In addition to the on-going work around the El Paso area, the I-10 Connect Project isn’t just using concrete and steel to improve traffic flow in Central El Paso.

It will also add intelligent traffic system (ITS) components like overhead lane management system (LMS) signs, additional dynamic message signs (DMSs) and new TransVista cameras to the Texas Department of Transportation’s set of tools to manage traffic flow through the heart of the city.

Work on several of those components will lead to complete closures on US 54 next week as well as lane closures on Interstate 10. Motorists are encouraged to avoid travel in the area during the closures if possible

Closure Links:  West Area Project Closures   |   I-10 Connect Closures   |   East Area Project Closures

Transmountain Project

Daily until further notice.

  • Transmountain (Loop 375) west and eastbound between US-54 and Tom Mays State Park reduced to one lane in both directions.  Bike lane closed.
  • Alternate lane closures to include shoulder closures west and eastbound between US-54 south and Resler.
  • Crews will be working on cable barrier, milling, paving, and installation of metal beam guardrail fence.

Sunday, April 11 through Thursday, April 15

Nightly, 9 p.m. to 6 a.m.

  • Loop 375 west and eastbound between US-54 south and Resler complete closure.
  • Crews will be working on detours, traffic switch, and moving of concrete barriers.

Mesa Rehabilitation Project

Continuous until further notice.

  • Mesa northbound/southbound between Castellano and Festival reduced to one lane.
  • Crews will be working on roadway rehabilitation.

Tuesday, April 13 through Thursday, April 15

Nightly, 9 p.m. to 5 a.m.

  • Mesa northbound between Castellano and Festival complete closure.
  • Detour: Access for through traffic will be provided.
  • Crews will be milling.

Bridge Maintenance Project

Monday, April 12 through Thursday, April 15

Nightly, 9 p.m. to 5 a.m.

  • I-10 eastbound at Hawkins bridge complete closure.
  • All traffic directed to Hawkins, Exit 26.
  • Crews will be replacing armor joints.

Guardrail Repair Project

Monday, April 12

9 a.m. to 4 p.m.

  • Loop 375 eastbound between Ascarate Park and Fonseca right lane closed.

Tuesday, April 13

9 a.m. to 4 p.m.

  • I-10 eastbound at Trowbridge on-ramp complete closure.

Wednesday, April 14

9 a.m. to 4 p.m.

  • US-62 eastbound between St. Vrain and Paisano left lane closed.

Thursday, April 15

9 a.m. to 4 p.m.

  • Gateway North at Cassidy on-ramp complete closure.

Friday, April 16

9 a.m. to 4 p.m.

  • US-54 southbound between Hercules and Dyer right lane closed.

Bridge Preventative Maintenance Project

Sunday, April 11 through Thursday, April 15

Nightly, 9 p.m. to 5:30 a.m.

  • I-10 westbound between Paisano and Hawkins alternate lane closures.
  • Crews will be working on bridge joint maintenance and repairs.

Loop 375 Frontage Road Project

Saturday, April 10

9 a.m. until 4 p.m.

  • Loop 375 northbound to southbound left shoulder closure between South Americas Avenue and North Loop Drive
  • Loop 375 main lanes will remain open

Crews will be dismantling traffic cameras

Monday, April 12 through Friday, April 16 (Be prepared to stop)

Daily, from 9 a.m. until 4 p.m.

  • South Americas Avenue (frontage road) southbound to northbound turnaround at Union Pacific Railroad (UPRR) tracks will be blocked occasionally
  • South Americas Avenue southbound to northbound traffic will remain open and be flagged through work zone

Crews will be hauling concrete and materials

Monday, April 12 through Friday, April 16 (Be prepared to stop)

Daily, from 9 a.m. until 4 p.m.

