.

 

This closure is necessary while crews haul debris through the area.

 

North Mesa

 

Overnight

Dec. 17-20

9 pm each night to 6 am each morning

 

·      The eastbound lanes on North Mesa Street (SH 20) – traveling in the direction from Osborne to Remcon – will close between Osborne Drive and Remcon Circle.

·      The North Mesa exit ramp (Exit 11) from I-10 Westbound will close.

·      The North Mesa entrance ramp to I-10 Eastbound will close.

·      The North Mesa exit ramp (Exit 11) from I-10 Eastbound will be open; however, exiting vehicles will be forced to turn right onto North Mesa Street (SH 20) at the signalized intersection.

·      The North Mesa entrance ramp to I-10 Westbound will be open.

 

By this time, traffic lane patterns will have been re-configured on North Mesa Street (SH 20).  Dec. 17 is the first night that crews begin the three-month process of upgrading the remaining section of pavement on North Mesa Street (SH 20).

  

North Mesa

 

Developing – details may change

 

27 HOURS

Sunday, Jan. 6 at 3 am

to

Monday, Jan. 7 at 6 am

 

Developing – details may change

 

·      I-10 Eastbound will close between Redd Road and Sunland Park Drive.

·      The North Mesa Street entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists will exit at Redd Road (Exit 9), follow Redd Road to Doniphan Drive, then follow Doniphan Drive to Sunland Park Drive. Motorists may re-enter I-10 Eastbound via the Sunland Park Drive entrance ramp.

 

LANE PATTERN CHANGE: Crews plan to change traffic lane patterns for motorists on I-10 Eastbound between North Mesa Street (SH 20) and Resler Drive. Once the 27-hour closure lifts, motorists can expect to be driving on the main lanes of I-10 after several months of driving on the collector-distributor (CD) lanes, which run alongside I-10’s main lanes.

 

Go10/TxDoT Detours, Construction for Week of December 2

Next week, nighttime work and closures continue at I-10/North Mesa and I-10/Sunland Park.

The next 27-hour closure is scheduled for Sunday, Dec. 9 at Sunland Park with the goal of opening more lanes on the Sunland Park Drive main overpass.

All closures are subject to change or cancelation due to weather. Updates are posted on the GO 10 website, Twitter, and Facebook.

GO10

North Mesa

Overnight

Sunday, December 2 through Thursday, December 6

8 p.m. each night to 6 a.m. each morning

  • North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.
  • All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close.
  • South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).
  • McClintock Drive access to South Desert Boulevard will close.
  • Crews will be installing concrete pavement at the I-10/North Mesa intersections.

 

I-10 West at Sunland

Overnight

Sunday, December 2 through Thursday, December 6

9 p.m. each night to 6 a.m. each morning

  • I-10 westbound will close at the Sunland Park exit ramp (Exit 13).
  • Sunland Park Direct Connect closed – Utilize Paisano EBFR to access I-10
  • Detour:  Motorists on I-10 westbound will exit at Sunland Park and immediately re-enter I-10 at the next ramp.
  • Crews will be demolishing concrete pavement in the median of I-10 and hauling the debris away.

 

Sunland Park

27 HOURS

Sunday, December 9 at 3 a.m. until Monday, December 10 at 6 a.m.

  • Sunland Park Drive will close in both directions between Machuca Road and the mall signalized intersection.
  • All Sunland Park exit ramps and entrance ramps at I-10 will close.
  • Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273).
  • The Racetrack Drive entrance ramp to westbound Paisano Drive (US 85) will close.
  • LANE PATTERN CHANGE:  The goal is to open more traffic lanes on the Sunland Park Drive middle overpass.
  • WEATHER NOTE:  This work activity is dependent on weather temperatures and, therefore, is subject to change.

 

Border West Expressway

Executive Center Blvd.

Saturday, December 8 to Sunday, December 9

6 a.m. to 10 p.m. (Continuous full closure)

  • Westbound and eastbound from I-10 to US 85
  • Closure is needed for roadway work

 

US 85

Saturday, December 1 to Sunday, December 2

4 a.m. to 6 p.m. (Continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco St.
  • Closure is needed for bridge work

Monday, December 3 to Thursday, December 6

9 p.m. to 5 a.m. (nightly full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco St.
  • Closure is needed for bridge work

 

Mesa Park Interchange Project 

Executive

Friday, Dec. 7 through Monday, Dec. 10
8 p.m. to 6 a.m. (continuous closure)

  • I-10 eastbound Executive entrance ramp will be closed
  • Monday, Dec. 10 during the morning hours traffic will enter I-10 eastbound under a temporary ramp, while the old adjacent entrance ramp undergoes construction
  • Traffic Signal outage to occur on Saturday morning between 6 a.m. to 9 a.m.
  • To avoid congestion in the area, traffic should seek alternate routes through Schuster or Downtown entrance ramps.

 

Alameda Pedestrian Improvements Project

Monday, Dec. 3 (until further notice)
7 a.m. to 4 p.m.

  • Right lane closure along Alameda Avenue (SH 20) between Flicker Way and Delta Drive
  • Closure is necessary for proposed construction of extending existing box culvert, RCP (reinforced concrete pipe) culvert, pedestrian and driveway improvements
  • Crews will be placing portable traffic control barrier and delineators

 

Alameda Reconstruction Project

Monday, Dec. 3 through Friday, Dec. 21
8 p.m. to 5 a.m. and 9 a.m. to 3 p.m.

  • Alameda Avenue (SH 20) eastbound and westbound alternating lane closures between Padres Drive and Loop 375
  • Crews will be removing existing striping and install new striping

Monday, Dec. 3 through Friday, Dec. 21
8 a.m. to 3 p.m. and 8 p.m. to 5 a.m.

  • Alternating westbound lane closures between Alameda Avenue (SH 20) and Presa Place
  • Crews will be installing water main placement

 

Night Work  

Thursday, Dec. 6
9 p.m. to 3 a.m. (one night only)

  • Right lane closure on I-10 westbound between the Dallas exit ramp to the Mesa exit ramp
  • Westbound Dallas entrance ramp will be closed
  • Westbound Mesa exit ramp will be closed

 

Maintenance  

Monday, Dec. 3 through Friday, Dec. 7
9 a.m. to 3 p.m. (throughout the day)

  • Alternate lane closures on I-10 east and westbound between Stateline to Redd Road
  • Right lane closure on South Desert Boulevard between Thorn Avenue to Graphite Drive
  • Left lane closure on North Desert Boulevard between Artcraft to Transmountain
  • Northbound Artcraft entrance ramp to I-10 will be closed
  • Eastbound Global Reach exit ramp on Spur 601 will be closed
  • Alternate lane closures on Bomarc north and southbound between Gateway Boulevard East and Gateway Boulevard West, crews will be working under the overpass.

 

Guardrail Repair Project

Thursday, Nov. 29
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on US 54 northbound between the Ellerthorpe entrance ramp to the Hondo Pass exit ramp
  • Northbound Ellerthorpe entrance ramp will be closed

Friday, Nov. 30
9 a.m. to 3 p.m. (throughout the day)

  • Left lane closure on Gateway Boulevard East between at the Copia intersection to Raynolds

Monday, Dec. 3
9 a.m. to 3 p.m. (throughout the day)

  • Left lane closure on Transmountain (Loop 375) eastbound between the Paseo del Norte entrance ramp to the Main Gap

Tuesday, Dec. 4
9 a.m. to 3 p.m. (throughout the day)

  • Alternate lane closure on Gateway Boulevard West between Airway Boulevard to Geronimo Boulevard
  • Robert E. Lee will be closed in the area

Wednesday, Dec. 5
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on Ramp K (US 54 south to I-10 west) southbound between the Montana exit ramp to the Piedras exit ramp
  • Westbound Piedras exit ramp will be closed

Thursday, Dec. 6
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on US 54 southbound between the Dyer exit ramp to the Spur 601 exit ramp
  • Southbound Ellerthorpe exit ramp will be closed
  • Southbound Spur 601 exit ramp will be closed
  • Alternate lane closure on Wyoming eastbound between Mesa Street and Kansas Street

Links to full lists of closures:

West Area Projects  |  GO10  |  Border West Expressway  |  East Area Projects

LOCATION DURATION DESCRIPTION
North Mesa

 

Overnight

Dec. 2-6

8 pm each night to 6 am each morning

 

·      North Mesa Street (SH 20) will close in both directions between Remcon Circle and Osborne Drive.

