• January 21, 2022
 TxDOT Closures for the week of January 10th

Photo courtesy TxDOT

TxDOT Closures for the week of January 10th

TxDOT Closures for the week of January 10th

Closure Links:

West Area Project Closures   East Area Project Closures   I-10 Connect Project Closures

US-54 Ramp Modification Project

Highway US-54 (Patriot Freeway) Frontage Road

Continuous until further notice.

  • Gateway North between Kenworthy and Golden Sands reduced to two lanes.

Crews will be working on US-54 northbound exit ramp reconfiguration.

 

Tuesday, Jan. 11 and Wednesday, Jan. 12

9 a.m. to 4 p.m.

  • US-54 northbound at Kenworthy exit ramp full freeway closure.
  • Transmountain northbound entrance ramp to US-54 closed.

Crews will be working on painting barrier wall.

 

Replacement of E3 Rail Project

Sunday, Jan. 9

Night, 9 p.m. to 5 a.m.

  • I-10 westbound right two lanes closed.

Crews will be working on removing illumination poles.

Monday, Jan. 10 through Wednesday, Jan. 12

Nightly, 9 p.m. to 5 a.m.

  • I-10 eastbound right two lanes closed.

Crews will be working on removing illumination poles.

Guardrail Repair Project

Monday, Jan. 10

9 a.m. to 4 p.m.

  • I-10 eastbound between Vinton and David left lane closed.
  • Spur 601 westbound to US-54 South overpass closed.

Tuesday, Jan. 11

9 a.m. to 4 p.m.

  • I-10 westbound between Hawkins and Airway right lane closed.
  • Gateway West at McRae on-ramp closed.

Wednesday, Jan. 12

9 a.m. to 4 p.m.

  • I-10 eastbound between Thorn and Mesa left lane closed.
  • Spur 601 westbound between Chaffee and Fred Wilson left and right lanes closed.

Thursday, Jan. 13

9 a.m. to 4 p.m.

  • North Desert between David and Vinton right lane closed.
  • South Desert between Thorn and Mesa right lane closed.

Friday, Jan. 14

9 a.m. to 4 p.m.

  • Loop 375 (Transmountain) westbound between US-54 and the Border Patrol Museum right lane closed.

Miscellaneous Concrete

Monday, Jan. 10 through Friday, Jan. 14

9 a.m. to 4 p.m.

  • I-10 westbound between Dallas and Kansas right lane closed.
  • Missouri westbound at Dallas on-ramp closed.

Crews will be installing curb.

Maintenance

Monday, Jan. 10 through Friday, Jan. 14

9 a.m. to 3 p.m.

  • I-10 westbound at Executive exit ramp closed.
  • North Desert between Vinton and Chile right lane closed.
  • Vinton westbound between Kiely and Doniphan right lane closed.

Crews will be installing signs.

 

Loop 375 Widening Project

Monday, Jan. 10 (complete closure)

3 a.m. until 12 p.m.

  • Loop 375 southbound Alameda Avenue Exit ramp will be closed
  • Loop 375 southbound traffic will detour at Pan American Drive turnaround

Crews will be installing high mast lighting foundations

Monday, Jan. 10 through Thursday, Jan. 13 (complete closure)

Nightly, 9 p.m. until 5 a.m. (overnight)

  • Loop 375 northbound complete lane closure between Pan American Drive and North Loop Drive
  • Loop 375 northbound traffic will exit at Pan American Drive and reenter at North Loop Drive

Crews will be placing temporary shoring, repairing work zone striping and installing drainage improvements

 

I-10 Connect
Monday, January 10, 9 a.m. to 4 p.m.

  • A full closure of Ramp P, which connects US 54 southbound to Loop 375 westbound, will be in place.
  • A full closure of Ramp Y, which connects US 62 to Loop 375 eastbound, will be in place.

Monday, January 10, through Saturday, January 15, 7 a.m. to 5 p.m.

  • A full closure of Gateway East, from entrance ramp to Marr Street, will be in place (as needed). DETOUR: Traffic should use Raynolds Street to access Gateway East.
  • A full closure of the I-10 eastbound entrance ramp at Copia Street will be in place (as needed). DETOUR: Traffic should proceed onto Durazno Avenue and use Raynolds Street to access Gateway East.
  • A closure of the right lane of Paisano Drive eastbound from San Marcial Street to Gateway South (as needed).
  • A closure of the right lane of Paisano Drive westbound from Gateway South to San Marcial Street (as needed).

 Monday, January 10, through Saturday, January 22, 24/7

  • A full closure of the US 54 southbound entrance ramp CD lanes from Cassidy Drive. DETOUR: Traffic should proceed over Pershing Drive, then enter US 54 southbound CD lanes.

 Monday, January 10, through Saturday, January 15, 8 a.m. to 5 p.m.

  • A full closure of truck lanes on I-110 southbound (as needed).

Crews will be working on ornamental fencing at Wall 1.

 Monday, January 9, through Thursday, January 13, 9 a.m. to 4 p.m.

  • A full closure of Ramp H, northbound and southbound, which connects I-10 eastbound to US 54 northbound, will be in place. DETOUR: Traffic should proceed to the Trowbridge Drive turnaround and then I-10 westbound to Ramp A, which connects I-10 westbound to US 54 northbound. Proceed to US 54 northbound, then to the Pershing Drive turnaround and on to US 54 southbound to Juarez.
  • A full closure of Bridge 15/4 at Ramp D, which connects US 54 southbound to I-10 eastbound, will be in place. DETOUR: Traffic should take Ramp D to the Trowbridge Drive turnaround and take I-10 westbound to Ramp A, which connects I-10 westbound to US 54 northbound, to Ramp F, which connects I-10 westbound to I-110 southbound.
  • A full closure of Bridge 2/5 at Ramp F, which connects I-10 westbound to I-110 southbound. DETOUR: Traffic should proceed to US 54 northbound to the Pershing Drive turnaround and then take US 54 southbound to Juarez.
  • A full closure of Bridge 8 at Ramp N, which connects Loop 375 eastbound to I-110 northbound. DETOUR: Traffic should proceed to the Fonseca Drive turnaround to Loop 375 westbound and then to Ramp R, to ramp for I-10 eastbound.
  • A full closure of Ramp B/C, which connects US 54 northbound to Gateway North (B) or US 54 northbound to I-10 westbound (C), will be in place. DETOUR: Traffic should proceed to the Pershing Drive turnaround to Gateway South to Montana Avenue.