TxDoT/Go10 Construction, Detours for Week of July 15
Next week closures on I-10 will still be in effect so progress can continue to be made on the Sunland Park Drive overpass.
In addition, the I-10 closure for our Vinton project was rescheduled for the 17 and 18, US 54 southbound will be closed all weekend between Hondo Pass and Hercules for work on the pedestrian bridge plus the Gateway Blvd (I-10) westbound Viscount entrance ramp will close July 23 so crews can progress on our Braided Ramp project
- GO 10, Mesa Park Interchange and Border West Expressway all have planned closures on I-10, it is best to avoid I-10 on the westside after 8:30 p.m. if at all possible.
- There are extended closures for Campbell and Kansas scheduled, an extended reconfiguration for Montana and a traffic switch planned for Alameda.
US 54 Widening and Illumination Project
Saturday, July 14 through Monday, July 16
3 a.m. to 5 a.m. (continuous)
- Complete closure of US 54 southbound between Hondo Pass Drive and Hercules Avenue
- Crews will be working on the pedestrian bridge, pouring concrete and then letting it cure
- Detour: Southbound traffic will exit US 54 southbound Hercules exit ramp, go through Hercules and Dyer intersections and back onto the freeway at Dyer-US 54
Loop 375 Border Highway
Saturday, July 21 to Monday, July 23
6 a.m. to 5 a.m. (continuous full closure)
- Eastbound and westbound from US 54 to Oregon Street
- Closure is needed for roadway work.
I-10
Thursday, July 26
9 p.m. to 5 a.m.
- Eastbound left lane from Schuster Avenue to Executive Center Boulevard
- Closure is needed for roadway repair.
Campbell Street
Monday, July 16 to Monday, Aug. 6
9 p.m. to 4 p.m. (continuous full closure)
- From Cesar Chavez to 7th Street
- Closure is needed for roadway work
Kansas Street
Monday, July 16 to Monday, Aug. 6
9 p.m. to 4 p.m. (continuous full closure)
- From Cesar Chavez to 7th Street
- Closure is needed for roadway work
Montana/Mattox Traffic and Operation Improvements Project
Monday, July 23
9 p.m. to 5 a.m. (one night)
- Full closure of Montana (US 62/180) between Hawkins Boulevard and Rutherglen Street
- Crews will be setting barrier in the median
Tuesday, July 24 through Friday, August 3
Continuous new reconfiguration until further notice
- Montana (US 62/180) east will be reduced to two lanes between Hawkins Boulevard and Rutherglen Street
- Crews will be working on traffic signals and operation improvements in the area.
Alameda Reconstruction Project
Friday, July 20 (closure until further notice)
9 a.m. to 4 p.m.
- Alameda Avenue (SH 20) westbound lane closure between Gaspar Street and Walmart Supercenter intersection
- Alameda Avenue (SH 20) traffic will be channelized to a single lane in each direction, utilizing the newly constructed SH 20 eastbound lanes
- Alameda Avenue (SH 20) alternating eastbound and westbound closures as needed between Gaspar Street and Walmart Supercenter intersection
- Alameda Avenue (SH 20) northbound closure at Carnes Road until further notice
- Please follow the detour signs in place and expect traffic delays
- Closures are necessary for construction of proposed concrete paving of westbound travel lanes, outside curb intersections, driveways, sidewalk, placement of new drainage/waterline, storm sewer, signals and illuminations
Spalling Repair Project
Sunday, July 15 through Thursday, July 19
9 p.m. to 5 a.m. (nightly)
- I-10 eastbound at Paisano – three left lanes closed
- I-10 eastbound at Raynolds entrance ramp closed
- Crews will be repairing spalled concrete pavement (potholes) in the area
Mesa Park Project
Sunday, July 15 through Thursday, July 19
9 p.m. to 6 a.m. (nightly)
- Complete closure on I-10 eastbound at Executive
- Detour: Eastbound traffic will exit at the Executive exit ramp and re-enter at Downtown
Sunday, July 22 through Thursday, July 26
9 p.m. to 6 a.m. (nightly)
- Complete closure on I-10 Eastbound at Executive
- Detour: Eastbound traffic will exit at the Executive exit ramp and re-enter at Downtown
Westway Project Phase III
Monday, July 16 through Friday, July 20
9 a.m. to 4 p.m. (throughout the day)
- Complete closure on North Desert Boulevard between Anthony and Vinton
- Northbound Vinton entrance ramp to I-10 west will be closed
Tuesday, July 17 and Wednesday, July 18
9 p.m. to 5 a.m. (nightly)
- Complete closure on I-10 east and westbound at the Vinton overpass
- Crews will be hanging beams at the new turnaround bridge
West Area Project Closures | Border West Expressway Closures | East Area Project Closures | GO 10 Closures
I-10 Eastbound
|
Overnight
Sunday, July 15 through Thursday, July 19
9 p.m. each night to 6 a.m. each following morning |
· I-10 Eastbound will close completely at the North Mesa Street overpass.
Detour: Motorists will be detoured onto North Mesa Street (SH 20) and will be able to re-enter I-10 Eastbound from the downtown Wyoming entrance ramp.
· The Sunland Park Drive overpass will close completely in both directions. · The Resler Drive flyover ramp to I-10 Eastbound will close. · Crockett Street access to Paisano Drive (US 85) will close. · I-10 Eastbound entrance ramp will close completely at Paisano Drive (US 85). · The Sunland Park flyover ramp to I-10 Eastbound will close.
Crews will be setting bridge beams and installing signage for the Sunland overpass. |
North Mesa | Overnight
Tuesday, July 17 through Wednesday, July 18
9 p.m. each night to 6 a.m. each following morning
|
Crews will be installing storm drain. |