·      All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

·      McClintock Drive access to South Desert Boulevard will close.

 

Crews will be installing concrete pavement at the I-10/North Mesa intersections.

 

I-10 West at Sunland

 

Overnight

Dec. 2-6

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close at the Sunland Park exit ramp (Exit 13).

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists on I-10 Westbound will exit at Sunland Park and immediately re-enter I-10 at the next ramp.

 

Crews will be demolishing concrete pavement in the median of I-10 and hauling away debris.

 

Sunland Park

 

27 HOURS

Dec. 9 at 3 am

until

Dec. 10 at 6 am

 

·      Sunland Park Drive will close in both directions between Machuca Road and the mall signalized intersection.

·      All Sunland Park exit ramps and entrance ramps at I-10 will close.

·      Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273).

·      The Racetrack Drive entrance ramp to westbound Paisano Drive (US 85) will close.

 

LANE PATTERN CHANGE:  The goal is to open more traffic lanes on the Sunland Park Drive middle overpass.

 

WEATHER NOTE:  This work activity is dependent on weather, therefore, is subject to change.

 

TxDoT/Go10 Project Closures, Detours for Week of November 4

Here’s a look at the TxDoT and Go10 project closures for the week ahead.  In addition, there is a major milestone scheduled for this month.

On November 11 and 18, GO 10 crews plan to OPEN the Sunland Park main overpass in two phases.

Opening the overpass will require two 27-hour closures of the I-10/Sunland Park interchange. As always, all closures are subject change or cancelation due to weather. Updates are being posted to the GO 10 website.

US 54 Widening and Illumination Project

Wednesday, Nov. 7
9 p.m. to 6 a.m. (one night only)

  • Complete closure on US 54 southbound between Transmountain to Hondo Pass
  • Detour: Southbound traffic will need to exit at the Transmountain exit ramp and re-enter at the Hondo Pass entrance ramp (existing ramp will be closed and the new ramps will be opened)

Sunday, Nov. 11
9 p.m. to 6 a.m. (one night only)

  • Complete closure on US 54 northbound between Transmountain to Hondo Pass
  • Detour: Southbound traffic will need to exit at the Hondo Pass exit ramp and re-enter at the Transmountain entrance ramp (existing ramp will be closed and the new ramps will be opened)
  • Diana underpass will open upon completion of work in the area. (until further notice)

 

Go10

I-10 Both Directions

Sunday, Nov. 4 through Thursday, Nov. 8
8 p.m. each night to 6 a.m. each morning

  • I-10 eastbound will close at Sunland Park (Exit 13). Detour: Motorists will exit at Sunland Park and immediately re-enter I-10 eastbound at the next ramp.
  • I-10 westbound will close at Executive Center (Exit 16). Detour: Motorists will exit at Executive Center, then follow the detour signs to North Mesa Street (SH 20). The North Mesa entrance ramp to I-10 westbound will be open.
  • Sunland Park Drive will close in both directions at the I-10 overpass. Detour: Motorists should use an alternate route.
  • Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273).
  • Both Sunland Park entrance ramps to I-10 eastbound will close.
  • Crockett Street access to Paisano Drive (US 85) will close.
  • The Resler flyover entrance ramp to I-10 eastbound will close.
  • The Sunland Park entrance ramp to I-10 westbound will close.
  • The Schuster/UTEP entrance ramp to I-10 westbound will close.
  • Crews will be making a lane pattern change on the eastbound Sunland Park exit ramp.

 

North Mesa

Monday, Nov. 5 through Thursday, Nov. 8
8 p.m. each night to 6 a.m. each morning

  • North Mesa Street (SH 20) eastbound lanes (traveling in the direction toward Remcon) will close between Osborne Drive and Remcon Circle.
  • The North Mesa entrance ramp to I-10 eastbound will close. Detour: Motorists should use an alternate entrance ramp. Note: The Sunland Park eastbound entrance ramps will be closed during this time.
  • The North Mesa exit ramp from I-10 eastbound will be open; however, motorists will only be able to turn right onto North Mesa Street (SH 20) at the North Mesa signalized intersection.
  • Crews will be installing concrete pavement on North Mesa Street (SH 20).

 

US 85

Friday, Nov. 2 to Tuesday, Nov. 6
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

Friday, Nov. 9 to Monday, Nov. 12
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for bridge work

West Area Project Closures  |  Go10 Closures  |  Border West Expressway Closures  |  East Area Project Closures

LOCATION DURATION DESCRIPTION
I-10 Both Directions

 

Overnight

Nov 4-8

8 pm each night to 6 am each morning

 

·      I-10 Eastbound will close at Sunland Park (Exit 13). Detour: Motorists will exit at Sunland Park and follow Sunland Park Drive to Doniphan Drive, then follow Doniphan Drive to Executive Center Boulevard. Motorists may re-enter I-10 Eastbound at the Executive Center entrance ramp.

·      I-10 Westbound will close at Executive Center (Exit 16). Detour: Motorists will exit at Executive Center, then follow the detour signs to North Mesa Street (SH 20). The North Mesa entrance ramp to I-10 Westbound will be open.

·      Sunland Park Drive will close in both directions at the I-10 overpass. Detour: Motorists should use an alternate route.

·      Paisano Drive (US 85) westbound will close at McNutt Road (NM 273). Detour: Motorists on westbound Paisano Drive (US 85) will exit at McNutt Road (NM 273).

·      Both Sunland Park entrance ramps to I-10 Eastbound will close.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Crews will be painting structures, hauling dirt, and preparing for an upcoming lane pattern change on Sunland Park Drive.

 

North Mesa

 

Overnight

Nov 5-8

8 pm each night to 6 am each morning

 

·      North Mesa Street (SH 20) eastbound lanes (traveling in the direction toward Remcon) will close between Osborne Drive and Remcon Circle.

·      The North Mesa entrance ramp to I-10 Eastbound will close. Detour: Motorists should use an alternate entrance ramp. Note: The Sunland Park eastbound entrance ramps will be closed during this time.

·      The North Mesa exit ramp from I-10 Eastbound will be open; however, motorists will only be able to turn right onto North Mesa Street (SH 20) at the North Mesa signalized intersection.

 

Crews will be installing concrete pavement on North Mesa Street (SH 20).

 

Sunland Park

 

27 HOURS

Sunday, Nov 11 at 3 am until Monday, Nov 12 at 6 am

 

·      The exit ramps and entrance ramps at the I-10/Sunland Park interchange will close.

·      Sunland Park Drive will close in both directions between Machuca Road and South Mesa Hills Drive. Detour: Motorists should use an alternate route.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

 

Detour:  Follow the detour signs in place.

  

TRAFFIC SHIFT, Part 1 of 2: Crews will be re-configuring traffic lane patterns on Sunland Park Drive. By the morning of Nov. 12, traffic on Sunland Park Drive traveling in the direction from South Mesa Hills Drive toward Doniphan Drive will be placed on the main, center overpass of Sunland Park Drive.

 

Sunland Park

 

27 HOURS

Sunday, Nov 18 at 3 am until Monday, Nov 19 at 6 am

 

·      The exit ramps and entrance ramps at the I-10/Sunland Park interchange will close.

·      Sunland Park Drive will close in both directions between Machuca Road and South Mesa Hills Drive. Detour: Motorists should use an alternate route.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

 

Detour:  Follow the detour signs in place.

 

TRAFFIC SHIFT, Part 2 of 2: Crews will be re-configuring traffic lane patterns on Sunland Park Drive. By the morning of Nov. 19, traffic on Sunland Park Drive traveling in the direction from Doniphan Drive toward South Mesa Hills Drive will be placed on the main, center overpass of Sunland Park Drive.

 

WEATHER NOTE: If weather prevents this work activity from taking place on Nov 18, then the traffic shift and the closure of the I-10/Sunland interchange will be re-scheduled to occur over the nights of Nov. 20 and Nov. 21.

 

TxDoT/GO10 Construction, Detours for Week of September 30

Here’s a look at project closures for the week ahead, highlights, detours and complete lists via hyperlinks below.

Don’t forget to follow us on Twitter at @TxDOTELP. PLUS sign up for traffic alerts on www.drivetexas.org

The latest on I-10/Sunland Park

Earlier this month, we told you crews were aiming to complete the Sunland Park Drive main overpass by the end of September.  Due to inclement weather and due to delays at a different location, crews are now aiming for mid-November to open the main overpass at Sunland Park Drive.

