Mesa Rehabilitation Project

Continuous until further notice.

  • Mesa northbound between Baltimore and Castellano reduced to one lane.
  • Mesa southbound between Castellano and Brentwood reduced to one lane.
  • Crews will be working on roadway rehabilitation.

Monday, March 8 through Tuesday, March 9

Nightly, 9 p.m. to 5 a.m.

  • Mesa northbound between Brentwood and Castellano complete closure.
  • Mesa southbound between Castellano and Brentwood complete closure.
  • Crews will move and reset concrete traffic barrier.

Bridge Maintenance Project

Sunday, March 7 through Thursday, March 11

Nightly, 9 p.m. to 5 a.m.

  • I-10 westbound at Trowbridge complete closure.
  • All traffic directed to Geronimo.
  • Crews will be replacing armor joints.

Bridge Preventative Maintenance Project

Sunday, March 7 through Thursday, March 11

Nightly, 9 p.m. to 5:30 a.m.

  • I-10 westbound between Paisano and Hawkins alternate lane closures.
  • Crews will be working on bridge joint maintenance and repairs.

Guardrail Repair Project

Monday, March 8

9 a.m. to 4 p.m.

  • North Desert between Artcraft and Northern Pass right lane closed.
  • Crews will be working on guardrail.

Tuesday, March 9

9 a.m. to 4 p.m.

  • North Desert to South Desert between Artcraft and Transmountain turnaround complete closure.
  • Crews will be working on guardrail.

Wednesday, March 10

9 a.m. to 4 p.m.

  • I-10 westbound between Schuster and Executive right lane closed.
  • Crews will be working on guardrail.

Thursday, March 11

9 a.m. to 4 p.m.

  • US-54 northbound between Cassidy and Railroad/Fred Wilson right lane closed.
  • Crews will be working on guardrail.

Friday, March 12

9 a.m. to 4 p.m.

  • Loop 375 eastbound between Yarbrough and Padres right lane closed.
  • Crews will be working on guardrail.

Miscellaneous Concrete

Wednesday, March 10

Nightly, 9 p.m. to 5 a.m.

  • I-10 westbound between Geronimo and Paisano right lane closed with a complete off-ramp closure at Paisano.
  • Crews will be repairing concrete barriers.

  

Maintenance

Monday, March 8 through March 12

9 a.m. to 3 p.m.

  • Spur 601 eastbound between Chaffee and Airport right lane closed.
  • Crews will be doing shoulder work.
  • Sun Bowl and Heisig intersection complete closure.
  • I-10 westbound at Schuster exit ramp closed.
  • Crews will be installing delineators and cleaning.
  • Desert North and Transmountain intersection alternate lane closures.
  • Crew will be doing curb work.
  • I-10 east and westbound between Thorn and Sunland Park alternate lane closures.
  • Crews will be cleaning.

Loop 375 Widening Project

Monday, March 8 through Friday, March 12

Daily, from 9 a.m. until 4 p.m.

  • Joe Battle Boulevard (frontage road) northbound right lane closure between Rojas Drive and Pellicano Drive
  • Traveling public will be restricted to two lanes

Crews will be installing drilled shafts for high mast lighting.

Monday, March 8 through Thursday, March 11

Daily and Nightly, from 9 a.m. until 9 p.m.

  • Joe Battle Boulevard (frontage road) southbound left lane closure between Bob Hope Drive and Rojas Drive
  • Traveling public will be restricted to one lane

Crews will be installing drilled shafts for high mast lighting.

Monday, March 8 through Thursday, March 11

Daily, from 9 a.m. until 4 p.m.

  • Loop 375 southbound right shoulder closure between Bob Hope Drive and Rojas Drive
  • Traveling public will be restricted to two lanes