TxDoT/Go10 Closures, Detours and More for Week of April 29th

The first of a few major closures in the Sunland Park Drive area started this weekend, however there is good news: the Sunland Park flyover opens by 6 a.m. Monday.

Crews will demo Sunland Park structures the following three weekends in May. 

 

 

 

Meanwhile, starting May 7 and lasting through the summer, I-10 in both directions will be reduced to two lanes near Sunland Park

To keep track of all the closures on GO10 sign up for those alerts at go10elpaso.com.

West Area Closures  |  East Area Closures  |  Border West Expressway Closures

LOCATION DURATION DESCRIPTION
Sunland Park 27 HOURS

3 am Sunday, April 29

through

6 am Monday, April 30

 

·      Sunland Park Drive in both directions will close between Doniphan Drive and Mesa Hills Drive.

·      All entrance ramps and exit ramps at Sunland Park will close.

 

Businesses:  Access to businesses along Sunland Park Drive will be maintained.

 

Detours:

o   Motorists on I-10 Eastbound who want to exit at Sunland Park Drive (Exit 13) will instead exit at North Mesa Street (Exit 11), then follow the detour signs to get to Sunland Park Drive.

o   Motorists on I-10 Westbound who want to exit at Sunland Park Drive (Exit 13) will instead exit at Executive Center Boulevard, then follow the detour signs to get to Sunland Park Drive.

 

Crews are working to reconfigure traffic patterns on the Sunland Park Drive overpass and to open the new Sunland Park flyover ramp.

 

Sunland Park

FLYOVER

OPEN  

6 am April 30

 

NEW STRUCTURE OPEN

·      The NEW Sunland Park Drive flyover entrance ramp to I-10 Eastbound opens.

 

Sunland Park OVERPASS Continuous, 24/7

6 am April 30 and until further notice

 

TRAFFIC SHIFT

·      Traffic will be diverted onto a narrower Sunland Park Drive overpass for at least five months and until further notice.

 

North Mesa

 

Overnight

April 30-May 3

9 pm each night to 6 am each morning

·      North Mesa Street (SH 20) will reduce to one lane in each direction between Osborne Drive and Remcon Circle.

 

Crews are demolishing the median of North Mesa Street (SH 20) and installing temporary paving.

 

North Desert

 

Continuous, 24/7

9 am April 30 and until further notice

 

·      North Desert Boulevard will be reduced to one lane for approximately 2,000 feet starting at North Mesa Street. The entrance ramp will remain open.

 

Crews are widening North Desert Boulevard.

I-10 West at Sunland

 

Overnight

April 30-May 3

9 pm each night

to

6 am each morning

 

·      I-10 Westbound will close between the Sunland Park exit and entrance ramps.

 

Detour: Motorists will exit at Sunland Park (Exit 13) and immediately re-enter I-10 Westbound using the Sunland Park entrance ramp.

 

Crews will be plugging potholes.

 

I-10 East at Resler

 

Daytime

May 1

9 am to 4 pm

 

·      I-10 Eastbound will be reduced to two lanes for approximately 200 feet at Resler Drive.

 

Crews will be setting barrier to install a new exit sign.

 

I-10 Both Directions near Sunland Continuous, 24/7

6 am May 7 and until further notice

 

·      I-10 in both directions will reduce to two lanes for a distance of 3,500 feet between Sunland Park Drive and the Buena Vista area.

 

Crews begin work to replace the pavement and barrier rail in the median of I-10.

 

I-10/Sunland Interchange 57-HOUR CINCO DE MAYO WEEKEND

9 pm Friday, May 4

to

6 am Monday, May 7

 

·      I-10 in both directions will close between the Sunland Park exit and entrance ramps.

·      All Sunland Park Drive overpasses in both directions will close.

·      The Resler entrance ramp to I-10 East will close.

 

Detour:  I-10 traffic will exit at Sunland Park (Exit 13) and immediately re-enter I-10 at the next ramp.

 

Crews will be demolishing the Sunland Park Drive overpass.

 

NOTE: There will be an interruption of work on Sunday, May 6, from 4:30 a.m. to 10:30 a.m. During this time, southbound traffic on Sunland Park Drive will be allowed access across the Sunland Park overpass.

 

OVERSIZED vehicles and high clearance vehicles may have a different detour route during these closures. For oversize permits and routes, got to http://txdmv.gov/motor-carriers/oversize-overweight-permits.

 

I-10/Sunland Interchange 57-HOUR MOTHER’S DAY WEEKEND

9 pm Friday, May 11

to

6 am Monday, May 14

 

 

·      I-10 in both directions will be closed at the Sunland Park exit and entrance ramps.

·      Sunland Park Drive southbound will close between Mesa Hills Drive and Paisano Drive (US 85).

·      The Sunland Park Drive northbound overpass will close.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      The Resler entrance ramp to I-10 East will close.