The latest on I-10/Resler

Once the Sunland Park overpass is open, the plan is to close the westbound Resler exit ramp for approximately six to eight weeks. Crews will be reconfiguring the Resler exit ramp and replacing the ramp’s pavement.  While the Resler exit ramp is closed, drivers may use the Sunland Park westbound exit instead. Click here to watch a video that shows the final design of the Resler exit ramp.

The latest on I-10/North Mesa

Two more lane pattern changes are coming to North Mesa Street (under the I-10 overpass) this year. The first lane pattern change could be in place by October 15. This change will require a 27-hour closure on October 14, as detailed below. The second change should occur before December. Delays have occurred at this location; but, plans are in place to recoup.

Almost there 

GO 10 is a four-year project that started in April 2015 and ends April 2019 (7 months away). When finished, crews will have:

  • Installed an equivalent of 72 acres of concrete pavement.
  • Erected an equivalent of 98 houses worth of retaining walls.
  • Moved enough dirt to fill 306 Olympic-sized swimming pools.
  • Built, rebuilt or widened 29 bridges – a length of approximately 11 football fields.

Links to full list of closures:  West Area Projects  |  Go10  |  Border West Expressway  |  East Area Projects

LOCATION DURATION DESCRIPTION
I-10 Both Directions Overnight

Oct. 1 – 4

8 pm each night to 6 am each morning

 

·         I-10 Eastbound will close completely at Sunland Park (Exit 13). Detour: Motorists will exit at Sunland Park, follow the detour signs to Doniphan Drive and Paisano Drive (US 85), then onto Executive Center Boulevard. The Executive Center Boulevard entrance ramp to I-10 Eastbound will be open.

·      I-10 Westbound will close completely at Executive Center Boulevard (Exit 16). Detour: Motorists will exit at Executive Center, then follow the detour signs to North Mesa Street (SH 20). The North Mesa entrance ramp to I-10 Westbound will be open.

·      Sunland Park Drive will close completely in both directions at the I-10 overpass. Detour: Motorists should use an alternate route.

·      Both Sunland Park entrance ramps to I-10 Eastbound will close.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Crews will be paving at Sunland Park Drive and painting structures.

North Mesa

 

Overnight

Oct. 1

8 pm to 6 am

 

·      The North Mesa exit ramp (Exit 11) from I-10 Eastbound will close. Detour: Motorists on I-10 Eastbound should use an alternate exit ramp.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

·      North Mesa Street (SH 20) westbound lanes (in the direction headed toward Doniphan Drive) will close at North Desert Boulevard. Detour: Motorists on westbound North Mesa Street (SH 20) should take an alternate route.

·      The North Mesa Street dedicated right turn lane onto North Desert Boulevard will remain open.

 

Crews will be conducting pavement work on North Mesa Street near South Desert Boulevard.

 

North Mesa 27 HOURS

Sunday, October 14 at 3 am to Monday, October 15 at 6 am

·      North Mesa Street (SH 20) will close completely in both directions between Remcon Circle and Osborne Drive. Detour:  Motorists should use an alternate route such as Sunland Park Drive, Thorn Avenue or Redd Road.

·      All North Mesa entrance ramps and exit ramps (Exit 11) to and from I-10 will close. Detour:  Motorists should use alternate ramps at Redd Road or Sunland Park Drive.

·      McClintock Drive access to South Desert Boulevard will close.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

 

Crews will be moving barrier walls and re-striping lanes.

 

IMPORTANT:  After the closure lifts, motorists on North Mesa Street (SH 20) at the I-10 overpass will experience a change in traffic lane patterns.  Motorists should plan for extra travel time and approach the area cautiously and patiently.

 

TxDoT, GO10 Closures, Detours for Week of September 23

All the closures and detours for the upcoming week, including all areas of El Paso roadways are listed below.

Last week, GO 10 announced a 27-hour closure of North Mesa Street would occur September 30-October 1.  That closure is now postponed to October 7-8.  The one proviso: inclement weather could cause the closure to be postponed again to the following weekend, October 14-15.

Links to FULL LISTS of closures:  

West Area Projects   |  GO 10    |   Border West Expressway   |  East Area Projects

Mesa Park Interchange project 

Saturday, Sept. 29
3 a.m. to 3 p.m. (one night only)

  •  I-10 eastbound Executive entrance and exit ramps will be closed
  • Note: I-10 Executive overpass will remain open
  • Crews will be placing cement for proposed roadway

 

US 54 Widening and Illumination project
3 a.m. Saturday, Sept. 22 through 5 a.m. Monday, Sept. 24

  • US 54 southbound will close completely at Transmountain
  • Crews will be pouring bridge deck over Diana Drive
  • Detour: Traffic will exit at Transmountain and re-enter after Hondo Pass

9 a.m. Saturday, Sept. 22 through 5 a.m. Monday, Sept. 24

  • US 54 northbound will close completely at Hondo Pass
  • Crews will be pouring bridge deck over Diana Drive
  • Detour: Traffic will exit at Hondo Pass and re-enter at Transmountain

 

Guardrail Repair project

Tuesday, Sept. 25
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on I-10 westbound between the Copia entrance ramp to the Piedras entrance ram
  •  I-10 westbound Copia entrance ramp will be closed

Wednesday, Sept. 26
9 a.m. to 3 p.m. (throughout the day)

  • Left lane closure on I-10 westbound between the Artcraft overpass to the Transmountain overpass

Thursday, Sept. 27
9 a.m. to 3 p.m. (throughout the day)

  • Left lane closure on Gateway West between the Piedras Street to the Cotton entrance ramp
  • I-10 westbound Copia entrance ramp will be closed
  • I-10 westbound Cotton exit ramp will be closed

Thursday, Sept. 27
9 p.m. to 3 a.m. (one night only)

  • Right lane closure on I-10 westbound between the Dallas entrance ramp to the Mesa exit ramp
  • I-10 westbound Mesa exit ramp will be closed

 

Border West Expressway project

I-10

Thursday, Sept. 27
9 p.m. to 5 a.m.

  • Eastbound left lane from Schuster Avenue to Executive Center Boulevard
  • Closure is needed for roadway repair

 

Loop 375

Friday, Sept. 28 to Monday, Oct. 1
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from US 54 to Oregon Street
  • Closure is needed for sound wall work

 

McNutt

Friday, Sept. 28 to Monday, Oct. 1
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Doniphan to Brickland Street
  • Closure is needed for permanent striping

 

Executive Center Boulevard

Friday, Oct. 5 – Monday, Oct. 8
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from I-10 to Paisano
  • Closure is needed for traffic switch

 

Border West Expressway Project (new)

US 62

Tuesday, September 25

9 p.m. to 5 a.m.  (Nightly full closure)

  • Eastbound from Coles St. to Saint Vrain St.
  • Closure is needed for roadway work.

 

From Saturday, October 6 to Monday, October 8

6 a.m. to 5 a.m.  (Nightly full closure)

  • Eastbound from Coles St. to Saint Vrain St.
  • Closure is needed for roadway work.
LOCATION DURATION DESCRIPTION
I-10 Both Directions Overnight

Sept. 24 and 25

8 pm each night to 6 am each morning

 

·      I-10 Eastbound will close completely at Sunland Park (Exit 13). Detour: Follow the detour signs along the frontage ramps to re-enter I-10 Eastbound.

·      I-10 Westbound will close completely at Executive Center Boulevard (Exit 16). Detour: Follow the detour signs to North Mesa Street (SH 20). The North Mesa entrance ramp to I-10 Westbound will be open.

·      Sunland Park Drive will close completely in both directions at the I-10 overpass. Detour: Motorists should use an alternate route.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Crews will be working on the Sunland Park Drive overpass and the westbound Sunland Park exit ramp.

 

I-10 East at Mesa

 

Overnight

Sept. 25

8 pm to 6 am

 

·      The North Mesa exit ramp (Exit 11) from I-10 Eastbound will close.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

 

Detour: Motorists should use an alternate exit ramp and take an alternate route.

 

Crews will be paving on North Mesa Street near the South Desert Boulevard intersection.

I-10 Both Directions Overnight

Sept. 26 and 27

8 pm each night to 6 am each morning

 

·      I-10 in both directions will close completely at Sunland Park (Exit 13).