  • South Americas Avenue (frontage road) northbound to southbound turnaround complete closure at North Loop Drive
  • Traveling public traffic detour at North Loop intersection

Crews will be hauling concrete and materials

Loop 375 Widening Project

Monday, April 12

9 p.m. until 4 a.m. (overnight)

  • Joe Battle Boulevard (frontage road) southbound Pellicano Drive entrance ramp to Loop 375 closed
  • Joe Battle Boulevard (frontage road) southbound Bob Hope Drive entrance ramp to Loop 375 closed
  • Traveling public will travel on Joe Battle Boulevard (frontage road) to North Loop Drive entrance ramp

Crews will be working on pavement markings and traffic barrier placement for Phase II configuration

Tuesday, April 13 through Thursday, April 15

Nightly, 9 p.m. until 4 a.m. (overnight)

  • Loop 375 northbound closure between I-10 to Pellicano Drive

Crews will be working on pavement markings and traffic barrier placement for Phase II configuration

Monday, April 12 through Friday, April 16

Daily, from 9 a.m. until 4 p.m.

  • Joe Battle Boulevard (frontage road) southbound right lane closure between Pellicano Drive to Rojas Drive
  • Joe Battle Boulevard (frontage road) northbound right lane closure between Rojas Drive to Pellicano Drive
  • Americas Avenue (frontage road) southbound right lane closure between Gateway Boulevard East and North Loop Drive
  • Americas Avenue (frontage road) southbound right lane closure between Pan American Drive and Southside Road
  • Americas Avenue (frontage road) northbound right lane closure between North Loop Drive and Gateway Boulevard East
  • Americas Avenue (frontage road) northbound left lane closure between Zaragoza Road and Joe Rodriguez Drive

Crews will be working on illumination infrastructure

Monday, April 12 through Thursday, April 15

Nightly, from 9 p.m. until 4 a.m. (overnight)

  • Loop 375 southbound right lane closure between Loop 375 exit ramp to North Loop overpass

Crews will be working on illumination infrastructure

IH-10 Mill and Inlay Project

Sunday, April 11 through Thursday, April 15 (complete closure)

Nightly, from 9 p.m. until 6 a.m. (overnight)

  • I-10 eastbound complete lane closure between McRae Boulevard and Lomaland Drive to include entrance and exit ramps

Crews will be performing grinding operation

Monday, April 12 through Friday, April 16

Daily, from 7 a.m. until 4 p.m.

  • Gateway Boulevard eastbound left lane closure between McRae Boulevard and Lomaland Drive to include entrance and exit ramps
  • Gateway Boulevard eastbound to westbound turnaround at Lee Trevino Drive closed

Crews will be performing electrical work, rock wall installation and removal

I-10 Connect

Sunday, April 11, from 9pm to 5am

  • Southbound US 54 will be reduced to a single lane between Cassidy Road and Thompkins Road.
  • The on ramp from Gateway Boulevard South to southbound US 54 at Cassidy road will be closed to all traffic.
  • DETOUR: Continue on Gateway South, enter US 54 at Pershing.

Crews will be working on a drilled shaft for an overhead sign.

Monday, April 12, from 9pm to 5am

  • Eastbound I-10 will be reduced to a single lane between Cotton Street and Piedras Street.
  • Gateway Boulevard East will be reduced to a single lane between Cotton Street and Piedras Street.
  • The onramp from Cotton Street to eastbound I-10 will be closed to all traffic.
  • NOTE: This closure may be repeated on Wednesday, April 14.

Crews will be working on LMS signs.

Monday, April 12, from 9pm to 5am

  • Southbound US 54 will be closed to all traffic between Spur 601 and Pershing Drive.
  • DETOUR: Take Exit 22B (Fort Bliss/Pershing Drive), then take the Pershing Drive/Altura Avenue exit, continue on Gateway South, and re-enter southbound US 54 at Pershing.
  • The offramp from westbound Spur 601 to southbound US 54 will be closed to all traffic.
  • DETOUR: Take northbound US 54, take Exit 24 (Ellerthorpe Avenue), u-turn at Ellerthorpe to enter southbound US 54.

Crews will be working on LMS signs.

Tuesday, April 13, from 9pm to 5am

  • The mainlanes of southbound US 54 will be closed to all traffic between Pershing Drive and I-10.
  • DETOURS: All traffic will be detoured into the collector/distributor (C/D) lanes. Traffic bound for eastbound I-10 will take Exit 21B (I-10 West/Las Cruces/Downtown), continue to Exit 20 (Cotton Street), turn left on Cotton and left on eastbound I-10. Traffic bound for Loop 375 will take Exit 21C (Montana Avenue), continue on Gateway Boulevard South, and re-enter southbound US 54 at Yandell Drive.
  • NOTE: During this closure, all traffic must access the Bridge of the Americas by taking westbound I-10 to Exit 22B (US 54/Juárez/Alamogordo/Fort Bliss), then veer left taking the “Juárez, México” exit to southbound Interstate 110.
  • NOTE: This closure may be repeated on Wednesday, April 14.