 

Detours:

    • I-10 Westbound traffic will exit at Sunland (Exit 13) and follow Sunland Park Drive to North Mesa St (SH 20), then follow North Mesa St (SH 20) to re-enter I-10 Westbound from the North Mesa entrance ramp.
    • I-10 Eastbound traffic will exit at Sunland (Exit 13) and immediately re-enter I-10 at the next ramp.

 

Crews will be removing 28 massive steel girders from the old Sunland flyover ramp.

  

NOTE: A third 57-hour weekend closure may be needed May 18-21 if work does not progress as planned. Progress could be impeded by factors such as wind.

 

OVERSIZED vehicles and high clearance vehicles may have a different detour route during these closures. For oversize permits and routes, got to http://txdmv.gov/motor-carriers/oversize-overweight-permits.

 

TxDoT/Go10 Closures, Detours for Week of April 22nd

Drivers that use the Sunland Park Interchange and I-10 in the area will experience a traffic switch, lane reductions and multiple weekend closures in May as construction advances on TxDOT’s GO 10 project.

Traffic Switch/27-Hour Closure

Crews will close Sunland Park Drive from Mesa Hills Drive to Doniphan Drive in both directions – along with all ramps at Sunland Park – from Sunday, April 29 at 3 a.m. to Monday, April 30 at 6.

The closure is needed to prepare for a traffic shift. During the 27-hour closure, motorists will be allowed access to businesses along Sunland Park Drive. Police officers and road signs will be in place to help drivers navigate the closure. Through traffic should avoid the Sunland Park corridor.

The traffic shift starts April 30 when crews close the Sunland Park overpass and shift traffic onto the newly constructed turnaround bridge parallel to the overpass for travel. The shift onto the turnaround bridge will mean fewer through lanes:  two northbound lanes and one southbound lane.

To assist drivers during this shift, the new Sunland Park flyover will be open. They can also use the westbound on ramp to I-10.

The closure and traffic shift will last at least five months. During that time crews will demolish and replace the Sunland Park Drive overpass. The new overpass will have an increased clearance height and additional lanes.

Extended Closures

57-Hour Weekend #1

I-10 will close in both directions between the Sunland Park exit and entrance ramps, the Sunland Park overpasses will close, and the Sunland Park flyover ramp will close from 9 p.m. Friday, May 4-Monday, May 7 at 6 a.m. Crews will be demolishing the Sunland Park Drive overpass. Drivers will be detoured onto the I-10 eastbound and westbound frontage road ramps.

57-Hour Weekend #2

The following weekend, I-10 will close so crews can continue the demolition and begin to remove massive steel girders from the old Sunland Park flyover ramp. I-10 at Sunland Park will close; Sunland Park Drive will close from Mesa Hills to Paisano, the Sunland Park flyover ramp will close, and the I-10 westbound on ramp at Sunland Park Drive will close.

Drivers traveling on I-10 eastbound will use the on/off ramp as a detour. Westbound traffic will exit at Sunland Park and use North Mesa Street (SH 20) as a detour. Closures will be in place Friday, May 11 from 9 p.m.-Monday, May 14 at 6 a.m.

57-Hour Weekend #3

A third 57-hour weekend closure may be needed if work does not progress as planned. Progress could be impeded by factors such as wind.  If a third 57-hour closure is needed, it will be Friday, May 18 from 9 p.m. – Monday, May 21 at 6 a.m.

Lane Reduction

A new traffic configuration will be in place on I-10, in both directions, through summer starting May 7. Lanes will be reduced to two lanes between Sunland Park and Buena Vista. Crews will be replacing the pavement and guard rail in the median of I-10.

The major takeaways for this week are:

LOCATION DURATION DESCRIPTION
North Mesa

 

Overnight

Monday, April 23 through Thursday, April 26

 

9 pm each night to 6 am each morning

·      North Mesa Street (SH 20) will be reduced to one lane in both directions between Osborne Drive and Remcon Circle.

 

Crews will demolish the median of North Mesa (SH 20).

 

I-10 West at Executive Center

 

Overnight

Monday, April 23 through Thursday, April 26

 

9 pm each night to 6 am each morning

 

·      I-10 Westbound will close between the Executive Center Boulevard exit (Exit 16) and Sunland Park Drive.

·      The Schuster Avenue entrance ramp to I-10 Westbound will close.

 

Detour: Motorists will exit at Executive Center Blvd (Exit 16) and follow the detour signs to North Mesa St (SH 20) and then to Sunland Park Dr. Motorists may re-enter I-10 Westbound via the Sunland Park entrance ramp.

 

Crews will be plugging potholes and hauling dirt.

Sunland Park

 

Continuous, 24/7

Through Monday, April 30

·      Sunland Park Drive northbound will have a right lane closed between Constitution Drive and Paisano Drive (US 85).

 

Motorists should proceed with caution.

 

Crews will be conducting pavement work at the I-10/Sunland Park interchange.

 

 

ATTENTION

On April 30th, the Sunland Park flyover opens and the Sunland Park overpass closes.