Detours:

–    Motorists on I-10 Eastbound will exit at Sunland Park (Exit 13) and follow the detour signs to Doniphan Drive and Paisano Drive (US 85). The Executive Center entrance ramp to I-10 Eastbound will be open.

–    Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and follow the detour signs to North Mesa Street (SH 20). The North Mesa entrance ramp to I-10 Westbound will be open.

·      Sunland Park Drive will close completely in both directions at the I-10 overpass. Detour: Motorists should use an alternate route.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Paisano Drive (US 85) entrance ramp to I-10 Eastbound will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

 

Crews will be working on the Sunland Park Drive overpass and will be drilling near Crockett Street.

 

North Mesa

 

27 HOURS

Sunday, October 7 at 3 am to Monday, October 8 at 6 am

·      North Mesa Street (SH 20) will close completely in both directions between Remcon Circle and Osborne Drive. Detour:  Motorists should use an alternate route such as Sunland Park Drive, Thorn Avenue or Redd Road.

·      All North Mesa entrance ramps and exit ramps (Exit 11) at I-10 will close. Detour:  Motorists should use alternate ramps at Redd Road or Sunland Park Drive.

·      McClintock Drive access to South Desert Boulevard will close.

·      South Desert Boulevard will close between McClintock Drive and North Mesa Street (SH 20).

 

Crews will be moving barrier walls and re-striping lanes.

 

IMPORTANT:  After the closure lifts, motorists on North Mesa Street (SH 20) at the I-10 overpass will experience a change in traffic lane patterns.  Motorists should plan for extra travel time and approach the area cautiously and patiently.

  

TxDoT/Go10 Closures, Detours for Week of September 9

This Sunday’s 27-hour closure of I-10 East at Redd Road will result in a change to traffic lane patterns on I-10 East at North Mesa Street.

Link to full lists of closures: West Area Projects  |  GO10  |  Border West Expressway  |  East Area Projects

US 54 Widening and Illumination Project

Sunday, September 9

11:00 p.m. to 2:00 a.m.

  • US-54 southbound will close completely from Hercules to Dyer
  • Crews will be power washing the pedestrian bridge to prepare it for painting.

 

Monday, September 10

9:00 p.m. to 5:00 a.m.

  • US-54 southbound will close completely from Hercules to Dyer
  • Crews will be painting the repaired pedestrian bridge.

 

Tuesday, Sept. 18

9 p.m. to 5 a.m. (one night only)

  • Complete closure on US 54 southbound between the Transmountain/Woodrow Bean exit ramp to the Hondo Pass overpass
  • DETOUR: US 54 southbound traffic will need to exit at the Transmountain/Woodrow Bean exit ramp and re-enter at the Hondo Pass entrance ramp
  • Crews will be working on opening the “New” ramp and closing the existing exit ramp between Transmountain and Diana.

 

Wednesday, Sept. 19

9 p.m. to 5 a.m. (one night only)

  • Complete closure on US 54 northbound between the Hondo Pass exit ramp to the Transmountain exit ramp
  • DETOUR: US 54 northbound traffic will need to exit at Hondo Pass and re-enter at the Transmountain/Woodrow Bean entrance ramp
  • Crews will be working on opening the “New” exit ramp between Diana and Transmountain.

 

UPCOMING 50-hour closures

3:00 a.m. Saturday, September 22 through 5:00 a.m. Monday, September 24

  • US-54 northbound will close completely at Hondo Pass
  • Crews will be pouring bridge deck over Diana Drive
  • Detour: Traffic will exit at Hondo Pass and reenter after Transmountain

 

3:00 a.m. Saturday, September 29 through 5:00 a.m. Monday, October 1

  • US-54 southbound will close completely at Transmountain
  • Crews will be pouring bridge deck over Diana Drive
  • Detour: Traffic will exit at Transmountain and reenter after Hondo Pass

Maintenance

Monday, Sept. 10 through Friday, Sept. 14
9 a.m. to 3 p.m. (throughout the day)

  • US 54 northbound Sun Valley exit ramp will be closed
  • Right lane closure on Transmountain/Woodrow Bean (Loop 375) eastbound between McCombs to Bomarc
  • Right lane closure on I-10 westbound between Airway to Geronimo
  • I-10 westbound Geronimo exit ramp will be closed
  • I-10 westbound Airway entrance ramp will be closed
  • Left lane closure on Loop 375 between the museum to Tom Mays for shoulder work (mile markers 14-21)
  • Right lane closure on Spur 601 east and westbound between Fred Wilson to Loop 375

Westway Project Phase III

Monday, Sept. 10 through Wednesday, Sept. 12

  • Westway on-ramp to I-10 westbound will be closed.

Loop 375 Border Highway

Friday, Sept. 7 to Monday, Sept. 10
9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from US 54 to Oregon Street
  • Closure is needed for roadway work

US 85

Friday, Sept. 7 to Monday, Sept. 10
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for cap work

Friday, Sept. 14 to Sunday, Sept. 16
9 p.m. to 6 p.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for cap work

McNutt

Friday, Sept. 14 to Monday, Sept. 17
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Doniphan to Brickland Street
  • Closure is needed for roadway work

Doniphan Drive

Friday, Sept. 7 to Monday, Sept. 10
9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from Racetrack to Paisano
  • Closure is needed for roadway work

US 62

Friday, Sept. 14 to Monday, Sept. 17
9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from Cole Street to Saint Vrain Street
  • Closure is needed for roadway work

Mall Braided Ramps Project

Sunday, Sept. 9 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • Gateway Boulevard eastbound complete frontage road closure between Airway Boulevard and Hawkins Boulevard
  • Crews will be removing portable concrete traffic barrier

Monday, Sept. 10 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound complete closure between Airway Boulevard and Hawkins Boulevard
  • Crews will be removing portable concrete traffic barrier
LOCATION DURATION DESCRIPTION
I-10 East at Redd

 

27 HOURS

Sunday, September 9 at 3 am until Monday, September 10 at 6 am

 

 

·      I-10 Eastbound will close completely at Redd Road (Exit 9).

·      The Redd Road entrance ramp to I-10 Eastbound will close.

·      The Artcraft Road entrance ramp to I-10 Eastbound will close.

·      The North Mesa Street entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists on I-10 Eastbound will exit at Redd Road (Exit 9), then take Doniphan Drive to Sunland Park Drive. The Sunland Park entrance ramp to I-10 will be open.

 

Business Access:  Access to area businesses will be open via South Desert Boulevard. Through traffic will not be allowed to use South Desert Boulevard as an alternate route.

 

Crews will be moving barrier walls and re-striping lanes on I-10 Eastbound.

 

IMPORTANT:  After the closure lifts, motorists on I-10 Eastbound at North Mesa Street (SH 20) will experience a change in traffic lane patterns.

 

I-10 Both Directions

 

Overnight

Sunday, September 9

8 pm to 6 am

 

·      I-10 Eastbound will be close completely at Redd Road (Exit 9). Detour:  Motorists on I-10 Eastbound will exit at Redd Road (Exit 9), then take Doniphan Drive to Sunland Park Drive. The Sunland Park entrance ramp to I-10 Eastbound will be open.

·      Sunland Park Drive will close completely in both directions at the I-10 overpass.

·      The Artcraft Road entrance ramp to I-10 Eastbound will close.

·      The Redd Road entrance ramp to I-10 Eastbound will close.

·      The North Mesa entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      I-10 Westbound will close completely at Sunland Park (Exit 13). Detour: Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and follow it to North Mesa Street (SH 20). Motorists may re-enter I-10 Westbound at the North Mesa entrance ramp.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

 

Business Access:  Access to area businesses will be open via South Desert Boulevard. Through traffic will not be allowed to use South Desert Boulevard as an alternate route.

 

Crews will be moving barrier walls and re-striping lanes on I-10 Eastbound. Crews will also be pouring concrete onto the I-10 overpass at Sunland Park Drive.

 

IMPORTANT:  After the closure lifts, motorists on I-10 Eastbound at North Mesa Street (SH 20) will experience a change in traffic lane patterns.

 

North Mesa

 

Overnight

September 10-13

9 pm each night to 6 am each morning

 

·      On North Mesa Street (SH 20), the lanes for traffic headed toward Doniphan Drive will close between North Desert Boulevard and Osborne Drive. Detour: Motorists should follow North Desert Boulevard to use the Thorn Avenue overpass.

