Go10/TxDoT Closures and Detours for Week of January 27

This Monday, there will be no entry to I-10 East from North Mesa Street. Drivers are asked to use an alternate entrance ramp.

Additionally, GO 10 managers have extended the closure of Paisano Drive (US 85) to March 4 due to cold overnight temperatures having caused delays to other nearby work.

In two weeks, GO 10 is planning a 24-hour closure of I-10 East at Redd Road on Sunday, Feb. 11.

This closure allows crews to prepare for the demolition the I-10 West overpass at North Mesa in late February or early March.

LOCATION DURATION DESCRIPTION
Paisano (US 85) @ Sunland

 

Ongoing – 24/7

Jan. 15-Mar. 4

 

·      Paisano Drive (US 85) remains closed for approximately 300 feet starting at Sunland Park Drive.

·      Sunland Park Drive will be kept to two lanes starting at Constitution Drive up to the Paisano Drive (US 85) intersection.

 

Motorists on Sunland Park Drive (coming from Doniphan Drive) have access to a dedicated right-turn lane leading to the I-10 Eastbound entrance ramp.

 

To help mitigate roadway congestion in this area, motorists should consider using alternate routes.

 

Business Access: Motorists will be able to access area businesses from Sunland Park Drive as well as from Constitution Drive and Crockett Street.

 

North Mesa

 

Daytime

Jan. 29-Feb. 9

9 am to 4 pm weekdays only

 

·      The right lane on North Mesa Street (SH 20) will close from North Desert Blvd to Osborne Drive.

 

I-10 East @ Mesa

 

 

Daytime

Jan. 29

9 am to 4 pm

 

·      The North Mesa Street entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists should use an alternate entrance ramp to I-10 East. Detour signs will direct people to Doniphan Drive and then to the Sunland Park Drive entrance ramp to I-10 Eastbound.

 

I-10 West @ Executive

 

Overnight

Jan. 29

9 pm to 6 am

 

·      I-10 Westbound will close completely between Executive Center Boulevard (Exit 16) and Sunland Park Drive.

·      The Schuster/UTEP entrance ramp to I-10 Westbound will close.

·      The Paisano Drive entrance ramp to I-10 Eastbound (in front of the auto dealerships) will close.

·      Crockett Street access to Paisano Drive will not be available.

 

Detours:

o   I-10 Westbound traffic will exit at Executive Center Boulevard (Exit 16) and take North Mesa Street (SH 20) to Sunland Park Drive where motorists may re-enter I-10 Westbound.

o   Motorists won’t be able to enter I-10 Eastbound from Paisano Drive (US 85) so they will be detoured to North Mesa Street (SH 20), then to Executive Center Boulevard, then to the Executive Center entrance ramp to I-10 Eastbound.

 

I-10 East @ Sunland

 

Overnight

Jan. 30 ‒ Feb. 1

9 pm each night to 6 am each morning

 

·      I-10 Eastbound will close completely between North Mesa Street (Exit 11) and Sunland Park Drive.

·      The North Mesa Street entrance ramp to I-10 Eastbound will close.

·      The Resler Drive entrance ramp to I-10 Eastbound will close.

·      The Sunland Park flyover entrance ramp to I-10 Eastbound will close.

 

Detour:  Motorists on I-10 Eastbound will exit at North Mesa Street (Exit 11) and be routed to Doniphan Drive, then to Sunland Park Drive where motorists may re-enter I-10 Eastbound. Follow the detour signs.

I-10 East @ Redd

 

24-Hour Closure

Sunday, Feb. 11

5 a.m. to 5 a.m. the next morning

 

·      I-10 Eastbound will close completely between Redd Road (Exit 9) and the North Mesa Street overpass.

·      The Redd Road entrance ramp to I-10 Eastbound will close.

 

Detour:  Drivers on I-10 Eastbound will exit at Redd Road (Exit 9) then take the frontage road to North Mesa Street (SH 20), where they will be able to re-enter I-10 Eastbound.

 

Crews will be moving barrier and re-configuring lanes on the I-10 East overpass at North Mesa (SH 20). This work is in preparation for demolition of the I-10 West overpass at North Mesa (SH 20) in late February or early March.