TxDoT/Go10 Closures/Detours and Projects for Week of May 27
All closures next week happen at night, including full closures of Mesa and I-10.
Stay informed on all the closures/work/projects, follow TxDoT Twitter and sign up for email alerts here
Border West Expressway | West Area Project Closures | East Area Project Closures | GO10 Closures
LOCATION | DURATION | DESCRIPTION |
North Mesa Street
|
Overnight
May 29-31 9 pm each night to 6 am each morning
|
· North Mesa Street (SH 20) will reduce to one lane in both directions between Osborne and Remcon streets.
· North Mesa Street (SH 20) will be closed completely under the I-10 overpass.
Crews are demolishing the medians, installing pavement, and setting deck panels onto the new I-10 Westbound overpass.
|
I-10 West at Sunland Park | Overnight
May 29 9 pm to 6 am the next morning
|
· I-10 Westbound will close completely between the Sunland Park exit and entrance ramps.
Detour: Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 at the next entrance ramp.
Crews will be plugging potholes. |
I-10/Sunland Park
|
Overnight
May 30-31 9 pm each night to 6 am each morning
|
· I-10 Eastbound will close completely between the Sunland Park exit and entrance ramps.
· The Sunland Park Drive flyover ramp to I-10 Eastbound will close. · Paisano Drive (US 85), including the entrance ramp to I-10 Eastbound, will close. · Crockett Street access to Paisano Drive (US 85) will close. · The Resler Drive flyover ramp to I-10 Eastbound will close. · I-10 Westbound will close completely between the Sunland Park exit and entrance ramps.
Detours: o Motorists on I-10 Westbound will exit at Sunland Park (Exit 13) and immediately re-enter I-10 at the next entrance ramp. o Motorists on I-10 Eastbound will exit at Sunland Park (Exit 13), then follow Sunland Park Drive to Doniphan Dr., then follow Doniphan Dr. to Executive Center Boulevard. Motorists may re-enter I-10 using the Executive Center Boulevard entrance ramp.
Crews will be installing underpass lighting, installing concrete pavement, and working on bridge structures.
|
North Desert Boulevard
|
Continuous, 24/7
|
Crews are widening North Desert Boulevard |
Doniphan Drive
Friday, June 1, to Monday, June 4
9 p.m. to 5 a.m. (continuous full closure)
- Eastbound and westbound from Racetrack to Paisano
- Closure is needed for painting barrier
US 54 Widening and Illumination Project
Tuesday, May 29, through Thursday, May 31
9 p.m. to 6 a.m. (two nights only)
- Complete closure on US 54 southbound between Sean Haggerty entrance ramp to the Hondo Pass entrance ramp
- Detour: Southbound traffic will stay on the frontage road and enter US 54 at the Transmountain entrance ramp
- Crews will be drilling in the area
Spalling Repair Project
Tuesday, May 29, through Thursday, May 31
9 p.m. to 5 a.m. (nightly)
- Alternate lane closures on I-10 westbound between Copia overpass to the Cotton overpass
- I-10 westbound Piedras entrance and exit ramps will be closed
- Ramp K (US 54 south to I-10 west) will be closed
- Crews will be repairing spalled concrete pavement (potholes) in the area
Maintenance
Tuesday, May 29, through Friday, June 1
9 a.m. to 3 p.m. (throughout the day)
- Alternate entrance and exit ramp closures on Cesar Chavez/Border Highway (Loop 375) east and westbound between Fonseca to Zaragoza
- Alternate lane closure on Railroad Drive north and southbound between US 54 to Spur 601
- Ramp on US 54 south to Spur 601 east will be closed
- Right lane closure on US 54 southbound between Pershing to Yandell
- US 54 northbound Pershing entrance ramp will be closed
Mall Braided Ramps Project
Tuesday, May 29, through Friday, June 1
8 a.m. to 4 p.m.
- Gateway Boulevard eastbound and westbound alternating right or left lane closures between Viscount Boulevard and Airway Boulevard
- Crews will be installing high mast illumination