·      The North Mesa exit ramp from I-10 Eastbound will close. Detour: Motorists should use the Redd Road exit ramp.

·      South Desert Boulevard will be closed between McClintock Drive and North Mesa Street. 

 

Crews will be paving a section of North Mesa Street (SH 20).  For some time, it may appear as though no work is taking place; but, in fact, the new pavement requires undisturbed curing time.

 

I-10 Both Directions

 

Overnight

September 10-13

8 pm each night to 6 am each morning

 

·      I-10 in both directions will close completely at Sunland Park (Exit 13).  Detours:  Motorists on I-10 Eastbound will exit at Sunland Park (Exit 13), follow Sunland Park Drive to Doniphan Drive, then follow Doniphan Drive to Executive Center Boulevard. The Executive Center entrance ramp to I-10 Eastbound will be open. Motorists on I-10 Westbound will exit at Sunland Park (Exit 13), follow it to North Mesa Street (SH 20), then re-enter I-10 Westbound using the North Mesa entrance ramp.

·      Sunland Park Drive will close completely in both directions at the I-10 overpass.  Detour: Motorists should use an alternate route or follow the detour signs in place.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Resler flyover entrance ramp to I-10 Eastbound will close.

·      Crockett Street access to Paisano Drive (US 85) will close.

 

Crews will be pouring bridge deck onto the center Sunland Park Drive overpass.

North Mesa 27 HOURS

Sunday, September 30 at 3 am to Monday, October 1 at 6 am

 

·      North Mesa Street (SH 20) will close completely in both directions at the I-10 overpass. Detour:  Motorists should use an alternate route such as Thorn Avenue or Redd Road.

·      All North Mesa entrance ramps and exit ramps (Exit 11) to and from I-10 will close. Detour:  Motorists should use alternate ramps at Redd Road or Sunland Park Drive.

·      McClintock Street access to South Desert Boulevard will close.

·      Graphite Drive access to South Desert Boulevard will close.

·      South Desert Boulevard will close between Thorn Avenue and North Mesa Street (SH 20)

 

Crews will be moving barrier walls and re-striping lanes.

 

IMPORTANT:  After the closure lifts, motorists on North Mesa Street (SH 20) at the I-10 overpass will experience a change in traffic lane patterns.  Motorists should plan for extra travel time and approach the area cautiously and patiently.

 

City Terminates Contract for Robinson Avenue Reconstruction Project

City Council voted Tuesday to terminate its contract with Saab Site Contractors in an effort to advance the Robinson Avenue reconstruction project which has experienced “significant setbacks.”

“The contactor had been given ample time to comply with the contract agreement. The action taken today by the City is necessary to complete these street improvements, which should have been completed in 2017. We owe it to the community to get the work done,” City of El Paso Capital Improvement Department Director Sam Rodriguez said.

Council’s vote enables the City of El Paso’s Capital Improvement Department to coordinate the completion with the surety company that bonded the project.

Construction on the Robinson reconstruction project began in 2016. Robinson from Piedmont Drive to Rim Road/Scenic Drive was programmed to receive a new concrete driving surface and drainage improvements.

The approximate $2.7 million project is funded through the 2012 Street Capital Infrastructure Plan.

In addition to a new roadway surface and drainage improvements, the Robinson reconstruction project aims to introduce a multi-modal transportation element, with a hike and bike path which will allow for users to have a safe path as they are able to enjoy the beauty of Billy Rogers Arroyo, the Franklin Mountains, and the views off of Scenic Drive.

Native trees and landscaping will also enhance the experience of all users. Safety illumination is also included as part of the project at the intersections.

The next steps in the project are to engage the surety company and take any necessary actions required to secure the site until resumption of work.

Project completion is anticipated by the fall of 2018.

TxDoT/Go10 Closures, Detours for Week of August 26

Here’s a look at the project closures for the week ahead.

Links to Full List of Closures:

West Area Project Closures  |  GO 10 Project Closures

Border West Expressway Closures  |  East Area Project Closures

LOCATION DURATION DESCRIPTION
I-10 West at Sunland

 

15 HOURS

Sunday, August 26

3 am to 6 pm

 

·      I-10 Westbound will close completely at Sunland Park (Exit 13).

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      Left turns onto Sunland Park Drive from the Sunland Park westbound exit ramp will not be permitted.

 

Detour:  Motorists on I-10 Westbound will exit at Sunland Park (Exit 13), then follow the detour signs to North Mesa Street (SH 20). Motorists may re-enter I-10 Westbound from the North Mesa Street entrance ramp.

 

Crews will be moving barrier walls and re-striping lanes on I-10 Westbound.

 

IMPORTANT:  After the closure lifts, motorists on I-10 Westbound should approach the North Mesa area with caution because traffic lane patterns will be changed.  

 

I-10 West at Executive Overnight

August 27-30

9 pm to 6 am nightly

 

·      I-10 Westbound will close completely at Executive Center Boulevard (Exit 16).

·      Sunland Park Drive will close in both directions at the I-10 overpass.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

 

Detour: Motorists on I-10 Westbound will exit at Executive Center (Exit 16), then follow the detour signs to North Mesa Street (SH 20). Motorists may re-enter I-10 Westbound from the North Mesa Street entrance ramp.

 

I-10 East at Redd 27 HOURS

Sunday, September 9 at 3 a.m. until Monday, September 10 at 6 a.m.

 

·      I-10 Eastbound will close at Redd Road (Exit 9).

·      The Redd Road entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists on I-10 Eastbound will exit at Redd Road (Exit 9), follow it to South Desert Boulevard, then follow South Desert Boulevard to North Mesa Street (SH 20). Motorists may re-enter I-10 Eastbound using the North Mesa Street entrance ramp.

 

Crews will be moving barrier walls and re-striping lanes on I-10 Eastbound.

 

IMPORTANT:  After the closure lifts, motorists on I-10 Eastbound at North Mesa Street (SH 20) will experience a change in traffic lane patterns. Please proceed cautiously.

 

Don’t forget to follow us on Twitter. Plus sign up for traffic alerts on www.drivetexas.org.

Rip-rap Repair Project

Sunday, Aug. 26 through Thursday, Aug. 30
9 p.m. to 5 a.m. (nightly)

  • I-10 westbound at Paisano – 2 right lanes closed
  • I-10 westbound Paisano exit ramp closed
  • I-10 westbound Trowbridge entrance ramp closed
  • Crews will be repairing spalled concrete pavement

 

Westway Project Phase III

Monday, Aug. 27 into Tuesday, Aug. 28
9 p.m. to 5 a.m.  (one night only)

  • Complete closure of I-10 east and westbound at the Vinton overpass
  • Crews will be placing concrete on the new turnaround bridge

 

US 54 Widening and Illumination Project

Starting Sunday, Sept. 9 and Monday, Sept. 10
9 p.m. to 5 a.m. (nightly)

  • Complete closure of US 54 southbound between Dyer exit ramp to the Ellerthorpe pedestrian bridge
  • Crews will be painting and installing clearance height signs on the pedestrian bridge

 

Tuesday, Sept. 11
9 p.m. to 5 p.m. (one night only)

  • Complete closure on US 54 southbound between the Transmountain/Woodrow Bean exit ramp to the Hondo Pass overpass
  • Detour: US 54 southbound traffic will need to exit at the Transmountain/Woodrow Bean exit ramp and re-enter at the Hondo Pass entrance ramp
  • Crews will be working on opening the new ramp and closing the existing exit ramp between Transmountain and Diana

 

Wednesday, Sept. 12
9 p.m. to 5 p.m. (one night only)

  • Complete closure on US 54 northbound between the Hondo Pass exit ramp to the Transmountain exit ramp
  • Detour: US 54 northbound traffic will need to exit at Hondo Pass and re-enter at the Transmountain/Woodrow Bean entrance ramp
  • Crews will be working on opening the new exit ramp between Diana and Transmountain

 

Mesa Park Project

Tuesday, Sept. 4
9 p.m. to 5 a.m. (one night only)

  • Complete closure on I-10 eastbound between Sunland Park to Executive
  • Detour: Eastbound traffic will need to exit at the Sunland Park exit ramp and use Mesa to enter at Executive
  • Crews will be removing traffic barriers in the area

 

Loop 375 Border Highway

Friday, Aug. 24 to Saturday Aug. 25
9 p.m. to 5 p.m. (continuous full closure)

  • Eastbound and westbound from US 54 to Oregon Street
  • Closure is needed for roadway work

 

Thursday, Sept. 6
9 p.m. to 5 a.m. (nightly full closure)

  • Eastbound and westbound from US 54 to Oregon Street
  • Closure is needed for roadway work

 

Friday, Sept. 7 to Sunday, Sept. 9
9 p.m. to 4 p.m. (nightly closure)

  • Eastbound and westbound from US 54 to Oregon Street
  • Closure is needed for roadway work

 

US 85

Friday, Aug. 24 to Saturday, Aug. 25
9 p.m. to 1 p.m. (continuous full closure)

  • Westbound and eastbound from Executive Center Boulevard to San Francisco Street
  • Closure is needed for utility work

 

Saturday, Aug. 25 to Monday, Aug. 27
1 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for cap work

 

Friday, Sept. 7 to Monday, Sept. 10
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for cap work

 

McNutt

Friday, Aug. 24 to Monday, Aug. 27
9 p.m. to 5 a.m. (continuous full closure)

  • Westbound and eastbound from Doniphan to Brickland Street
  • Closure is needed for roadway work

 

Border West Expressway Project

Wednesday, Aug. 29
9 p.m. to 5 a.m.