But first, a 27-hour closure of Sunland Park Drive is required on Sunday, April 29.

Sunland Park

 

27 HOURS

3 am Sunday, April 29

to

6 am Monday, April 30

 

·      Sunland Park Drive in both directions will close between Doniphan Drive and Mesa Hills Drive.

·      All entrance ramps and exit ramps at Sunland Park will close.

 

Businesses:  Access to businesses along Sunland Park Drive will be maintained.

 

Detours:

o   Motorists on I-10 Eastbound who want to exit at Sunland Park Drive (Exit 13) will instead exit at North Mesa Street (Exit 11), then follow the detour signs to get to Sunland Park Drive.

o   Motorists on I-10 Westbound who want to exit at Sunland Park Drive (Exit 13) will instead exit at Executive Center Boulevard, then follow the detour signs to get to Sunland Park Drive.

 

Crews are reconfiguring traffic patterns on the Sunland Park Drive overpass. The change will detour motorists onto the newly constructed, adjacent overpass starting at 6 am on Monday, April 30. The reconfigured traffic pattern will be in place for at least five months and until further notice while crews demolish and reconstruct the closed overpass.  More at http://bit.ly/SunlandSwitch.

 

Sunland Park

FLYOVER

Continuous, 24/7

Until 6 am Monday, April 30

 

·      The Sunland Park Drive flyover entrance ramp to I-10 Eastbound remains inaccessible.

 

Detour:  While the flyover entrance ramp is closed, motorists should continue to follow the detour signs to the Paisano Drive entrance ramp.

 

Sunland Park OVERPASS

 

Continuous

Starting at 6 am Monday, April 30 and until further notice

·      The Sunland Park Drive overpass that allows traffic across I-10 will be closed for at least five months.

 

Detour:  Traffic will be detoured onto the newly constructed turnaround bridge located alongside the closed overpass.

 

Crews will be demolishing and reconstructing the closed overpass. More at http://bit.ly/SunlandSwitch.

 

ATTENTION

For two weekends in May, the I-10/Sunland Park interchange will shut down. Crews to demolish bridges.

A third weekend closure may be needed if work does not progress as planned.

I-10/Sunland Interchange

 

57-HOUR WEEKEND #1

9 pm Friday, May 4

to

6 am Monday, May 7

 

·      I-10 in both directions will close between the Sunland Park exit and entrance ramps.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

·      All Sunland Park Drive overpasses in both directions will close.

 

Detour:  I-10 traffic will exit at Sunland Park (Exit 13) and immediately re-enter I-10 at the next ramp.

 

Crews will be demolishing the Sunland Park Drive overpass.

 

NOTE: There will be an interruption of work on Sunday, May 6, from 4:30 am to 10:30 am. During this time, southbound traffic on Sunland Park Drive will be allowed access across the Sunland Park overpass.

 

OVERSIZED vehicles and high clearance vehicles may have a different detour route during this closure. For oversize permits and routes, go to http://txdmv.gov/motor-carriers/oversize-overweight-permits.

 

I-10/Sunland Interchange

 

57-HOUR WEEKEND #2

9 pm Friday, May 11

to

6 am Monday, May 14

 

 

·      I-10 in both directions will be closed at the Sunland Park exit and entrance ramps.

·      Sunland Park Drive southbound will close between Mesa Hills Drive and Paisano Drive (US 85).

·      Sunland Park Drive northbound will close at the I-10 overpass.

·      The Sunland Park entrance ramp to I-10 Westbound will close.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

 

Detours:

I-10 Westbound traffic will exit at Sunland (Exit 13) and follow Sunland Park Drive to North Mesa St (SH 20), then follow North Mesa St (SH 20) to re-enter I-10 Westbound from the North Mesa entrance ramp.

I-10 Eastbound traffic will exit at Sunland (Exit 13) and immediately re-enter I-10 at the next ramp.

 

OVERSIZED vehicles and high clearance vehicles may have a different detour route during these closures. For oversize permits and routes, go to http://txdmv.gov/motor-carriers/oversize-overweight-permits.

 

Crews will painstakingly remove 28 massive steel girders from the old Sunland Park flyover ramp. Each girder weighs more than 100,000 pounds. The girders will be cut into 30-foot sections, then carried (not dropped) and placed onto waiting trucks.

 

The dismantling of the girders will be accomplished with the help of cranes, each positioned near newly erected Sunland bridges. Crane setup alone takes six hours. Re-positioning of the cranes will be necessary during the girder removal process.

 

The operation is dangerous and requires precision. If winds reach 25 miles per hour, the operation will be halted.

 

Thank you for your patience during these high profile weekend closures.

 

I-10/Sunland Interchange

 

57-HOUR WEEKEND #3

May 18-21

Still developing:

A third 57-hour weekend closure may be needed if work does not progress as planned during the first two weekends. Progress may be impeded by factors such as wind.