Go10 Closures for the Week of April 24th

While work at I-10 and Sunland continues this week, engineers and crews plan to close I-10 for three nights in May.

I-10 & Sunland

Daytime – Monday, April 24 through Friday, April 28

9 a.m. to 4 p.m. each day

  • The two-lane Sunland Park Exit Ramp (Exit 13, Westbound) will be reduced to one lane.

This closure is necessary to give crews access to the work site. [No Map]

 

Daytime – Monday, April 24 through Friday, April 28

9 a.m. to 4 p.m. each day

  • The left lane on I-10 in both directions will close between Buena Vista and Sunland Park.

Crews are constructing new US 85 bridge columns in the area. Thank you for your patience. [See Map]

 

Daytime – Monday, April 24 through Wednesday, April 26

9 a.m. to 4 p.m. each day

  • The left turn lane from the I-10 Westbound Sunland Park Exit Ramp onto Sunland Park Drive will close.

Crews will be installing a traffic camera in the area. [See Map]

 

Overnight – Tuesday, April 25

9 p.m. to 6 a.m. the next morning

  • I-10 Westbound will be reduced to one lane between Buena Vista and the Sunland Park Entrance Ramp to I-10 Westbound.

Crews are re-setting barrier walls. [No Map]

 

I 10 WILL CLOSE FOR THREE NIGHTS

I-10 & Resler

Overnight – Tuesday, May 9

9 p.m. to 6 a.m. the next morning

  • I-10 Westbound will close completely between Resler Drive (Exit 12) and North Mesa Street (Exit 11).

Crews will be pouring bridge deck onto the new Resler Flyover Ramp. [No Map]

Detour: Traffic on I-10 West will exit at Resler Drive (Exit 12), take Resler Drive to North Mesa Street (SH 20), and take North Mesa Street to I-10 Westbound.

 

Overnight – Wednesday, May 10 and Thursday, May 11

9 p.m. each night to 6 a.m. each morning

  • I-10 in both directions will close completely at Resler Drive (Exit 12).

Crews will be pouring bridge deck onto the new Resler Flyover Ramp. [No Map]

Westbound Detour:        Vehicles traveling on I-10 West will exit at Resler Drive (Exit 12), take Resler Drive to North Mesa Street (SH 20), and take North Mesa Street to I-10.

Eastbound Detour:  Vehicles traveling on I-10 East will exit at North Mesa Street (Exit 11), take North Mesa Street (SH 20) to Doniphan Drive (SH 20), take Doniphan Drive to Sunland Park Drive, and take Sunland Park Drive to I-10.

G010_ClosureMap_042117

TxDoT website continues to explain on-going West El Paso construction on I10

Just about a year into the multi-million dollar Interstate 10 reconstruction project, officials with the Texas Department of Transportation here in El Paso continue to explain the project and help motorists find routes around the the work.

Known as Go10 Project, the information is available via a website or a facebook page that were first launched late last year. In addition to the social media sites, motorists can get updates via twitter or email, simply by signing up at the site.

The project is slated to be completed in 2019 and encompasses the infrastructure reconstruction of Interstate 10 (I-10) on El Paso’s Westside, between the Executive Center Boulevard and North Mesa Street (SH 20) exits.

The $158 million project extends 5.75 miles and entails four major components:

• The construction of collector-distributor lanes through the corridor

• The improvement of I-10’s direct connection with Paisano Drive (US 85) and the Border West Expressway

• The intermittent addition of lanes to I-10’s mainlanes in both directions

• The reconfi guration of ramps and overpasses at Sunland Park Drive, Resler Drive, and North Mesa Street The project will also entail upgrades to a portion of North Mesa Street and portions of North and South Desert Boulevard frontage roads, such as improved turning movements and drainage.  Turnarounds will be constructed at North Mesa Street and Sunland Park Drive.