  • I-10 eastbound left lane from Schuster Avenue to Executive Center Boulevard
  • Closure is needed for roadway repair

 

Doniphan Drive

Friday, Sept. 7 to Monday, Sept. 10
9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from Racetrack to Paisano
  • Closure is needed for roadway work

 

Monday, Sept. 10
9 p.m. to 5 a.m. (nightly full closure)

  • Eastbound and westbound from Racetrack to Paisano
  • Closure is needed for roadway work

 

Oregon Street

Friday, Aug. 24 to Friday, Sept. 14
5 a.m. to 4 p.m.

  • Southbound from Cesar Chavez to 7th Street
  • Closure is needed for roadway work

TxDoT/Go10 Closures, Detours for Week of August 5

Here’s a look at all the project closures for the week ahead. Other highlights are included, as are the complete lists via hyperlinks.

GO 10 is on the tail-end of its four-year timeline and that means plenty of construction milestones to applaud:

  • Recently, crews finished paving half of North Mesa Street (SH 20) under the I‐10 overpass. Work will start next week to start paving the other half. Traffic on North Mesa Street (SH 20) will be switched onto the newly paved lanes later this month.
  • Next week, crews will place the final beams on the new Sunland Park overpass.
  • On August 20, the I‐10 Westbound overpass at North Mesa Street (SH 20) will open to traffic.

Plus, 27-hour closures are planned for Aug 19 and Aug 26.

Mall Braided Ramps Project

Sunday, Aug. 5 through Friday, Aug. 10 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 westbound complete closure between Viscount Boulevard and Airway Boulevard
  • Crews will be installing overhead sign structure

Sunday, Aug. 5 through Friday, Aug. 10 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound complete closure between Airway Boulevard and Viscount Boulevard
  • Crews will be installing overhead sign structures

 

Spalling Repair Project

Sunday, Aug. 5 through Thursday, Aug. 9
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound at Paisano 3 Left lanes closed
  • I-10 eastbound at Raynolds entrance ramp closed
  • Crews will be repairing concrete barriers in the area.

Sunday, Aug. 5 through Thursday, Aug, 9
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound from the Santa Fe exit ramp to Campbell entrance ramp left 2 lanes closed
  • Crews will be repairing spalled concrete pavement.

August 1, 2018 through August 15, 2018 Long Term Closure:

• Northbound and Southbound on Paseo Grande St. from Vista Del Sol Dr. to Paseo Alegre Dr. Will be closed for the installation of new Sanitary Sewer system.

West Area Project Closures  |   East Area Project Closures  |  Border West Expressway Closures  |  GO10 Closures

LOCATION DURATION DESCRIPTION
North Mesa Street

 

Continuous

Monday, August 6 at 9 am until Friday, August 10 at 3 pm

 

·      The right lane on North Mesa Street (SH 20) – in the direction traveling toward Doniphan Drive – will close between Remcon Circle and Osborne Drive.

 

Bus Service:  The Sun Metro bus stop on North Mesa Street (SH 20) at Osborne Drive (near Taco Cabana) will be closed during this work activity. An alternate bus stop is available on North Mesa Street (SH 20) at Crossroads Drive (near Pizza Hut). For more information, contact Sun Metro at (915) 212-3436 or (915) 212-3300.

 

I-10 West at Sunland Park

 

Continuous

Monday, August 6 at 9 am until Thursday, August 9 until 3 pm

·           The Sunland Park exit ramp from I-10 Westbound will be kept to one lane.

 

Note: Motorists on I-10 Westbound should slow down as they approach the Sunland Park exit. Traffic may slow or stop suddenly.

 

I-10 Both Directions

 

Overnight

Tuesday, August 7 through Thursday, August 9

 

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close at Executive Center (Exit 16).

Detour: Motorists will exit at Executive Center Boulevard (Exit 16) and follow it to North Mesa Street (SH 20). Motorists may re-enter I-10 Westbound using the North Mesa Street entrance ramp.

·      I-10 Eastbound will close at Sunland Park (Exit 13).

Detour: Motorists will exit at Sunland Park Drive (Exit 13) and immediately re-enter I-10 at the next ramp.

·      Sunland Park Drive will close in both directions at the I-10 overpass.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Resler Drive flyover entrance ramp to I-10 Eastbound will close.

·      The Schuster Avenue entrance ramp to I-10 Westbound will close.

 

Milestone: Crews will be placing the final set of beams on the Sunland Park Drive overpass.

 

North Mesa Street

 

Overnight

Tuesday, August 7 through Thursday, August 9

 

8 pm each night to 6 am each morning

 

·      North Mesa Street (SH 20) – only the lanes for traffic traveling toward Remcon Circle – will close completely between South Desert Boulevard and Remcon Circle.

Detour:  Motorists on North Mesa Street (SH 20) who want to cross from the Osborne side of I-10 to the Remcon side of I-10 should use an alternate route such as Thorn Avenue or Redd Road. The Sunland Park Drive overpass will not be an alternate route option as it will also close during these nights.

·      The North Mesa exit ramp (Exit 11) from I-10 Westbound will close.

Detour:  Motorists on I-10 Westbound who want to exit at North Mesa (Exit 11) should find an alternate exit ramp or follow the detour signs in place.

 

Milestone:  Crews have finished paving half the through-lanes on North Mesa Street under I-10. Traffic on North Mesa Street (SH 20) will be switched onto the newly paved lanes later this month.

  

I-10 West at Sunland

 

27-HOURS

Sunday, August 19 at 3 am until Monday, August 20 at 6 am

 

·      I-10 Westbound will close at Sunland Park (Exit 13).

·      The Sunland Park Drive entrance ramp to I-10 Westbound will close.

Detour:  Motorists on I-10 Westbound will exit at Sunland Park (Exit 13), follow it to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) northbound to re-enter I-10 Westbound.

 

Crews will be re-striping lanes on I-10 Westbound and moving barrier walls.

 

ATTENTION:  By the morning of August 20, traffic on I-10 Westbound approaching North Mesa Street (SH 20) will experience a change in lane patterns. Please proceed cautiously.

  

I-10 East at Redd

 

27-HOURS

Sunday, August 26 at 3 am until Monday, August 27 at 6 am

 

·      I-10 Eastbound will close at Redd Road (Exit 9).

·      The Redd Road entrance ramp to I-10 Eastbound will close.

Detour:  Motorists on I-10 Eastbound will exit at Redd Road (Exit 9), follow it to South Desert Boulevard, then follow South Desert Boulevard to North Mesa Street (SH 20). Motorists may re-enter I-10 Eastbound using the North Mesa Street entrance ramp.

 

Crews will be re-striping lanes on I-10 Eastbound and moving barrier walls.

 

ATTENTION:  By the morning of August 27, traffic on I-10 Eastbound at North Mesa Street (SH 20) will experience a change in lane patterns. Please proceed cautiously.