Crews will be working on LMS signs.

Tuesday, April 13, from 9pm to 5am

  • Northbound US 54 will be reduced to a single lane between Pershing Drive and Cassidy Road.
  • The on-ramp from Gateway Boulevard North to northbound US 54 at Pershing Drive will be closed to all traffic.

Crews will be drilling a support shaft for a new dynamic message sign (DMS).

Wednesday, April 14, from 9pm to 5am

  • Westbound I-10 will be reduced to a single lane between US 54 and Copia Street.

Crews will be drilling a support shaft for a new dynamic message sign (DMS).

Thursday, April 15, from 9pm to 5am

  • The C/D lanes on southbound US 54 will be closed to all traffic between Pershing Drive and Montana Avenue.
  • Onramps from Gateway Boulevard South to southbound US 54 north and south of Pershing will be closed to all traffic; onramps at Trowbridge and Yandell will be open.
  • DETOUR: Traffic bound for westbound I-10 will take Exit 21A (I-10 East/San Antonio), continue on eastbound to I-10 to Exit 24A (Trowbridge Drive), use the newly widened turnaround and enter westbound I-10.

Crews will be removing an existing overhead sign.

Thursday, April 15, from 9pm to 5am

  • Northbound US 54 will be reduced to a single lane between Pershing Drive and Cassidy Road.
  • The offramp from northbound US 54 to Cassidy Road will be closed to all traffic.
  • DETOUR: Take Exit 24A (Fred Wilson Avenue) and use the turnaround to enter southbound US 54. Continue to Exit 22 (Fort Bliss/Pershing Drive), then take the Fort Bliss/Cassidy Road exit.

Crews will be working on a new LMS sign and a support shaft for a new TransVista camera.

Nightly I-110 Closures Coming Later This Spring

In the coming weeks, crews will begin installing nearly forty overhead bridge girders as they reconstruct the overpass which will carry US 62 (Paisano Drive) over Interstate 110 immediately north of the Bridge of the Americas. To safely conduct this work, southbound I-110 leading to the bridge will close nightly for several weeks later this spring. An exact date for this work has not yet been finalized. Updated information will be provided as soon as it is available.

On-Going Closures Will Continue Without Interruption

  • Ramp H which connects eastbound I-10 to US 54 and Juárez remains closed until further notice.
  • Interstate 110, the short freeway spur leading to and from the Bridge of the Americas, remains closed to northbound traffic until further notice.
  • US 62 (Paisano Drive) remains closed to traffic in both directions between San Marcial Street and Gateway Boulevard South.
  • Gateway Boulevard East remains closed to thru traffic between Loop 478 (Copia Street) and Marr Street.
  • The ramp from southbound US 54 to US 62 (Paisano Drive) remains closed until further notice.
  • Both turnarounds under US 54 at US 62 (Paisano Drive) remains closed until further notice.
  • Intermittent closures on Durazno Avenue, Rosa Avenue and Uva Street.
  • Intermittent lane closures on Gateway Boulevard East between Piedras Street and US 62/180 (Paisano Drive).
  • Intermittent lane closures on Gateway Boulevard West between Boone Street and Palm Street.

Onramp and offramp closures may begin up to one hour earlier than stated times. All information is subject to change based upon weather and field conditions.

Staff Report

Staff Reports are just that, Staff Reporting the news. No skew, no opinion just the news. We pride ourselves on making sure that we bring you the news as soon as it is published, submitted or sent to us. No need to have a reporter rewrite or give their opinion. The facts or information, nothing more.

Related post

El Paso Herald Post Download the new ElPasoHeraldPost.com app and get notifications for community news, deals and community calendar info. Your info is never shared and we would love for you to share our app with your friends!
Dismiss
Allow Notifications