 

TxDoT/Go10 Closures, Detours for Week of July 29

Here’s a look at the project closures for the week ahead. As always don’t forget to follow TxDoT on Twitter and sign up for traffic alerts on www.drivetexas.org

Mall Braided Ramps Project

Sunday, July 29 through Friday, Aug. 3 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 westbound complete closure between Viscount Boulevard and Airway Boulevard
  • Crews will be installing overhead sign structure

 

Sunday, July 29 through Friday, Aug. 3 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound complete closure between Airway Boulevard and Viscount Boulevard
  • Crews will be installing overhead sign structures

 

Joe Battle (Loop 375) Sound Walls

Monday, May 30 (complete closures until further notice)

  • Southbound left lane closure on Joe Battle Boulevard (frontage road) between Montana Avenue (US62/180) and Edgemere Boulevard
  • Southbound left lane closure on Joe Battle Boulevard (frontage road) between Vista Del Sol Avenue and Pellicano Drive

 

US 85

Saturday, August 4 to Monday, August 6

6 p.m. to 5 a.m. (Continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco St.
  • Closure is needed for bridge deck pour.

 

Doniphan

Saturday, August 4 to Sunday, August 5

5 a.m. to 9 p.m. (Continuous full closure)

  • Eastbound and westbound from Racetrack to Paisano.
  • Closure is needed for concrete paving

 

Monday, August 6 and Tuesday, August 7

9 p.m. to 5 a.m. (Nightly full closure)

  • Eastbound and westbound from Racetrack to Paisano.
  • Closure is needed for striping

 

Saturday, August 4 to Monday August 6

6 a.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from US-54 to Oregon St.
  • Closure is needed for roadway work.

 

Spalling Repair Project

Sunday, July 29 through Thursday, August 2

9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound at Paisano 3 Left lanes closed
  • I-10 eastbound at Raynolds entrance ramp closed
  • Crews will be repairing concrete barriers in the area.

 

Sunday, July 29 through Thursday, August 2
9 p.m. to 5 a.m. (overnight)

  • I-10 eastbound from Santa Fe exit ramp to Campbell entrance ramp left 2 lanes closed.
  • Crews will be repairing spalled concrete pavement.

 

US 54 Widening and Illumination Project

Sunday, July 29 through Wednesday, August 1
9 p.m. to 6 a.m. (nightly weather permitting)

  • Complete closure of US 54 southbound between Hondo Pass Drive and Hercules Avenue
  • Crews will be working on the pedestrian bridge, installing poly fiber wrap
  • DETOUR:  Southbound traffic will exit US 54 southbound Hercules exit ramp, go through Hercules and Dyer intersections and back onto the freeway at Dyer-US 54

West Area Project Closures  |   East Area Project Closures  |  Border West Expressway Closures  |  GO10 Closures

LOCATION DURATION DESCRIPTION
North Mesa Street

 

Continuous

Monday, July 30 at 9 am through Friday, August 3 at 3 pm

·         The right lane on North Mesa Street (SH 20) – in the direction traveling toward Doniphan Drive – will close between North Desert Boulevard and Osborne Drive.

 

Crews will continue work to install a storm drain pipe.

 

Note:  One Sun Metro bus stop on North Mesa Street at Osborne Drive (near Taco Cabana) will be closed July 25-27 due to this work activity. An alternate bus stop will be available on North Mesa Street at Crossroads Drive (near Pizza Hut). For more information, contact Sun Metro at (915) 212-3436 or (915) 212-3300.

 

North Mesa Street

 

Overnight

Monday, July 30 and Tuesday, July 31

9 pm to 6 am nightly

·         North Mesa Street (SH 20) in both directions will close between South Desert and North Desert boulevards.

·         There will be no access to the I-10 Westbound entrance ramp from North Mesa Street (SH 20).

·         The North Mesa exit ramp (exit 11) from I-10 Westbound will close.

 

Detour: Motorists should find an alternate route or follow the detour signs in place.

 

Business access: Access to area businesses will be open.

 

Crews will be working on the I-10 overpass and working on traffic signals.

 

North Mesa Street

 

Overnight

Wednesday, August 1 and Thursday, August 2

9 pm to 6 am nightly

 

·         North Mesa Street (SH 20) ) – in the direction traveling toward Doniphan Drive – will close between North Desert and South Desert boulevards.

·         The North Mesa exit ramp (exit 11) from I-10 Westbound will close.

 

Detour:  Motorists should find an alternate route or follow the detour signs in place.

 

Crews are paving on North Mesa Street.

 

TxDoT/Go10 Construction, Detours for Week of July 15

Next week closures on I-10 will still be in effect so progress can continue to be made on the Sunland Park Drive overpass.

In addition, the I-10 closure for our Vinton project was rescheduled for the 17 and 18, US 54 southbound will be closed all weekend between Hondo Pass and Hercules for work on the pedestrian bridge plus the Gateway Blvd (I-10) westbound Viscount entrance ramp will close July 23 so crews can progress on our Braided Ramp project

  • GO 10, Mesa Park Interchange and Border West Expressway all have planned closures on I-10, it is best to avoid I-10 on the westside after 8:30 p.m. if at all possible.
  • There are extended closures for Campbell and Kansas scheduled, an extended reconfiguration for Montana and a traffic switch planned for Alameda.

US 54 Widening and Illumination Project

Saturday, July 14 through Monday, July 16
3 a.m. to 5 a.m. (continuous)

  • Complete closure of US 54 southbound between Hondo Pass Drive and Hercules Avenue
  • Crews will be working on the pedestrian bridge, pouring concrete and then letting it cure
  • Detour: Southbound traffic will exit US 54 southbound Hercules exit ramp, go through Hercules and Dyer intersections and back onto the freeway at Dyer-US 54

 

 

Loop 375 Border Highway

Saturday, July 21 to Monday, July 23
6 a.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from US 54 to Oregon Street
  • Closure is needed for roadway work.

 

I-10

Thursday, July 26
9 p.m. to 5 a.m.

  • Eastbound left lane from Schuster Avenue to Executive Center Boulevard
  • Closure is needed for roadway repair.

 

Campbell Street

Monday, July 16 to Monday, Aug. 6
9 p.m. to 4 p.m. (continuous full closure)

  • From Cesar Chavez to 7th Street
  • Closure is needed for roadway work

 

Kansas Street

Monday, July 16 to Monday, Aug. 6
9 p.m. to 4 p.m. (continuous full closure)

  • From Cesar Chavez to 7th Street
  • Closure is needed for roadway work

 

Montana/Mattox Traffic and Operation Improvements Project

Monday, July 23
9 p.m. to 5 a.m. (one night)

  • Full closure of Montana (US 62/180) between Hawkins Boulevard and Rutherglen Street
  • Crews will be setting barrier in the median

Tuesday, July 24 through Friday, August 3
Continuous new reconfiguration until further notice

  • Montana (US 62/180) east will be reduced to two lanes between Hawkins Boulevard and Rutherglen Street
  • Crews will be working on traffic signals and operation improvements in the area.

 

Alameda Reconstruction Project

Friday, July 20 (closure until further notice)
9 a.m. to 4 p.m.

  • Alameda Avenue (SH 20) westbound lane closure between Gaspar Street and Walmart Supercenter intersection
  • Alameda Avenue (SH 20) traffic will be channelized to a single lane in each direction, utilizing the newly constructed SH 20 eastbound lanes
  • Alameda Avenue (SH 20) alternating eastbound and westbound closures as needed between Gaspar Street and Walmart Supercenter intersection
  • Alameda Avenue (SH 20) northbound closure at Carnes Road until further notice
  • Please follow the detour signs in place and expect traffic delays
  • Closures are necessary for construction of proposed concrete paving of westbound travel lanes, outside curb intersections, driveways, sidewalk, placement of new drainage/waterline, storm sewer, signals and illuminations

 

Spalling Repair Project

Sunday, July 15 through Thursday, July 19
9 p.m. to 5 a.m. (nightly)

  • I-10 eastbound at Paisano – three left lanes closed
  • I-10 eastbound at Raynolds entrance ramp closed
  • Crews will be repairing spalled concrete pavement (potholes) in the area

 

Mesa Park Project

Sunday, July 15 through Thursday, July 19
9 p.m. to 6 a.m. (nightly)

  • Complete closure on I-10 eastbound at Executive
  • Detour: Eastbound traffic will exit at the Executive exit ramp and re-enter at Downtown

 

Sunday, July 22 through Thursday, July 26
9 p.m. to 6 a.m. (nightly)

  • Complete closure on I-10 Eastbound at Executive
  • Detour: Eastbound traffic will exit at the Executive exit ramp and re-enter at Downtown

 

Westway Project Phase III

Monday, July 16 through Friday, July 20
9 a.m. to 4 p.m. (throughout the day)

  • Complete closure on North Desert Boulevard between Anthony and Vinton
  • Northbound Vinton entrance ramp to I-10 west will be closed

 

Tuesday, July 17 and Wednesday, July 18
9 p.m. to 5 a.m. (nightly)

  • Complete closure on I-10 east and westbound at the Vinton overpass
  • Crews will be hanging beams at the new turnaround bridge

West Area Project Closures  |  Border West Expressway Closures  |  East Area Project Closures  |  GO 10 Closures

I-10 Eastbound

 

 

Overnight

Sunday, July 15 through Thursday, July 19

 

9 p.m. each night to 6 a.m. each following morning

·      I-10 Eastbound will close completely at the North Mesa Street overpass.

 

Detour: Motorists will be detoured onto North Mesa Street (SH 20) and will be able to re-enter I-10 Eastbound from the downtown Wyoming entrance ramp.

 

·      The Sunland Park Drive overpass will close completely in both directions.

·      The Resler Drive flyover ramp to I-10 Eastbound will close.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      I-10 Eastbound entrance ramp will close completely at Paisano Drive (US 85).

·      The Sunland Park flyover ramp to I-10 Eastbound will close.

 

Crews will be setting bridge beams and installing signage for the Sunland overpass.

North Mesa Overnight

Tuesday, July 17 through Wednesday, July 18

 

9 p.m. each night to 6 a.m. each following morning

 

  • The I-10 Westbound exit ramp left turn lane to turn left on to North Mesa Street (SH 20) will close.

 

Crews will be installing storm drain.

TxDoT/Go10 Closures, Detours for Week of June 17

If Resler Drive is your usual I-10 exit, then pay attention – crews are exploring ways to avoid closing the Resler Drive exit ramp for several weeks starting sometime this month or early next month.

Officials say, “If there is no way to avoid it, the goal will be to restore the exit ramp before the new school year starts. Be prepared: starting considering your alternate routes.”

West Area Project Closures  |  East Area Project Closures  |  Border West Expressway Closures  |  GO10 Closures

Doniphan Drive

Friday, June 22 to Wednesday, June 27
9 p.m. to 5 a.m. (continuous full closure)

  • Eastbound and westbound from Racetrack to Paisano
  • Closure is needed for painting barrier and roadway work

US 85 (Paisano)

Friday, June 22 to Sunday, June 24
9 p.m. to 6 p.m. (continuous full closure)

  • Westbound and eastbound from Spur 1966 to San Francisco Street
  • Closure is needed for cap forming

Mall Braided Ramps Project

Monday, June 18 (complete closure)
9 p.m. to 5 a.m. (overnight)

  • Gateway Boulevard westbound closure between McRae Boulevard and Airway Boulevard
  • Entrance and exit ramps between McRae Boulevard and Airway Boulevard may close up to one hour before scheduled closure
  • Crews will be pouring concrete for a bridge deck

Mesa Park Project

Monday, June 18 through Thursday, June 21
9 p.m. to 5 a.m. (nightly)

  • Complete closure of I-10 westbound.
  • Traffic will exit at Schuster and re-enter at Sunland Park

Crews will be repaving shoulder, restriping and working on existing roadway

Westway Project Phase III

Wednesday, June 20
9 p.m. to 5 a.m. (one night only)

  • Complete closure of I-10 in both directions
  • Traffic will exit and enter at Vinton
  • Crews will be bringing in beams for the turnaround bridge under construction

Monday, June 18 through Friday, June 22
9 a.m. to 4 p.m. (throughout the day)

  • Complete closure on North Desert Boulevard between Anthony and Vinton
  • Northbound Vinton entrance ramp to I-10 west will be closed

 

US 54

Monday, June 18 through Friday, June 22
9 p.m. to 5 a.m. (nightly)

  • Complete closure on US 54 southbound between the Hercules exit to the Dyer entrance ramp
  • Detour: Southbound traffic will exit at the Hercules exit ramp and renter US 54 at the Dyer entrance ramp

Crews will be repairing the pedestrian bridge in the area

Spalling Repair Project

Monday, June 18 through Thursday, June 21
9 p.m. to 5 a.m. (nightly)

  • Two right lane closures on I-10 eastbound at the Raynolds overpass
  • Ramp D (US 54 south to I-10 east) will be closed
  • Ramp J (I-110 (Juarez) to I-10 east will be closed
  • Right lane closure on Raynolds Street at Gateway Boulevard east
  • Ramp Z (Paisano entrance ramp to Ramp J to I-10 east) Newest Ramp by the Zoo

Maintenance

Monday, June 18 through Friday, June 22
9 a.m. to 3 p.m. (throughout the day)

  • Right lane closure on Cesar Chavez/Border Highway (Loop 375) westbound between Fonseca to the Bridge of the Americas
  • Ramp O (Cesar Chavez/Border Highway (Loop 375) west to US 54 north)
  • Alternate entrance and exit ramp closures on Cesar Chavez/Border Highway (Loop 375) east and westbound between Fonseca to Zaragoza
  • Ramp on US 54 south to Spur 601 east will be closed
  • Right lane closure on US 54 southbound between Pershing to Yandell
  • US 54 northbound Pershing entrance ramp will be closed
LOCATION DURATION DESCRIPTION
I-10 West at Sunland

 

27 HOURS

Sunday, June 17 (Father’s Day)

3 am to 6 am the next morning

 

·      I-10 Westbound will close completely between Sunland Park (Exit 13) and North Mesa Street (SH 20).

·      North Mesa Street (SH 20) will close completely in both directions between Osborne Drive and Remcon Circle.

 

Detour:  Traffic on I-10 Westbound will exit at Sunland Park (Exit 13), follow Sunland Park Drive to North Mesa Street (SH 20), then follow North Mesa Street (SH 20) to re-enter I-10 Westbound. Traffic on North Mesa Street should follow the detour signs.

 

NOTICE:  This 27-hour closure will result in several changes to traffic lane patterns along I-10 Westbound near Resler Drive. Motorists exiting I-10 Westbound at North Mesa (Exit 11) will also notice the signalized intersection at North Mesa Street (SH 20) will be shifted to the left.

 

I-10 Both Directions at Sunland

 

Overnight

(The night of Father’s Day)

Sunday, June 17

9 pm to 6 am

 

·      I-10 Westbound will be closed completely between Sunland Park (Exit 13) and North Mesa Street (SH 20).

·      North Mesa Street (SH 20) will be closed completely in both directions between Osborne Drive and Remcon Circle.

·      I-10 Eastbound will close completely between Sunland Park (Exit 13) and Executive Center Boulevard. Motorists will be detoured onto Doniphan Drive.

·      Both Sunland Park entrance ramps to I-10 Eastbound will close.

·         Paisano Drive (US 85) will close at Sunland Park Drive.

·         Crockett Street access to Paisano Drive (US 85) will close.

·         The Resler Drive flyover ramp to I-10 Eastbound will close.

 

I-10 East at Sunland Overnight

June 18-21

9 pm each night to 6 am each morning

 

·      I-10 Eastbound will close completely between Sunland Park (Exit 13) and Executive Center Boulevard. Motorists will be detoured onto Doniphan Drive.

·      Both Sunland Park entrance ramps to I-10 Eastbound will close.

·      Paisano Drive (US 85) will close at Sunland Park Drive.

·      Crockett Street access to Paisano Drive (US 85) will close.

·      The Resler Drive flyover ramp to I-10 Eastbound will close.

 

I-10 West at Mesa

 

27 HOURS

Sunday, July 1

3 am to 6 am the next day

 

·      I-10 Westbound will close completely at North Mesa Street (Exit 11). Motorists will exit at North Mesa (Exit 11 and follow the frontage to re-enter I-10 at the next entrance ramp.

·      North Mesa Street (SH 20) will close completely in both directions under the I-10 overpass. All entrance ramps to I-10 from North Mesa Street will be open. Follow the detour signs.

·      NOTE: Crews could open North Mesa Street (SH 20) as early as 4 pm on July 1.

 

Crews will be placing bridge deck panels and pouring concrete onto the new I-10 Westbound overpass.

  

Curing Time: For several hours during this closure, it may seem as though no work is taking place; but in fact, the freshly poured concrete will be curing (drying and hardening).

 